Show Job Controls
Bid Cobra

HARRIS SL 8 (3256-02-095)

Items: 100

County: HARRIS
Length: N/A
Highway: SL 8
District: HOUSTON
Control Number: 3256-02-095
DBE Goal: N/A
Project: NH 2018(461)
Guaranty: N/A
Time: 83 WORKING DAYS
Engineer's Estimate: $1,722,587.42
Date: 06/05/2019 (7 years ago)
Contract Number: N/A
Type: FRNTG RD PAV RPR W/ 2.5"TBCO,MRK & LP DETECT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$1,722,587.42
$2,046,085.22
Over/Under Est: 18.78% $323,497.80
Over/Under Est: 53.73% $925,540.45
Amt Left: 29.42% $602,042.65

Bid Items & Bid Tabulations

100 Total 0 of 100
HARRIS  |  SL 8  |  HOUSTON  |  3256-02-095  |  06/05/2019  |  $1,722,587.42  |  NH 2018(461)  |  FRNTG RD PAV RPR W/ 2.5"TBCO,MRK & L...  |  83 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANGEL BROTHERS HOLDINGS CORP.
DURWOOD GREENE CONSTRUCTION CO.
REMOVING CONC (RIPRAP)
SY 64.000 $20.000 $23.000 $40.000
REMOVING CONC (CURB)
LF 422.000 $6.000 $5.750 $15.000
REMOVING CONCRETE(MOW STRIP)
LF 138.000 $7.000 $10.000 $50.000
ASPH (A-R TYPE II OR III)
GAL 35,826.000 $3.600 $4.000 $4.000
AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B)
CY 653.000 $130.000 $142.000 $150.000
TOM (ASPHALT) PG 76-22
TON 240.000 $133.000 $144.000 $200.000
TOM-C (AGGREGATE) SAC-A
TON 3,345.000 $133.000 $144.000 $200.000
PLAN & TEXT CONC PAV(0" TO 1-1/2")
SY 6,457.000 $15.600 $20.000 $30.000
FULL - DEPTH REPAIR CRCP (10")
SY 545.000 $300.000 $430.000 $450.000
STRUCT EXCAV
CY 8.000 $7.610 $57.000 $500.000
CEM STABIL BKFL
CY 21.000 $62.560 $57.000 $200.000
CUT & RESTORE CONC PAVING
SY 20.000 $200.000 $430.000 $450.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 2.000 $100.000 $57.000 $200.000
TRENCH EXCAVATION PROTECTION
LF 10.000 $2.000 $11.000 $200.000
RIPRAP (CONC)(4 IN)
CY 64.000 $367.000 $805.000 $800.000
RIPRAP (MOW STRIP)(4 IN)
CY 26.000 $480.000 $780.000 $1,000.000
RC PIPE (CL III)(24 IN)
LF 45.000 $72.170 $230.000 $200.000
INLET (COMPL)(CURB)(TY C)
EA 1.000 $3,996.000 $10,350.000 $14,000.000
ADJUSTING MANHOLES
EA 3.000 $480.000 $595.000 $1,000.000
REMOV STR (INLET)
EA 1.000 $528.840 $1,725.000 $2,000.000
REMOV STR (PIPE)
LF 45.000 $19.320 $28.000 $25.000
MOBILIZATION
LS 1.000 $110,000.000 $146,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $6,985.000 $835.000 $7,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 922.000 $6.000 $8.900 $25.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 922.000 $0.860 $1.800 $3.000
CONC CURB (MONO) (TY II)
LF 600.000 $28.000 $45.000 $50.000
MTL W-BEAM GD FEN (TIM POST)
LF 250.000 $23.000 $24.000 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 3.000 $1,776.530 $2,200.000 $2,550.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,188.270 $1,500.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 189.000 $4.220 $6.000 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $180.000 $535.000 $200.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $250.000 $415.000 $400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,644.580 $3,150.000 $2,950.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $230.000 $300.000 $300.000
CRASH CUSH ATTEN (INSTL)
EA 4.000 $20,570.000 $27,500.000 $30,000.000
CRASH CUSH ATTEN (REMOVE)
EA 3.000 $1,055.000 $1,190.000 $1,250.000
CONDT (PVC) (SCH 80) (2")
LF 390.000 $7.940 $12.000 $15.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 310.000 $12.500 $19.000 $22.000
ELEC CONDR (NO.6) BARE
LF 700.000 $1.880 $1.700 $2.000
GROUND BOX TY D (162922)W/APRON
EA 9.000 $1,370.000 $1,070.000 $1,100.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 9.000 $25.000 $24.000 $25.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 3.000 $76.850 $57.000 $110.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 10.000 $11.000 $24.000 $20.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 6,270.000 $0.190 $0.300 $0.500
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 1,741.000 $0.170 $0.300 $0.500
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 4,413.000 $0.400 $0.600 $1.500
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 357.000 $1.400 $1.500 $3.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 321.000 $3.500 $3.000 $7.000
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 9.000 $60.000 $80.000 $100.000
WK ZN PAV MRK NON-REMOV (W)(DBL ARW)
EA 4.000 $100.000 $100.000 $100.000
WK ZN PAV MRK NON-REMOV (W)(UTURN ARW)
EA 2.000 $131.260 $100.000 $100.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 11.000 $86.000 $113.000 $100.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 3,956.000 $1.120 $1.400 $2.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 357.000 $2.840 $3.350 $8.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 65.000 $5.750 $6.150 $20.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 9.000 $220.000 $180.000 $220.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 4.000 $167.000 $220.000 $250.000
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 2.000 $180.000 $220.000 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 11.000 $180.000 $240.000 $250.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 6,079.000 $0.670 $1.250 $1.000
PAVEMENT SEALER (ARROW)
EA 9.000 $27.510 $20.000 $35.000
PAVEMENT SEALER (WORD)
EA 11.000 $29.310 $20.000 $35.000
PAVEMENT SEALER (DBL ARROW)
EA 4.000 $38.940 $20.000 $35.000
PAVEMENT SEALER (UTURN ARROW)
EA 2.000 $43.180 $20.000 $35.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 6,110.000 $0.510 $1.250 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 1,190.000 $0.450 $1.250 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 718.000 $0.460 $1.250 $1.000
REFL PAV MRKR TY I-C
EA 90.000 $3.640 $4.200 $6.000
REFL PAV MRKR TY II-A-A
EA 38.000 $3.680 $4.200 $6.000
REFL PAV MRKR TY II-C-R
EA 455.000 $4.040 $4.200 $6.000
ELIM EXT PAV MRK & MRKS (6")
LF 15,526.000 $0.310 $0.050 $0.600
ELIM EXT PAV MRK & MRKS (8")
LF 4,413.000 $0.440 $0.100 $1.500
ELIM EXT PAV MRK & MRKS (12")
LF 357.000 $1.020 $2.500 $1.800
ELIM EXT PAV MRK & MRKS (24")
LF 321.000 $2.200 $5.000 $2.500
ELIM EXT PAV MRK & MRKS (ARROW)
EA 9.000 $35.000 $40.000 $65.000
ELIM EXT PAV MRK & MRKS (DBL ARROW)
EA 4.000 $53.760 $40.000 $65.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 11.000 $56.000 $40.000 $65.000
PAV SURF PREP FOR MRK (6")
LF 15,526.000 $0.010 $0.010 $0.010
PAV SURF PREP FOR MRK (8")
LF 4,413.000 $0.060 $0.010 $0.010
PAV SURF PREP FOR MRK (12")
LF 357.000 $0.120 $0.010 $0.010
PAV SURF PREP FOR MRK (24")
LF 321.000 $0.830 $0.010 $0.010
PAV SURF PREP FOR MRK (ARROW)
EA 9.000 $9.300 $6.000 $5.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 4.000 $7.360 $6.000 $5.000
PAV SURF PREP FOR MRK (UTURN ARR)
EA 2.000 $7.850 $6.000 $5.000
PAV SURF PREP FOR MRK (WORD)
EA 11.000 $9.880 $6.000 $5.000
PAV SURF PREP FOR MRK (RPM)
EA 583.000 $0.170 $1.200 $1.000
SPALLING REPAIR (POLYMERIC) (SEMIRIGID)
GAL 5,065.000 $40.000 $63.000 $70.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 64.000 $60.000 $54.000 $700.000
RADAR PRESENCE DETECTOR
EA 6.000 $7,000.000 $9,400.000 $8,700.000
RADAR PRESENCE DETECTOR COMM CABLE
LF 1,200.000 $3.000 $3.000 $3.000
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 551.000 $0.530 $1.150 $2.000
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 160.000 $0.530 $1.150 $2.000
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 457.000 $0.870 $1.800 $6.000
MULTIPOLYMER PAV MRK (W)(12")(SLD)
LF 110.000 $2.190 $7.750 $10.000
MULTIPOLYMER PAV MRK (W)(24")(SLD)
LF 256.000 $5.160 $11.000 $25.000
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
LF 718.000 $0.520 $1.150 $2.000
MULTIPOLYMER PAV MRK (BLK)(6")(BRK)
LF 40.000 $0.670 $4.150 $2.000
RADAR ADVANCED DETECTION DEVICE
EA 2.000 $7,578.000 $10,100.000 $9,500.000
TMA (STATIONARY)
EA 23.000 $3,986.700 $5.150 $500.000
TMA (MOBILE OPERATION)
HR 144.000 $26.350 $40.000 $50.000
Totals: $1,722,568.410 $2,046,085.220 $2,648,127.870