HARRIS SL 8 (3256-02-121)
Items: 66
County: HARRIS
Length: 1.8340 MILES
Highway: SL 8
District: HOUSTON
Control Number: 3256-02-121
DBE Goal: 0.0%
Project: F 2026(604)
Guaranty: $46,000.00
Time: 56 WORKING DAYS
Engineer's Estimate: $2,286,187.03
Date: 05/07/2026 (4 weeks ago)
Contract Number: 5263221
Type: RESURFACE ROADWAY
Project ID: A00215811
Contract Type: Federal
Project Description: BASE REPAIR, SEAL COAT, 2-INCH SP D OVERLAY, AND PAVEMENT MARKINGS (FRONTAGE ROADS)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
PHILLIP GARLIN
NYEMB NYEMB
HARRIS SL 8 (3256-02-121)
Project Name: N/A
Project: F 2026(604)
Length: 1.8340 MILES
Project Type: CONSTRUCTION
Limits From: WEST OF HARDY ST.
Limits To: 0.2 MI EAST OF ALDINE WESTFIELD RD.
Project Description: BASE REPAIR, SEAL COAT, 2-INCH SP D OVERLAY, AND PAVEMENT MARKINGS (FRONTAGE ROADS)
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,286,187.03 | |||
| $2,254,485.54 |
-1.39%
-$31,701.49
|
|||
| $2,276,558.15 |
-0.42%
-$9,628.88
|
0.98%
$22,072.61
|
||
| $2,758,532.20 |
20.66%
$472,345.17
|
22.36%
$504,046.66
|
-21.17%
-$481,974.05
|
|
| $3,212,944.97 |
40.54%
$926,757.94
|
42.51%
$958,459.43
|
-16.47%
-$454,412.77
|
|
| $3,317,777.65 |
45.12%
$1,031,590.62
|
47.16%
$1,063,292.11
|
-3.26%
-$104,832.68
|
E
Engineer's Estimate
$2,286,187.03
1
Awarded
$2,254,485.54
Over/Under Est:
-1.39%
-$31,701.49
$2,276,558.15
Over/Under Est:
-0.42%
-$9,628.88
Amt Left:
0.98%
$22,072.61
$2,758,532.20
Over/Under Est:
20.66%
$472,345.17
Amt Left:
22.36%
$504,046.66
Delta:
-21.17%
-$481,974.05
$3,212,944.97
Over/Under Est:
40.54%
$926,757.94
Amt Left:
42.51%
$958,459.43
Delta:
-16.47%
-$454,412.77
$3,317,777.65
Over/Under Est:
45.12%
$1,031,590.62
Amt Left:
47.16%
$1,063,292.11
Delta:
-3.26%
-$104,832.68
Bid Items & Bid Tabulations
66
Total
0 of 66
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $12,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| Total: | $16,000.00 |