Show Job Controls
Bid Cobra

HARRIS SH0249 (6465-10-001)

Items: 14

County: HARRIS
Length: 0.0100 MILES
Highway: SH0249
District: HOUSTON
Control Number: 6465-10-001
DBE Goal: N/A
Project: RMC - 646510001
Guaranty: $11,000.00
Time: 180 W
Engineer's Estimate: $571,547.40
Date: 11/26/2024 (1 year ago)
Contract Number: 11241202
Type: FULL DEPTH CONCRETE REPAIR
Project ID: A00207983
Project Description: FULL DEPTH REPAIR AND PAVEMENT MARKINGS ON SH 249 SOUTHBOUND FRONTAGE ROAD
Mail/Deliver Bids To: N/A
REGINALD PHIPPS
BRITTAIN HUGHES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$571,547.40
Over/Under Est: -39.6% -$226,320.10
$447,887.47
Over/Under Est: -21.64% -$123,659.93
Amt Left: 29.74% $102,660.17
$488,560.00
Over/Under Est: -14.52% -$82,987.40
Amt Left: 41.52% $143,332.70
Delta: -9.08% -$40,672.53
Over/Under Est: -6.79% -$38,834.90
Amt Left: 54.31% $187,485.20
Delta: -9.04% -$44,152.50

Bid Items & Bid Tabulations

14 Total 0 of 14
HARRIS  |  SH0249  |  HOUSTON  |  6465-10-001  |  11/26/2024  |  $571,547.40  |  RMC - 646510001  |  FULL DEPTH CONC REPAIR  |  180 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
FORDE CONSTRUCTION COMPANY, INC.
MC2 CIVIL, LLC
RHINO EQUITY, LLC
B & MS CONSTRUCTION, INC.
D-GR HMA TY-F PG64-22
TON 69.000 $160.000 $195.000 $140.000 $450.000 $600.000
FULL - DEPTH REPAIR CRCP (10")
CY 278.000 $1,500.000 $1,000.000 $1,300.000 $1,200.000 $1,285.000
MOBILIZATION
LS 1.000 $46,383.400 $21,000.000 $44,000.010 $50,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $100.000 $1,500.000 $900.000 $3,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 26.000 $200.000 $200.000 $150.000 $300.000 $290.000
TMA (STATIONARY)
DAY 120.000 $400.000 $150.000 $5.000 $240.000 $285.000
TMA (MOBILE OPERATION)
DAY 6.000 $450.000 $150.000 $500.000 $350.000 $325.000
CONC CURB (MONO) (TY II)
LF 250.000 $40.000 $20.000 $50.000 $50.000 $65.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 60.000 $6.000 $12.000 $15.000 $70.000 $15.000
PAVEMENT SLER 6"
LF 120.000 $2.000 $12.000 $15.000 $40.000 $6.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 60.000 $6.000 $12.000 $15.000 $80.000 $5.500
REFL PAV MRKR TY II-C-R
EA 3.000 $20.000 $60.000 $75.000 $10.000 $35.000
PAV SURF PREP FOR MRK (6")
LF 120.000 $1.200 $0.100 $0.020 $20.000 $8.000
PAV SURF PREP FOR MRK (RPM)
EA 3.000 $20.000 $0.100 $0.020 $360.000 $42.500
Totals: $571,547.400 $345,227.300 $447,887.470 $488,560.000 $532,712.500