Show Job Controls
Bid Cobra

HARRIS SL 8 (3256-02-098)

Items: 65

County: HARRIS
Length: N/A
Highway: SL 8
District: HOUSTON
Control Number: 3256-02-098
DBE Goal: N/A
Project: NH 2020(369)
Guaranty: N/A
Time: 79 WORKING DAYS
Engineer's Estimate: $600,815.89
Date: 12/04/2019 (6 years ago)
Contract Number: N/A
Type: EB RAMP & FRONTAGE RD WIDENING AND STRIPING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$600,815.89
Over/Under Est: 22.22% $133,483.21
Over/Under Est: 32.62% $196,013.49
Amt Left: 8.52% $62,530.28
Over/Under Est: 48.57% $291,840.11
Amt Left: 21.57% $158,356.90
Delta: -12.03% -$95,826.62
Over/Under Est: 89.22% $536,032.23
Amt Left: 54.82% $402,549.02
Delta: -27.36% -$244,192.12
$1,531,099.00
Over/Under Est: 154.84% $930,283.11
Amt Left: 108.51% $796,799.90
Delta: -34.68% -$394,250.88

Bid Items & Bid Tabulations

65 Total 0 of 65
HARRIS  |  SL 8  |  HOUSTON  |  3256-02-098  |  12/04/2019  |  $600,815.89  |  NH 2020(369)  |  EB RAMP & FRONTAGE RD WIDENING AND S...  |  79 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ARANDA BROTHERS CONSTRUCTION CO., INC.
TRIPLE B SERVICES LLP
MAIN LANE INDUSTRIES LTD.
RAGLE CONSTRUCTION, INC.
FNH CONSTRUCTION, LLC
PREPARING ROW
AC 1.000 $28,500.000 $7,541.000 $35,000.000 $10,000.000 $100,000.000 $65,000.000
REMOVING CONC (CURB)
LF 2,620.000 $3.460 $4.000 $2.000 $15.000 $5.000 $20.000
EXCAVATION (ROADWAY)
CY 1,299.000 $11.500 $9.000 $20.000 $30.000 $60.000 $20.000
FURNISHING AND PLACING TOPSOIL (4")
SY 386.000 $3.500 $8.000 $3.700 $3.000 $2.000 $6.000
BLOCK SODDING
SY 5,339.000 $3.000 $5.000 $4.000 $4.000 $5.500 $6.000
FERTILIZER
AC 2.000 $700.000 $1,322.000 $2,800.000 $1,250.000 $1,250.000 $2,500.000
VEGETATIVE WATERING
MG 40.000 $25.000 $40.000 $50.000 $30.000 $100.000 $100.000
CONC PVMT (CONT REINF)(FAST TRK)(12")
SY 3,350.000 $70.000 $80.000 $107.000 $115.000 $160.000 $150.000
TRENCH EXCAVATION PROTECTION
LF 60.000 $10.000 $1.000 $1.000 $1.000 $1.000 $10.000
RIPRAP (CONC)(4 IN)
CY 200.000 $320.000 $385.000 $370.000 $350.000 $50.000 $550.000
RIPRAP (MOW STRIP)(4 IN)
CY 2.000 $550.000 $500.000 $950.000 $1,600.000 $1,000.000 $550.000
RC PIPE (CL III)(24 IN)
LF 34.000 $80.000 $75.000 $180.000 $300.000 $140.000 $200.000
INLET (COMPL)(TY AAD)
EA 4.000 $5,000.000 $2,750.000 $5,350.000 $5,500.000 $5,500.000 $6,500.000
MOBILIZATION
LS 1.000 $60,000.000 $50,000.000 $45,000.000 $80,000.000 $90,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $7,500.000 $1,649.000 $2,000.000 $10,000.000 $25,500.000 $8,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 190.000 $35.000 $30.000 $35.000 $25.000 $25.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 190.000 $13.000 $5.000 $9.500 $5.000 $10.000 $20.000
CONSTRUCTION PERIMETER FENCE
LF 2,770.000 $2.500 $7.000 $4.800 $5.000 $5.000 $20.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 262.000 $8.000 $12.000 $8.000 $10.000 $5.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 262.000 $2.500 $5.000 $5.000 $2.000 $1.000 $12.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 3,400.000 $8.000 $20.000 $16.000 $16.000 $9.000 $30.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 830.000 $5.000 $15.000 $11.000 $8.000 $3.000 $20.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 3,400.000 $8.000 $15.000 $11.000 $9.000 $9.000 $20.000
CONC CURB (MONO) (TY II)
LF 2,620.000 $4.000 $7.250 $5.000 $6.000 $6.000 $35.000
MTL W-BEAM GD FEN (TIM POST)
LF 194.000 $23.000 $35.000 $35.000 $28.000 $37.500 $25.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,800.000 $2,750.000 $3,500.000 $3,000.000 $3,750.000 $3,000.000
RIDE PAYMENT ADJUSTMENT (ITEM 360)
DOL 1.000 $1.000 $15,000.000 $500.000 $1.000 $1.000 $50,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 2.000 $500.000 $750.000 $625.000 $550.000 $335.440 $8,500.000
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND(BR)
EA 3.000 $80.000 $100.000 $85.000 $80.000 $40.720 $100.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 1,821.000 $0.800 $1.150 $1.130 $1.000 $0.980 $3.000
WK ZN PAV MRK REMOV (Y)8"(SLD)
LF 3,075.000 $0.850 $2.000 $1.740 $1.500 $1.500 $3.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 59.000 $6.000 $8.000 $8.000 $7.000 $7.000 $20.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 2.000 $120.000 $155.000 $171.000 $150.000 $150.000 $250.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 1.000 $200.000 $250.000 $228.000 $200.000 $200.000 $250.000
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 2.000 $190.000 $250.000 $290.000 $250.000 $250.000 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 4.000 $140.000 $250.000 $200.000 $175.000 $175.000 $250.000
PAVEMENT SEALER 24"
LF 59.000 $1.150 $0.500 $2.300 $0.500 $0.250 $4.000
PAVEMENT SEALER (ARROW)
EA 2.000 $30.000 $11.000 $11.600 $10.000 $10.000 $150.000
PAVEMENT SEALER (WORD)
EA 4.000 $28.000 $11.000 $11.600 $10.000 $10.000 $150.000
PAVEMENT SEALER (DBL ARROW)
EA 1.000 $35.000 $11.000 $11.600 $10.000 $10.000 $150.000
PAVEMENT SEALER (UTURN ARROW)
EA 2.000 $43.000 $11.000 $11.600 $10.000 $10.000 $150.000
REFL PAV MRKR TY II-C-R
EA 146.000 $4.100 $6.000 $7.000 $6.000 $6.000 $15.000
ELIM EXT PAV MRK & MRKS (6")
LF 1,532.000 $0.300 $1.000 $0.460 $0.500 $0.400 $3.000
ELIM EXT PAV MRK & MRKS (8")
LF 1,559.000 $0.500 $1.000 $0.580 $0.500 $0.500 $3.000
ELIM EXT PAV MRK & MRKS (24")
LF 59.000 $2.150 $3.000 $3.500 $3.000 $3.000 $3.000
ELIM EXT PAV MRK & MRKS (ARROW)
EA 4.000 $32.000 $50.000 $40.500 $35.000 $35.000 $250.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 6.000 $42.000 $50.000 $52.000 $45.000 $45.000 $250.000
ELIM EXT PAV MRK & MRKS (UTURN ARROW)
EA 2.000 $72.000 $50.000 $52.000 $45.000 $45.000 $250.000
PAV SURF PREP FOR MRK (6")
LF 4,356.000 $0.050 $0.050 $0.060 $0.050 $0.050 $2.000
PAV SURF PREP FOR MRK (8")
LF 1,559.000 $0.080 $0.050 $0.090 $0.100 $0.080 $3.000
PAV SURF PREP FOR MRK (12")
LF 116.000 $0.200 $0.050 $0.140 $0.150 $0.120 $3.000
PAV SURF PREP FOR MRK (24")
LF 59.000 $0.800 $0.050 $0.290 $0.500 $0.250 $3.000
PAV SURF PREP FOR MRK (ARROW)
EA 4.000 $9.000 $0.150 $5.790 $5.000 $5.000 $250.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 1.000 $8.000 $0.150 $11.500 $10.000 $10.000 $250.000
PAV SURF PREP FOR MRK (UTURN ARR)
EA 2.000 $9.000 $0.150 $11.500 $10.000 $10.000 $250.000
PAV SURF PREP FOR MRK (WORD)
EA 4.000 $9.500 $0.150 $11.500 $10.000 $10.000 $250.000
PAV SURF PREP FOR MRK (RPM)
EA 146.000 $0.200 $0.150 $0.460 $0.400 $0.400 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 21.000 $40.000 $250.000 $140.000 $100.000 $46.160 $150.000
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 2,178.000 $0.640 $1.500 $0.870 $0.750 $0.750 $3.000
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 1,408.000 $1.000 $2.000 $1.450 $1.250 $1.250 $3.000
MULTIPOLYMER PAV MRK (Y)(8")(SLD)
LF 151.000 $1.000 $2.500 $1.750 $1.500 $1.500 $3.000
MULTIPOLYMER PAV MRK (Y)(12")(SLD)
LF 116.000 $2.600 $7.000 $3.500 $3.000 $3.000 $6.000
MULTIPOLYMER PAV MRK (BLK)(6")(BRK)
LF 2,178.000 $0.700 $1.550 $0.870 $0.750 $0.750 $3.000
TMA (STATIONARY)
DAY 8.000 $260.000 $450.000 $385.000 $250.000 $500.000 $550.000
TMA (MOBILE OPERATION)
HR 80.000 $30.000 $145.000 $90.000 $70.000 $80.000 $85.000
Totals: $600,815.890 $734,299.100 $796,829.380 $892,656.000 $1,136,848.120 $1,531,099.000