HARRISON US 59 (0062-07-103)
Items: 32
County: HARRISON
Length: N/A
Highway: US 59
District: ATLANTA
Control Number: 0062-07-103
DBE Goal: 0.0%
Project: STP 2B24(045)VRU
Guaranty: N/A
Time: 170 WORKING DAYS
Engineer's Estimate: $1,345,548.70
Date: 04/04/2024 (2 years ago)
Contract Number: N/A
Type: INSTALL ILLUMINATION
Mail/Deliver Bids To: N/A
CHRISTINA TROWLER
KENNETH BURNS
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,345,548.70 | |||
| $1,254,209.20 |
-6.79%
-$91,339.50
|
|||
| $1,472,897.60 |
9.46%
$127,348.90
|
17.44%
$218,688.40
|
||
| $1,488,828.00 |
10.65%
$143,279.30
|
18.71%
$234,618.80
|
-1.08%
-$15,930.40
|
E
Engineer's Estimate
$1,345,548.70
1
Awarded
$1,254,209.20
Over/Under Est:
-6.79%
-$91,339.50
$1,472,897.60
Over/Under Est:
9.46%
$127,348.90
Amt Left:
17.44%
$218,688.40
$1,488,828.00
Over/Under Est:
10.65%
$143,279.30
Amt Left:
18.71%
$234,618.80
Delta:
-1.08%
-$15,930.40
| Subcontractor | Percentage | Amount |
|---|---|---|
| SAFETEX,INC. | 3.69% | $46,280.32 |
| Total: | 3.69% | $46,280.32 |
Bid Items & Bid Tabulations
32
Total
0 of 32