HARRIS IH0069 (6457-09-001)

Items: 69

County: HARRIS
Length: N/A
Highway: IH0069
District: HOUSTON
Control Number: 6457-09-001
DBE Goal: 0.0%
Project: RMC - 645709001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $2,016,708.60
Date: 06/06/2024 (2 years ago) Changed
Contract Number: N/A
Type: SWEEPING AND DEBRIS REMOVAL
Mail/Deliver Bids To: N/A
REGINALD PHIPPS
BRITTAIN HUGHES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$2,016,708.60
$1,690,158.00
Over/Under Est: -16.19% -$326,550.60
Over/Under Est: -7.3% -$147,200.60
Amt Left: 10.61% $179,350.00
Over/Under Est: -5.93% -$119,668.60
Amt Left: 12.24% $206,882.00
Delta: -1.47% -$27,532.00
Over/Under Est: 3.41% $68,683.40
Amt Left: 23.38% $395,234.00
Delta: -9.93% -$188,352.00

Bid Items & Bid Tabulations

69 Total 0 of 69
HARRIS  |  IH0069  |  HOUSTON  |  6457-09-001  |  06/06/2024  |  $2,016,708.60  |  RMC - 645709001  |  SWEEPING AND DEBRIS RMVL  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DIGG COMMERCIAL, LLC
SWEEPING CORPORATION OF AMERICA, LLC
HAZMAT INTERNATIONAL, INC.
PROFESSIONAL TRAFFIC CONTROL LLC
MOBILIZATION (CALLOUT)
EA 60.000 $100.500 $1.000 $100.000 $1,200.000 $1.000
MOBILIZATION (EMERGENCY)
EA 8.000 $525.000 $1.000 $250.000 $2,500.000 $500.000
DEBRIS REMOVAL (SPOT DEBRIS)
MI 20.000 $58.320 $500.000 $25.000 $100.000 $250.000
DEBRIS-CNTR MEDIANS/MAINLANES-AREA (1)
CYC 24.000 $810.000 $500.000 $481.500 $450.000 $1,000.000
DEBRIS-CNTR MEDIANS/MAINLANES-AREA (3)
CYC 24.000 $830.000 $500.000 $374.500 $350.000 $1,000.000
DEBRIS-CNTR MEDIANS/MAINLANES-AREA (5)
CYC 24.000 $1,260.000 $500.000 $749.000 $700.000 $1,250.000
DEBRIS-CNTR MEDIANS/MAINLANES-AREA (18)
CYC 24.000 $950.000 $500.000 $535.000 $500.000 $1,000.000
DEBRIS-CNTR MEDIANS/MAINLANES-AREA (20)
CYC 24.000 $775.000 $250.000 $481.500 $300.000 $450.000
DEBRIS-DIRECT CONNECTOR - AREA (9)
CYC 24.000 $190.000 $500.000 $53.500 $50.000 $225.000
DEBRIS-DIRECT CONNECTOR - AREA (10)
CYC 24.000 $320.000 $250.000 $160.500 $150.000 $225.000
DEBRIS-DIRECT CONNECTOR - AREA (19)
CYC 24.000 $575.000 $500.000 $107.000 $100.000 $75.000
DEBRIS-DIRECT CONNECTOR - AREA (20)
CYC 24.000 $550.000 $450.000 $160.500 $150.000 $225.000
DEBRIS-CNTR MEDIANS/MAINLANES-AREA (21)
CYC 48.000 $950.000 $250.000 $1,177.000 $700.000 $700.000
CLEANING / SWEEPING (SPOT)
MI 20.000 $240.000 $200.000 $300.000 $100.000 $150.000
CLEANING / SWEEPING (HANDWORK)
SY 120,000.000 $0.230 $0.100 $0.050 $0.500 $0.050
CLEAN / SWEEP - CENTER MEDIAN - AREA(1)
CYC 48.000 $1,566.000 $500.000 $1,116.000 $900.000 $1,687.500
CLEAN / SWEEP - CENTER MEDIAN - AREA(3)
CYC 48.000 $1,218.000 $250.000 $868.000 $700.000 $1,575.000
CLEAN / SWEEP - CENTER MEDIAN - AREA(5)
CYC 48.000 $2,436.000 $500.000 $1,736.000 $1,000.000 $2,400.000
CLEAN / SWEEP - CENTER MEDIAN - AREA(7)
CYC 12.000 $367.250 $500.000 $496.000 $225.000 $169.000
CLEAN / SWEEP - CENTER MEDIAN - AREA(8)
CYC 12.000 $499.500 $500.000 $372.000 $450.000 $338.000
CLEAN / SWEEP - CENTER MEDIAN-AREA (11)
CYC 24.000 $1,130.500 $500.000 $868.000 $900.000 $315.000
CLEAN / SWEEP - CENTER MEDIAN-AREA (12)
CYC 24.000 $393.750 $500.000 $372.000 $450.000 $135.000
CLEAN / SWEEP - CENTER MEDIAN-AREA (13)
CYC 12.000 $2,000.000 $500.000 $1,984.000 $1,000.000 $1,200.000
CLEAN / SWEEP - CENTER MEDIAN-AREA (14)
CYC 12.000 $1,375.000 $500.000 $1,240.000 $900.000 $1,875.000
CLEAN / SWEEP - CENTER MEDIAN-AREA (15)
CYC 12.000 $457.500 $500.000 $372.000 $450.000 $563.000
CLEAN / SWEEP - CENTER MEDIAN-AREA (16)
CYC 12.000 $725.000 $500.000 $1,240.000 $450.000 $338.000
CLEAN / SWEEP - CENTER MEDIAN-AREA (18)
CYC 48.000 $1,375.000 $500.000 $1,240.000 $900.000 $2,250.000
CLEAN / SWEEP - CENTER MEDIAN-AREA (20)
CYC 48.000 $825.000 $500.000 $1,116.000 $900.000 $1,125.000
CLEAN / SWEEP-OUTSIDE MAIN LANE-AREA(1)
CYC 48.000 $1,237.500 $500.000 $1,116.000 $900.000 $1,687.500
CLEAN / SWEEP-OUTSIDE MAIN LANE-AREA(3)
CYC 48.000 $1,400.000 $500.000 $868.000 $900.000 $1,575.000
CLEAN / SWEEP-OUTSIDE MAIN LANE-AREA(5)
CYC 48.000 $1,925.000 $500.000 $1,736.000 $900.000 $2,000.000
CLEAN / SWEEP-OUTSIDE MAIN LANE-AREA(7)
CYC 12.000 $312.500 $500.000 $496.000 $225.000 $169.000
CLEAN / SWEEP-OUTSIDE MAIN LANE-AREA(8)
CYC 12.000 $375.000 $500.000 $372.000 $450.000 $338.000
CLEAN /SWEEP-OUTSIDE MAIN LANE-AREA(11)
CYC 24.000 $700.000 $500.000 $868.000 $900.000 $315.000
CLEAN /SWEEP-OUTSIDE MAIN LANE-AREA(12)
CYC 24.000 $318.750 $500.000 $372.000 $450.000 $135.000
CLEAN /SWEEP-OUTSIDE MAIN LANE-AREA(13)
CYC 12.000 $2,000.000 $500.000 $1,984.000 $900.000 $1,200.000
CLEAN /SWEEP-OUTSIDE MAIN LANE-AREA(14)
CYC 12.000 $1,375.000 $250.000 $1,240.000 $900.000 $1,875.000
CLEAN /SWEEP-OUTSIDE MAIN LANE-AREA(15)
CYC 12.000 $457.500 $250.000 $372.000 $450.000 $563.000
CLEAN /SWEEP-OUTSIDE MAIN LANE-AREA(16)
CYC 12.000 $725.000 $250.000 $1,240.000 $450.000 $338.000
CLEAN /SWEEP-OUTSIDE MAIN LANE-AREA(17)
CYC 12.000 $175.000 $250.000 $496.000 $150.000 $75.000
CLEAN /SWEEP-OUTSIDE MAIN LANE-AREA(18)
CYC 48.000 $1,375.000 $250.000 $1,240.000 $900.000 $2,250.000
CLEAN /SWEEP-OUTSIDE MAIN LANE-AREA(20)
CYC 48.000 $915.000 $250.000 $1,116.000 $800.000 $1,125.000
CLEAN / SWEEP - FRONTAGE ROAD - AREA(2)
CYC 24.000 $2,960.000 $250.000 $3,968.000 $5,000.000 $240.000
CLEAN / SWEEP - FRONTAGE ROAD - AREA(3)
CYC 24.000 $700.000 $250.000 $868.000 $900.000 $315.000
CLEAN / SWEEP - FRONTAGE ROAD - AREA(6)
CYC 24.000 $1,275.000 $250.000 $1,860.000 $1,400.000 $540.000
CLEAN / SWEEP - FRONTAGE ROAD -AREA(18)
CYC 24.000 $1,400.000 $250.000 $1,240.000 $900.000 $450.000
CLEAN / SWEEP - FRONTAGE ROAD -AREA(20)
CYC 24.000 $600.000 $250.000 $1,116.000 $800.000 $270.000
CLEAN / SWEEP - (ENTR /EXT RMP)(AREA 1)
CYC 24.000 $900.000 $250.000 $1,116.000 $900.000 $270.000
CLEAN / SWEEP - (ENTR /EXT RMP)(AREA 3)
CYC 24.000 $875.000 $250.000 $868.000 $900.000 $405.000
CLEAN / SWEEP - (ENTR /EXT RMP)(AREA 4)
CYC 24.000 $800.000 $250.000 $992.000 $900.000 $315.000
CLEAN / SWEEP - (ENTR/EXT RMP)(AREA 18)
CYC 24.000 $1,250.000 $250.000 $1,240.000 $900.000 $600.000
CLEAN / SWEEP - (ENTR/EXT RMP)(AREA 20)
CYC 24.000 $600.000 $250.000 $1,116.000 $900.000 $750.000
CLEAN/SWEEPING-DIRECT CONNECT-AREA(9)
CYC 48.000 $152.500 $250.000 $124.000 $200.000 $250.000
CLEAN/SWEEPING-DIRECT CONNECT-AREA(10
CYC 48.000 $380.000 $250.000 $248.000 $600.000 $750.000
CLEAN/SWEEPING-DIRECT CONNECT-AREA(19)
CYC 24.000 $220.750 $250.000 $248.000 $400.000 $300.000
CLEAN/SWEEPING-DIRECT CONNECT-AREA(20)
CYC 48.000 $600.000 $250.000 $372.000 $600.000 $750.000
CLEAN/SWEEP-CENTER MEDIAN-AREA (21)
CYC 24.000 $2,135.000 $250.000 $1,736.000 $1,400.000 $2,400.000
CLEAN/SWEEP-CENTER MEDIAN-AREA (22)
CYC 24.000 $800.000 $250.000 $992.000 $900.000 $600.000
CLEAN/SWEEP-CENTER MEDIAN-AREA (24)
CYC 24.000 $800.000 $250.000 $992.000 $900.000 $600.000
CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA(21)
CYC 24.000 $2,135.000 $250.000 $1,736.000 $1,400.000 $2,400.000
CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA(22)
CYC 24.000 $1,000.000 $250.000 $992.000 $900.000 $600.000
CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA(23)
CYC 24.000 $950.000 $250.000 $1,736.000 $1,400.000 $360.000
CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA(24)
CYC 24.000 $800.000 $250.000 $992.000 $900.000 $360.000
CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA(25)
CYC 12.000 $1,000.000 $250.000 $992.000 $900.000 $630.000
CLEAN/SWEEP-FRONTAGE ROAD - AREA (21)
CYC 24.000 $1,000.000 $250.000 $1,736.000 $1,800.000 $630.000
CLEAN/SWEEP - (ENTR/EXT RMP) (AREA 21)
CYC 24.000 $1,400.000 $250.000 $1,736.000 $1,800.000 $630.000
MAKE READY: DRAIN SLOTS, BARRIER SLOTS
LS 1.000 $33,000.000 $250.000 $20,000.000 $25,000.000 $10,000.000
TMA (STATIONARY)
DAY 40.000 $101.280 $1.000 $1.000 $1.000 $1.000
TMA (MOBILE OPERATION)
HR 6,000.000 $42.500 $180.000 $35.000 $60.000 $85.000
Totals: $2,016,708.600 $1,690,158.000 $1,869,508.000 $1,897,040.000 $2,085,392.000