HARRIS SH 6 (1685-05-137)

Items: 19

County: HARRIS
Length: N/A
Highway: SH 6
District: HOUSTON
Control Number: 1685-05-137
DBE Goal: 0.0%
Project: C 1685-5-137
Guaranty: N/A
Time: 25 WORKING DAYS
Engineer's Estimate: $261,453.00
Date: 05/03/2024 (2 years ago)
Contract Number: N/A
Type: EMBANKMENT STABILIZATION
Mail/Deliver Bids To: N/A
HAMOON BAHRAMI
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$261,453.00
$223,865.00
Over/Under Est: -14.38% -$37,588.00
$333,176.00
Over/Under Est: 27.43% $71,723.00
Amt Left: 48.83% $109,311.00
Over/Under Est: 33.28% $87,017.00
Amt Left: 55.66% $124,605.00
Delta: -4.59% -$15,294.00
Over/Under Est: 77.73% $203,240.00
Amt Left: 107.58% $240,828.00
Delta: -33.35% -$116,223.00

Bid Items & Bid Tabulations

19 Total 0 of 19
HARRIS  |  SH 6  |  HOUSTON  |  1685-05-137  |  05/03/2024  |  $261,453.00  |  C 1685-5-137  |  EMBANKMENT STABILIZATION  |  25 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
MBN ENTERPRISES LLC
EARTH BUILDERS, L.P.
RAGLE CONSTRUCTION, INC.
REMOVING CONC (RIPRAP)
SY 500.000 $50.000 $60.000 $10.000 $65.000 $36.000
REMOVING CONC (HEADWALL)
CY 8.000 $520.000 $300.000 $170.000 $500.000 $210.000
BLOCK SODDING
SY 712.000 $7.000 $10.000 $8.000 $10.000 $16.500
FERTILIZER
AC 0.150 $1,500.000 $1,000.000 $5,000.000 $5,000.000 $5,000.000
VEGETATIVE WATERING
MG 18.000 $75.000 $200.000 $80.000 $100.000 $272.000
CEM STABIL BKFL
CY 334.000 $126.000 $200.000 $190.000 $250.000 $141.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 600.000 $80.000 $15.000 $60.000 $25.000 $81.000
CL C CONC (HEADWALL)
CY 8.000 $3,200.000 $1,000.000 $3,000.000 $3,000.000 $1,800.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 20.000 $230.000 $200.000 $4,000.000 $400.000 $300.000
RIPRAP (CONC)(5 IN)
CY 70.000 $710.000 $700.000 $550.000 $1,350.000 $766.000
RAIL (TY PR22)
LF 30.000 $200.000 $90.000 $350.000 $350.000 $140.000
REMOVE STR (RAIL)
LF 30.000 $100.000 $20.000 $225.000 $20.000 $26.000
MOBILIZATION
LS 1.000 $22,000.000 $25,000.000 $30,000.000 $35,000.000 $46,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $10,000.000 $5,000.000 $10,000.000 $10,000.000 $100,000.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 45.000 $40.000 $10.000 $55.000 $90.000 $50.000
CONSTRUCTION EXITS (REMOVE)
SY 45.000 $15.000 $1.000 $11.000 $20.000 $25.000
CONC CURB (MONO) (TY II)
LF 50.000 $7.500 $50.000 $85.000 $65.000 $21.000
TERMINAL ANCHOR SECTION
EA 1.000 $1,500.000 $2,000.000 $1,500.000 $2,000.000 $2,000.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $400.000 $500.000 $1,000.000 $1,000.000 $500.000
Totals: $261,453.000 $223,865.000 $333,176.000 $348,470.000 $464,693.000