HARRIS SH 99 (3510-05-045)

Items: 26

County: HARRIS
Length: N/A
Highway: SH 99
District: HOUSTON
Control Number: 3510-05-045
DBE Goal: N/A
Project: C 3510-5-45
Guaranty: N/A
Time: 210 WORKING DAYS
Engineer's Estimate: $4,059,577.25
Date: 08/06/2019 (6 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$4,059,577.25
$3,484,500.00
Over/Under Est: -14.17% -$575,077.25
Over/Under Est: -12.38% -$502,563.68
Amt Left: 2.08% $72,513.57
$3,803,764.00
Over/Under Est: -6.3% -$255,813.25
Amt Left: 9.16% $319,264.00
Delta: -6.94% -$246,750.43
Over/Under Est: -5.01% -$203,464.88
Amt Left: 10.66% $371,612.37
Delta: -1.38% -$52,348.37

Bid Items & Bid Tabulations

26 Total 0 of 26
HARRIS  |  SH 99  |  HOUSTON  |  3510-05-045  |  08/06/2019  |  $4,059,577.25  |  C 3510-5-45  |  LANDSCAPE DEVELOPMENT  |  210 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
APEX LANDSCAPE & IRRIGATION, LLC
CENTRAL NORTH CONSTRUCTION, LLC
TEXAS WALL & LANDSCAPE
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
PREP ROW (TREE) (2" TO 12" DIA)
EA 1.000 $500.000 $500.000 $10,000.000 $4,500.000 $2,500.000
FURNISHING AND PLACING TOPSOIL
CY 345.000 $30.000 $40.000 $50.000 $60.000 $58.439
EROSION CONTROL COMPOST
CY 28,628.000 $27.000 $17.250 $18.700 $20.000 $23.945
GENERAL USE COMPOST
CY 14,235.000 $29.000 $20.250 $19.000 $20.000 $23.228
FERTILIZER
AC 22.500 $650.000 $1,000.000 $750.000 $900.000 $1,577.061
VEGETATIVE WATERING
MG 441.000 $25.000 $0.100 $18.000 $65.000 $34.745
WILDFLOWER SEEDING
AC 22.500 $1,200.000 $595.000 $1,250.000 $2,600.000 $1,146.953
WILDFLOWER SEEDING (MIX 1)
AC 51.000 $750.000 $315.000 $1,250.000 $2,600.000 $917.141
PLANT MATERIAL (3-GAL)
EA 5,549.000 $12.500 $17.250 $10.900 $20.500 $12.208
MULCH
CY 9,993.000 $12.000 $12.000 $17.000 $24.000 $17.754
PLANT MATERIAL (5 GAL) (TREE)
EA 25,886.000 $15.000 $20.250 $12.300 $21.000 $13.850
PLANT MATERIAL (15 GAL) (TREE)
EA 5,534.000 $100.000 $91.000 $64.700 $70.000 $92.682
PLANT MATERIAL (3 GAL) (SHRUB)
EA 228.000 $15.000 $16.000 $11.600 $20.500 $9.904
PLANT BED PREP (TYPE II)
SY 254,812.000 $0.800 $0.300 $0.270 $0.900 $0.329
PLANT BED PREP (TYPE III)
SY 904.000 $2.000 $1.550 $0.500 $10.000 $0.321
PLANT MAINTENANCE
MO 18.000 $25,000.000 $20,000.000 $18,500.000 $8,000.000 $34,310.036
PLANT MAINTENANCE
CYC 11.000 $5,500.000 $18,500.000 $52,500.000 $7,500.000 $14,662.757
MOBILIZATION
LS 1.000 $381,300.000 $341,521.050 $430,000.000 $375,000.000 $385,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $5,000.000 $2,850.000 $1,675.800 $5,500.000 $806.452
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 15,000.000 $6.000 $1.250 $3.200 $4.500 $3.387
BIODEG EROSN CONT LOGS (REMOVE)
LF 15,000.000 $2.000 $0.250 $0.280 $2.000 $0.323
LANDSCAPE SOIL AMENDMENT (TYPE I)
SY 264,328.000 $0.500 $0.350 $0.130 $0.200 $0.146
LANDSCAPE SOIL AMENDMENT (TYPE II)
SY 264,328.000 $0.300 $0.300 $0.125 $0.090 $0.132
LANDSCAPE SOIL AMENDMENT (TYPE III)
SY 36,969.000 $1.500 $1.150 $0.810 $2.750 $0.803
LANDSCAPE SOIL AMENDMENT (TYPE IV)
SY 184,845.000 $0.350 $0.650 $0.230 $1.000 $0.423
LANDSCAPE SOIL AMENDMENT (TYPE V)
SY 37,197.000 $0.500 $0.250 $1.950 $0.390 $2.118
Totals: $4,059,577.250 $3,484,500.000 $3,557,013.570 $3,803,764.000 $3,856,112.467