HARRIS SH 6 (1685-05-126)
Items: 87
County: HARRIS
Length: N/A
Highway: SH 6
District: HOUSTON
Control Number: 1685-05-126
DBE Goal: N/A
Project: STP 2021(261)HES
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $1,061,587.90
Date: 01/08/2021 (5 years ago)
Contract Number: N/A
Type: IMPROVE TRAFFIC SIGNALS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,061,587.90 | |||
| $882,567.27 |
-16.86%
-$179,020.63
|
|||
| $981,335.00 |
-7.56%
-$80,252.90
|
11.19%
$98,767.73
|
||
| $988,888.80 |
-6.85%
-$72,699.10
|
12.05%
$106,321.53
|
-0.77%
-$7,553.80
|
|
| $1,045,065.75 |
-1.56%
-$16,522.15
|
18.41%
$162,498.48
|
-5.68%
-$56,176.95
|
|
| $1,057,497.91 |
-0.39%
-$4,089.99
|
19.82%
$174,930.64
|
-1.19%
-$12,432.16
|
E
Engineer's Estimate
$1,061,587.90
1
Awarded
$882,567.27
Over/Under Est:
-16.86%
-$179,020.63
$981,335.00
Over/Under Est:
-7.56%
-$80,252.90
Amt Left:
11.19%
$98,767.73
$988,888.80
Over/Under Est:
-6.85%
-$72,699.10
Amt Left:
12.05%
$106,321.53
Delta:
-0.77%
-$7,553.80
$1,045,065.75
Over/Under Est:
-1.56%
-$16,522.15
Amt Left:
18.41%
$162,498.48
Delta:
-5.68%
-$56,176.95
$1,057,497.91
Over/Under Est:
-0.39%
-$4,089.99
Amt Left:
19.82%
$174,930.64
Delta:
-1.19%
-$12,432.16
| Subcontractor | Percentage | Amount |
|---|---|---|
| ALLY GENERAL SOLUTIONS, LLC | 8.08% | $73,251.69 |
| H&N CONTRACTORS | 3.86% | $34,994.00 |
| MLH CONCRETE | 1.99% | $18,040.95 |
| SEMPER STRIPING LLC | 1.50% | $13,598.70 |
| Total: | 15.43% | $139,885.34 |
Bid Items & Bid Tabulations
87
Total
0 of 87