HARRIS FM 526 (2633-01-014)

Items: 36

County: HARRIS
Length: 1.0600 MILES
Highway: FM 526
District: HOUSTON
Control Number: 2633-01-014
DBE Goal: 0.0%
Project: F 2025(215)
Guaranty: $37,000.00
Time: 42 WORKING DAYS
Engineer's Estimate: $1,858,367.48
Date: 01/08/2025 (1 year ago)
Contract Number: 1253226
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00130684
Contract Type: Federal
Project Description: PAVEMENT REPAIR, MILLING, SEAL COAT, ASPHALT, OVERLAY AND PAVEMENT MARKINGS.
Mail/Deliver Bids To: N/A
PHILLIP GARLIN
NYEMB NYEMB
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$1,858,367.48
$1,067,872.27
Over/Under Est: -42.54% -$790,495.21
Over/Under Est: -37.09% -$689,351.09
Amt Left: 9.47% $101,144.12
Over/Under Est: -34.85% -$647,561.13
Amt Left: 13.38% $142,934.08
Delta: -3.57% -$41,789.96
Over/Under Est: -34.52% -$641,501.01
Amt Left: 13.95% $148,994.20
Delta: -0.50% -$6,060.12
$1,378,850.77
Over/Under Est: -25.8% -$479,516.71
Amt Left: 29.12% $310,978.50
Delta: -13.31% -$161,984.30
Over/Under Est: -17.93% -$333,270.73
Amt Left: 42.82% $457,224.48
Delta: -10.61% -$146,245.98
Subcontractor Percentage Amount
BATTERSON, LLP 7.68% $74,401.51
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. 3.41% $33,035.05
INTERSTATE BARRICADES & MARKINGS, INC. 0.49% $4,746.97
Total: 11.58% $112,183.53

Bid Items & Bid Tabulations

36 Total 0 of 36
HARRIS  |  FM 526  |  HOUSTON  |  2633-01-014  |  01/08/2025  |  $1,858,367.48  |  F 2025(215)  |  SURF/ROADWAY RESTOR  |  42 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DURWOOD GREENE CONSTRUCTION CO.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
TEXAS MATERIALS GROUP, INC.
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
HAYDEN PAVING, INC.
FORDE CONSTRUCTION COMPANY, INC.
BACKFILL (TY A OR B)
STA 52.000 $415.000 $200.000 $350.000 $416.000 $481.670 $250.000 $525.000
ASPH (AC-20-5TR)
GAL 17,403.000 $5.500 $3.850 $3.900 $3.450 $3.530 $5.000 $5.000
AGGR (TY-PL, GR-4)(SAC-B)
CY 387.000 $200.000 $150.000 $180.000 $276.000 $260.510 $450.000 $300.000
SP MIXES SP-D SAC-A PG76-22
TON 3,626.000 $181.750 $153.000 $123.500 $145.250 $136.500 $140.000 $155.000
TACK COAT
GAL 2,900.000 $6.500 $3.500 $4.000 $2.700 $5.250 $4.750 $5.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(19")
SY 1,500.000 $250.000 $97.000 $155.000 $147.500 $131.190 $210.000 $200.000
PLANE ASPH CONC PAV(2")
SY 48,341.000 $5.300 $1.000 $1.800 $1.900 $1.890 $0.750 $2.750
MOBILIZATION
LS 1.000 $170,000.000 $55,000.000 $50,000.000 $76,400.000 $101,869.640 $123,000.000 $110,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $12,000.000 $2,500.000 $4,000.000 $2,850.000 $14,334.830 $1,250.000 $25,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $200.000 $300.000 $65.000 $115.000 $81.840 $500.000 $300.000
TMA (STATIONARY)
DAY 29.000 $350.000 $300.000 $75.000 $260.000 $469.640 $250.000 $500.000
TMA (MOBILE OPERATION)
HR 48.000 $115.000 $50.000 $30.000 $64.000 $32.210 $125.000 $30.000
RIDE PAYMENT ADJUSTMENT (ITEM 344)
DOL 1.000 $1.000 $10.000 $1.000 $1.000 $1.000 $4,500.000 $5,000.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 4,880.000 $1.500 $0.670 $0.480 $0.550 $0.480 $0.490 $0.600
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 19,760.000 $0.820 $0.650 $0.480 $0.550 $0.480 $0.490 $0.130
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,200.000 $1.250 $1.000 $0.960 $1.050 $0.960 $0.970 $1.100
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 590.000 $3.530 $5.000 $5.000 $5.400 $5.000 $5.500 $5.500
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 18.000 $82.500 $95.000 $110.000 $118.300 $110.000 $150.000 $120.000
WK ZN PAV MRK NON-REMOV (W)(RR XING)
EA 4.000 $270.000 $200.000 $355.000 $382.000 $355.000 $400.000 $385.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 2.000 $92.500 $110.000 $130.000 $140.000 $130.000 $260.000 $140.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 4,680.000 $0.840 $0.690 $0.480 $0.550 $0.480 $0.490 $0.600
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 20,012.000 $0.840 $0.660 $0.480 $0.550 $0.480 $0.490 $0.600
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 260.000 $3.250 $6.000 $6.000 $6.450 $6.000 $7.000 $6.500
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 538.000 $3.500 $6.000 $6.000 $6.450 $6.000 $7.000 $6.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 600.000 $2.000 $1.500 $165.000 $1.800 $1.650 $2.000 $1.800
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 295.000 $10.000 $7.000 $7.550 $8.150 $7.550 $8.000 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 9.000 $214.500 $175.000 $225.000 $242.000 $225.000 $300.000 $244.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 1.000 $264.500 $250.000 $245.000 $263.500 $245.000 $350.000 $265.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 2.000 $500.000 $400.000 $475.000 $510.750 $475.000 $500.000 $515.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 2,440.000 $1.750 $1.000 $0.880 $0.950 $0.880 $0.890 $1.000
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 9,880.000 $2.500 $1.500 $0.880 $0.950 $0.880 $0.890 $1.000
ALL-WTHER PM TY I (W)6"(BRK)(100MIL)
LF 2,440.000 $1.750 $1.500 $0.880 $0.950 $0.880 $0.890 $1.000
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 10,006.000 $2.500 $1.500 $0.880 $0.950 $0.880 $0.890 $1.000
ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)
LF 2,340.000 $2.250 $1.500 $0.880 $0.950 $0.880 $0.890 $1.000
REFL PAV MRKR TY I-C
EA 130.000 $7.500 $6.000 $6.000 $6.450 $6.000 $7.000 $7.000
REFL PAV MRKR TY II-A-A
EA 269.000 $8.000 $6.000 $6.000 $6.450 $6.000 $7.000 $7.000
Totals: $1,858,367.480 $1,067,872.270 $1,169,016.390 $1,210,806.350 $1,216,866.470 $1,378,850.770 $1,525,096.750