HARRIS IH0010 (6366-19-001)

Items: 48

County: HARRIS
Length: N/A
Highway: IH0010
District: HOUSTON
Control Number: 6366-19-001
DBE Goal: N/A
Project: RMC - 636619001
Guaranty: N/A
Time: 40 W
Engineer's Estimate: $701,916.18
Date: 11/05/2020 (5 years ago)
Contract Number: N/A
Type: MILLING AND OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$701,916.18
$783,387.50
Over/Under Est: 11.61% $81,471.32
Over/Under Est: 15.23% $106,893.08
Amt Left: 3.25% $25,421.76
Over/Under Est: 22.52% $158,048.00
Amt Left: 9.78% $76,576.68
Delta: -6.32% -$51,154.92
Over/Under Est: 42.24% $296,483.40
Amt Left: 27.45% $215,012.08
Delta: -16.10% -$138,435.40

Bid Items & Bid Tabulations

48 Total 0 of 48
HARRIS  |  IH0010  |  HOUSTON  |  6366-19-001  |  11/05/2020  |  $701,916.18  |  RMC - 636619001  |  MILLING AND OVERLAY  |  40 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANGEL BROTHERS HOLDINGS CORP.
B & MS CONSTRUCTION, INC.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
FORDE CONSTRUCTION COMPANY, INC.
AGGR(TY-PB GR-4 SAC-B)
CY 200.620 $93.560 $180.000 $145.000 $98.000 $280.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 10,953.600 $4.070 $2.950 $5.000 $2.900 $3.400
TOM (ASPHALT) PG 76-22
TON 228.400 $147.080 $133.000 $121.100 $147.000 $160.000
TOM-C (AGGREGATE) SAC-A
TON 1,874.720 $114.690 $133.000 $115.000 $147.000 $160.000
TOM - F (AGGREGATE) SAC - A
TON 1,245.800 $129.350 $133.000 $110.800 $147.000 $160.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 200.000 $72.280 $73.000 $80.500 $89.000 $175.000
PLANE ASPH CONC PAV(0" TO 3")
SY 888.000 $1.950 $10.000 $11.500 $2.900 $9.000
PLANE ASPH CONC PAV (3")
SY 26,080.000 $1.950 $2.500 $5.400 $2.900 $2.500
FULL - DEPTH REPAIR CRCP (9")
SY 300.000 $166.630 $310.000 $272.550 $455.000 $415.000
MOBILIZATION
LS 1.000 $47,796.000 $30,000.000 $25,000.000 $35,000.000 $33,900.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $8,068.160 $3,500.000 $3,375.250 $4,000.000 $12,500.000
CONC CURB (TY II)
LF 100.000 $18.460 $40.000 $41.000 $65.000 $65.750
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 2,560.000 $0.290 $0.300 $0.500 $0.250 $0.250
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 1,658.000 $0.320 $0.300 $0.500 $0.250 $0.250
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,177.000 $0.600 $0.650 $0.860 $0.500 $0.500
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 6.000 $61.910 $72.000 $95.000 $60.000 $60.000
WK ZN PAV MRK NON-REMOV (W)(DBL ARW)
EA 2.000 $107.830 $94.000 $115.000 $75.000 $75.000
WK ZN PAV MRK NON-REMOV (W)(UTURN ARW)
EA 2.000 $226.400 $94.000 $115.000 $75.000 $75.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 8.000 $67.590 $72.000 $115.000 $60.000 $60.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 1,097.000 $0.320 $0.280 $0.450 $0.250 $0.250
WK ZN PAV MRK NON-REMOV (Y)8"(SLD)
LF 690.000 $1.000 $0.700 $0.790 $0.500 $0.500
WK ZN PAV MRK NON-REMOV (Y)12"(SLD)
LF 326.000 $0.940 $0.850 $1.100 $1.250 $1.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,177.000 $0.840 $1.100 $0.890 $0.850 $0.850
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 690.000 $1.050 $1.250 $1.220 $0.850 $0.850
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 326.000 $2.580 $3.000 $3.300 $3.000 $3.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 2,560.000 $0.780 $0.700 $0.900 $0.750 $0.750
PAVEMENT SEALER 6"
LF 7,875.000 $0.150 $0.030 $0.090 $0.250 $0.250
PAVEMENT SEALER 8"
LF 1,867.000 $1.070 $0.040 $0.120 $0.500 $0.500
PAVEMENT SEALER 12"
LF 326.000 $1.290 $0.070 $0.210 $1.000 $1.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 2,560.000 $0.560 $0.660 $0.690 $0.500 $0.500
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 1,658.000 $0.500 $0.660 $0.530 $0.500 $0.500
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 1,097.000 $0.520 $0.660 $0.520 $0.500 $0.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 6.000 $214.480 $266.000 $234.600 $225.000 $225.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 2.000 $373.680 $310.000 $407.100 $300.000 $300.000
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 2.000 $352.300 $385.000 $417.450 $325.000 $325.000
PREFAB PAV MRK TY C (W) (WORD)
EA 8.000 $268.110 $310.000 $311.650 $260.000 $260.000
REFL PAV MRKR TY I-A
EA 30.000 $3.100 $4.500 $3.450 $5.000 $5.000
REFL PAV MRKR TY II-C-R
EA 154.000 $3.320 $6.000 $3.340 $5.000 $5.000
PAV SURF PREP FOR MRK (6")
LF 7,875.000 $0.040 $0.010 $0.020 $0.010 $0.010
PAV SURF PREP FOR MRK (8")
LF 1,867.000 $0.140 $0.010 $0.030 $0.020 $0.020
PAV SURF PREP FOR MRK (12")
LF 326.000 $0.400 $0.010 $0.130 $0.500 $0.500
PAV SURF PREP FOR MRK (ARROW)
EA 6.000 $15.390 $0.010 $9.890 $10.000 $10.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 2.000 $20.170 $0.010 $11.500 $10.000 $10.000
PAV SURF PREP FOR MRK (UTURN ARR)
EA 2.000 $16.670 $0.010 $16.680 $10.000 $10.000
PAV SURF PREP FOR MRK (WORD)
EA 8.000 $21.000 $0.010 $16.100 $10.000 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 50.000 $66.290 $60.000 $188.600 $50.000 $175.000
TMA (STATIONARY)
DAY 50.000 $204.620 $260.000 $155.250 $50.000 $480.000
TMA (MOBILE OPERATION)
HR 200.000 $50.200 $55.000 $95.450 $45.000 $90.000
Totals: $701,916.178 $783,387.500 $808,809.260 $859,964.180 $998,399.580