HARRIS FM 529 (1006-01-087)
Items: 87
County: HARRIS
Length: 0.0000 MILES
Highway: FM 529
District: HOUSTON
Control Number: 1006-01-087
DBE Goal: 0.0%
Project: STP 2025(868)HES
Guaranty: $31,000.00
Time: 164 WORKING DAYS
Engineer's Estimate: $1,784,321.05
Date: 08/07/2025 (10 months ago)
Contract Number: 8253019
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00186780
Contract Type: Federal
Project Description: IMPROVE TRAFFIC SIGNALS AND FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
HARRIS FM 529 (1006-01-087)
Project Name: N/A
Project: STP 2025(868)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: AT QUEENSTON BLVD
Limits To: .
Project Description: IMPROVE TRAFFIC SIGNALS AND FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
HARRIS FM 529 (1006-01-089)
Project Name: FM 529 AT JONES RD
Project: STP 2025(868)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: AT JONES ROAD
Limits To: .
Project Description: IMPROVE TRAFFIC SIGNALS AND FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
HARRIS FM 529 (1006-01-088)
Project Name: FM 529 AT GLEN CHASE DR
Project: STP 2025(868)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: AT GLEN CHASE DRIVE
Limits To: .
Project Description: IMPROVE TRAFFIC SIGNALS AND FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
HARRIS FM 529 (1006-01-086)
Project Name: FM 529 AT HAVEN CREEK DR
Project: STP 2025(868)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: AT HAVEN CREEK DRIVE
Limits To: .
Project Description: IMPROVE TRAFFIC SIGNALS AND FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,784,321.05 | |||
| $1,474,737.54 |
-17.35%
-$309,583.51
|
|||
| $1,525,777.96 |
-14.49%
-$258,543.09
|
3.46%
$51,040.42
|
||
| $1,698,415.00 |
-4.81%
-$85,906.05
|
15.17%
$223,677.46
|
-11.31%
-$172,637.04
|
|
| $1,749,994.99 |
-1.92%
-$34,326.06
|
18.66%
$275,257.45
|
-3.04%
-$51,579.99
|
|
| $1,903,343.37 |
6.67%
$119,022.32
|
29.06%
$428,605.83
|
-8.76%
-$153,348.38
|
|
| $1,995,079.61 |
11.81%
$210,758.56
|
35.28%
$520,342.07
|
-4.82%
-$91,736.24
|
|
| $2,358,358.00 |
32.17%
$574,036.95
|
59.92%
$883,620.46
|
-18.21%
-$363,278.39
|
E
Engineer's Estimate
$1,784,321.05
1
Awarded
$1,474,737.54
Over/Under Est:
-17.35%
-$309,583.51
$1,525,777.96
Over/Under Est:
-14.49%
-$258,543.09
Amt Left:
3.46%
$51,040.42
$1,698,415.00
Over/Under Est:
-4.81%
-$85,906.05
Amt Left:
15.17%
$223,677.46
Delta:
-11.31%
-$172,637.04
$1,749,994.99
Over/Under Est:
-1.92%
-$34,326.06
Amt Left:
18.66%
$275,257.45
Delta:
-3.04%
-$51,579.99
$1,903,343.37
Over/Under Est:
6.67%
$119,022.32
Amt Left:
29.06%
$428,605.83
Delta:
-8.76%
-$153,348.38
$1,995,079.61
Over/Under Est:
11.81%
$210,758.56
Amt Left:
35.28%
$520,342.07
Delta:
-4.82%
-$91,736.24
$2,358,358.00
Over/Under Est:
32.17%
$574,036.95
Amt Left:
59.92%
$883,620.46
Delta:
-18.21%
-$363,278.39
| Subcontractor | Percentage | Amount |
|---|---|---|
| BADGER DAYLIGHTING CORP. | 0.00% | $0.00 |
| Total: | 0.00% | $0.00 |
Bid Items & Bid Tabulations
87
Total
0 of 87
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $9,000.00 |
| PUBLIC UTILITY FORCE ACCT WORK (NON- PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $24,000.00 |