Bid Cobra

HARRIS VA (0912-72-314)

Items: 128

County: HARRIS
Length: N/A
Highway: VA
District: HOUSTON
Control Number: 0912-72-314
DBE Goal: N/A
Project: CM 1602(099)
Guaranty: N/A
Time: 452 WORKING DAYS
Engineer's Estimate: $5,817,462.35
Date: 09/07/2018 (7 years ago)
Contract Number: N/A
Type: CONSTRUCT MULTI-USE PATH
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$5,817,462.35
$5,646,450.50
Over/Under Est: -2.94% -$171,011.85
Over/Under Est: 1.41% $81,817.18
Amt Left: 4.48% $252,829.03
$6,492,517.68
Over/Under Est: 11.6% $675,055.33
Amt Left: 14.98% $846,067.18
Delta: -10.06% -$593,238.15
$6,670,003.58
Over/Under Est: 14.65% $852,541.23
Amt Left: 18.13% $1,023,553.08
Delta: -2.73% -$177,485.90

Bid Items & Bid Tabulations

128 Total 0 of 128
HARRIS  |  VA  |  HOUSTON  |  0912-72-314  |  09/07/2018  |  $5,817,462.35  |  CM 1602(099)  |  CONSTRUCT MULTI-USE PATH  |  452 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PAUL J. SCARIANO, INC.
MAIN LANE INDUSTRIES LTD.
NBG CONSTRUCTORS, INC.
TEXAS WALL & LANDSCAPE
PREPARING ROW
AC 1.790 $10,000.000 $50,000.000 $97,000.000 $50,000.000 $15,000.000
PREPARING ROW (TREE)(10" TO 48" DIA)
EA 45.000 $500.000 $500.000 $750.000 $1,500.000 $1,500.000
PREPARING ROW (HAND CLEARING)
AC 0.960 $20,000.000 $8,300.000 $6,000.000 $40,000.000 $20,000.000
REMOVING CONC (FOUNDATIONS)
SY 895.000 $25.000 $8.500 $8.940 $7.000 $5.000
REMOVING CONC (SIDEWALKS)
SY 620.000 $25.000 $5.500 $2.000 $5.000 $4.000
REMOVING CONC (CURB AND GUTTER)
LF 103.000 $7.800 $5.000 $2.000 $3.000 $2.500
EXCAVATION (ROADWAY)
CY 17,421.000 $15.000 $20.000 $17.500 $1.000 $12.000
EMBANKMENT (FINAL)(DENS CONT)(TY D)
CY 12,067.000 $10.000 $6.000 $4.500 $1.000 $11.000
EMB(FNL)(DC)(TYC)(CSBE)(RWALL FND IMPR)
CY 51.000 $40.000 $35.000 $150.000 $70.000 $76.000
FURNISH AND PLACE TOPSOIL (5")
SY 48,026.000 $1.250 $3.000 $1.500 $2.000 $5.000
BLOCK SODDING
SY 11,777.000 $5.000 $3.500 $4.100 $4.100 $3.000
BROADCAST SEED (PERM)(SPECIAL MIX)
SY 34,536.000 $3.000 $0.250 $0.300 $0.300 $0.180
CELL FBR MLCH SEED(PERM)(SPECIAL MIX)
SY 36,249.000 $1.000 $0.500 $0.490 $0.500 $0.400
FERTILIZER
AC 17.000 $700.000 $1,200.000 $692.320 $700.000 $300.000
VEGETATIVE WATERING
MG 2,040.000 $17.000 $30.000 $20.000 $39.000 $50.000
WILDFLOWER SEEDING
AC 0.350 $13,125.000 $2,750.000 $3,062.710 $3,100.000 $4,500.000
PLANT MATERIAL (1-GAL)
EA 3,759.000 $30.000 $11.000 $9.140 $9.200 $12.000
PLANT MATERIAL (3-GAL)
EA 128.000 $50.000 $24.000 $15.080 $15.200 $20.000
PLANT MATERIAL (5-GAL)
EA 132.000 $80.000 $40.000 $14.980 $15.000 $35.000
MULCH
SY 1,047.000 $10.000 $80.000 $23.950 $24.000 $2.700
PLANT MATERIAL (10 GAL) (TREE)
EA 19.000 $180.000 $240.000 $96.960 $100.000 $120.000
PLANT MATERIAL (15 GAL) (TREE)
EA 170.000 $200.000 $300.000 $175.170 $176.000 $130.000
PLANT MATERIAL (30 GAL) (TREE)
EA 176.000 $240.000 $325.000 $360.450 $365.000 $250.000
LANDSCAPE EDGE (TYPE I)
LF 218.000 $25.000 $25.000 $21.000 $12.000 $18.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 210.000 $18.000 $55.000 $35.000 $27.000 $30.000
LIME TRT (EXST MATL) (6")
SY 6,526.000 $8.000 $2.500 $10.000 $5.000 $6.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 127.700 $185.000 $200.000 $170.000 $175.000 $220.000
FLY ASH (CLASS FS)
TON 159.300 $190.000 $185.000 $120.000 $80.000 $210.000
LFA TREAT SUBGRADE (6")
SY 8,554.000 $6.000 $3.000 $10.000 $5.000 $4.500
ASPH (MULTI OPTION)
GAL 176.000 $3.000 $4.000 $3.500 $10.000 $4.500
AGGR(TY-PB GR-4 SAC-A)
CY 4.000 $128.000 $100.000 $100.000 $200.000 $100.000
LRA PAV TY-I GR-A
TON 38.000 $400.000 $175.000 $160.000 $250.000 $225.000
D-GR HMA TY-D SAC-B PG70-22
TON 44.200 $75.000 $100.000 $300.000 $300.000 $175.000
PLANE ASPH CONC PAV(0" TO 2")
SY 401.000 $2.000 $3.000 $8.000 $15.000 $16.500
CEM STABIL BKFL
CY 737.000 $70.000 $65.000 $35.000 $60.000 $65.000
TEMPORARY SPL SHORING
SF 6,700.000 $15.000 $10.000 $16.000 $24.000 $25.000
TEMPORARY SPL SHORING (SOIL NAIL)
SF 298.000 $35.000 $40.000 $30.000 $15.000 $19.000
SOIL NAIL ANCHORS
LF 270.000 $20.000 $27.000 $44.000 $70.000 $28.000
DRILL SHAFT (18 IN)
LF 280.000 $90.000 $120.000 $75.000 $150.000 $111.000
DRILL SHAFT (30 IN)
LF 300.000 $150.000 $250.000 $180.000 $350.000 $265.000
DRILL SHAFT (42 IN)
LF 80.000 $205.000 $300.000 $350.000 $600.000 $541.000
CL C CONC (ABUT)
CY 81.800 $1,200.000 $800.000 $1,200.000 $1,500.000 $1,100.000
CL C CONC (CAP)
CY 20.200 $925.000 $900.000 $1,200.000 $1,200.000 $1,800.000
CL C CONC (COLUMN)
CY 20.700 $925.000 $1,000.000 $2,000.000 $1,200.000 $1,750.000
CL C CONC (INLET)
CY 38.000 $420.000 $650.000 $1,000.000 $750.000 $820.000
RETAINING WALL (CONC BLOCK)
SF 2,432.000 $50.000 $23.000 $51.000 $60.000 $49.000
RETAINING WALL (CAST - IN - PLACE)
SF 6,302.000 $65.000 $60.000 $80.000 $100.000 $99.000
RETAINING WALL (SOIL NAIL)(FACIA)
SF 298.000 $50.000 $65.000 $85.000 $100.000 $53.000
PNEUMATICALLY PLACED CONC (ENCASEMENT)
SF 425.000 $22.000 $25.000 $7.000 $8.000 $9.000
PNEUMATICALLY PLACED CONC (REPAIR)
CF 261.000 $25.000 $60.000 $17.000 $10.000 $23.000
RIPRAP (CONC)(6 IN)
CY 305.000 $440.000 $390.000 $350.000 $580.000 $480.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 30.000 $200.000 $500.000 $550.000 $500.000 $618.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 50.000 $100.000 $100.000 $150.000 $130.000 $145.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 3,452.000 $100.000 $130.000 $130.000 $170.000 $145.000
CONCRETE OVERLAY (2 IN)
SY 153.000 $201.000 $50.000 $60.000 $20.000 $1.000
STR STEEL (MISC NON - BRIDGE)
LB 81,161.000 $2.700 $4.000 $2.300 $5.500 $4.500
RAIL (TY C221)
LF 215.000 $99.000 $100.000 $160.000 $350.000 $140.000
RAIL (TY PR11)
LF 560.000 $105.000 $95.000 $85.000 $110.000 $175.000
CMP (GAL STL 24 IN)
LF 593.000 $95.000 $80.000 $75.000 $120.000 $180.000
CMP (GAL STL 30 IN)
LF 282.000 $110.000 $85.000 $100.000 $120.000 $155.000
CMP (GAL STL 36 IN)
LF 44.000 $120.000 $95.000 $115.000 $130.000 $200.000
CONC BOX CULV (12 FT X 10 FT)
LF 44.000 $1,000.000 $1,300.000 $2,000.000 $2,200.000 $1,650.000
RC PIPE (CL III)(24 IN)
LF 99.000 $120.000 $95.000 $150.000 $85.000 $150.000
RC PIPE (CL III)(48 IN)
LF 112.000 $190.000 $200.000 $175.000 $220.000 $250.000
INLET (COMPL)(TY A)
EA 3.000 $3,500.000 $3,200.000 $3,000.000 $4,500.000 $4,350.000
MANH (COMPL)(TY A)
EA 5.000 $4,000.000 $6,400.000 $4,400.000 $7,000.000 $5,700.000
WINGWALL (PW - 1) (HW=16 FT)
EA 2.000 $60,000.000 $39,000.000 $50,000.000 $110,000.000 $81,000.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 4.000 $1,000.000 $1,300.000 $1,500.000 $1,500.000 $1,500.000
SET (TY II) (36 IN) (CMP) (3: 1) (C)
EA 1.000 $3,000.000 $2,700.000 $3,750.000 $2,500.000 $2,900.000
SET (TY II) (48 IN) (RCP) (3: 1) (P)
EA 2.000 $3,810.000 $3,500.000 $6,500.000 $6,700.000 $6,200.000
GRATE AND FRAME(BRIDGE DRAIN)(2 GRATES)
EA 2.000 $2,000.000 $1,200.000 $3,500.000 $500.000 $5,500.000
CAST-IN-PLACE TRENCH DRAIN
LF 20.000 $1,700.000 $700.000 $230.000 $150.000 $125.000
ADJUSTING MANHOLES
EA 1.000 $1,050.000 $300.000 $550.000 $500.000 $2,500.000
PIPE (PVC) (SCH 40) (4 IN)
LF 160.000 $35.000 $40.000 $60.000 $35.000 $28.000
PIPE (PVC) (SCH 40) (6 IN)
LF 55.000 $40.000 $50.000 $90.000 $40.000 $35.000
REMOV STR (MANHOLE)
EA 1.000 $1,100.000 $600.000 $500.000 $1,500.000 $2,000.000
REMOV STR (PIPE)
LF 295.000 $15.000 $35.000 $35.000 $50.000 $9.000
REMOV STR (PICNIC AREA)
EA 2.000 $1,000.000 $600.000 $60.000 $800.000 $700.000
REMOV STR (SMALL FENCE)
LF 303.000 $8.000 $19.000 $4.000 $3.000 $9.000
REMOVE STR (RAIL)
LF 141.000 $35.000 $25.000 $15.000 $22.000 $12.000
MOBILIZATION
LS 1.000 $540,000.000 $510,000.000 $400,000.000 $640,000.000 $310,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 30.000 $900.000 $500.000 $1,500.000 $1,000.000 $3,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 546.000 $20.000 $35.000 $30.000 $45.000 $28.000
CONSTRUCTION EXITS (REMOVE)
SY 546.000 $14.000 $10.000 $8.000 $10.000 $8.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 12,787.000 $2.000 $2.000 $3.000 $3.000 $2.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 12,787.000 $1.000 $0.500 $0.750 $0.700 $1.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 706.000 $5.000 $3.000 $2.250 $6.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 706.000 $1.500 $0.500 $1.000 $0.700 $1.000
COLORED TEXTURED CONC (6")
SY 306.000 $90.000 $75.000 $120.000 $120.000 $175.000
CONC CURB & GUTTER (TY II)
LF 163.000 $40.000 $45.000 $80.000 $20.000 $100.000
CONC CURB (SLOTTED)
LF 152.000 $25.000 $25.000 $30.000 $8.000 $19.000
CONC SIDEWALKS (6")
SY 13,328.000 $71.000 $67.000 $72.000 $45.000 $76.000
CURB RAMPS (TY 5)
EA 1.000 $2,460.000 $1,700.000 $2,800.000 $2,000.000 $2,800.000
CURB RAMPS (TY 10)
EA 1.000 $1,650.000 $1,700.000 $2,600.000 $2,500.000 $3,200.000
MTL W-BEAM GD FEN (TIM POST)
LF 37.500 $20.000 $25.000 $60.000 $50.000 $65.000
TERMINAL ANCHOR SECTION
EA 1.000 $750.000 $2,500.000 $950.000 $3,800.000 $3,000.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $1,800.000 $2,500.000 $2,200.000 $3,000.000 $650.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,350.000 $1,500.000 $1,500.000 $1,500.000 $3,000.000
REMOVE METAL BEAM GUARD FENCE
LF 23.000 $5.000 $8.000 $10.000 $5.000 $5.000
CHAIN LINK FENCE (REMOVE)
LF 36.000 $8.000 $5.000 $4.000 $3.000 $10.000
CHAIN LINK FENCE (INSTALL) (8')
LF 329.000 $80.000 $70.000 $22.000 $25.000 $35.000
CHN LNK FNCE(PVC-COATD)(8' MESH)(INSTL)
LF 321.000 $85.000 $85.000 $30.000 $45.000 $40.000
REFL PAV MRK TY I (W)(SYMBOL)(100MIL)
EA 2.000 $475.000 $340.000 $365.630 $260.000 $300.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 756.000 $0.500 $4.000 $3.000 $4.000 $3.500
REFL PAV MRK TY II (Y) 4" (SLD)
LF 596.000 $0.500 $4.000 $3.000 $4.000 $3.500
REMOVAL OF TIMBER POLES
EA 1.000 $1,000.000 $650.000 $280.000 $100.000 $1,600.000
INSTL DOWN GUY W/GUARD
EA 2.000 $100.000 $400.000 $500.000 $500.000 $1,200.000
REPLACE DOWN GUY W/GUARD
EA 2.000 $5,000.000 $500.000 $500.000 $500.000 $1,200.000
LANDSCAPE AMENITY
EA 4.000 $5,000.000 $2,500.000 $8,000.000 $3,500.000 $2,200.000
LANDSCAPE AMENITY (TY 1)
EA 6.000 $10,000.000 $2,600.000 $14,000.000 $4,000.000 $1,275.000
LANDSCAPE AMENITY (TY 2)
EA 6.000 $1,250.000 $1,000.000 $1,500.000 $1,600.000 $2,300.000
LANDSCAPE AMENITY (TY 3)
EA 6.000 $1,250.000 $1,000.000 $1,500.000 $1,600.000 $2,300.000
LANDSCAPE AMENITY (TY 4)
EA 12.000 $3,500.000 $3,000.000 $6,000.000 $9,000.000 $6,400.000
LANDSCAPE AMENITY (TY 5)
EA 1.000 $30,000.000 $30,000.000 $45,000.000 $40,000.000 $19,100.000
LANDSCAPE AMENITY (TY 6)
EA 3.000 $6,000.000 $12,000.000 $28,000.000 $28,000.000 $12,100.000
LANDSCAPE AMENITY (TY 7)
EA 4.000 $3,000.000 $2,000.000 $3,500.000 $3,100.000 $3,600.000
LANDSCAPE AMENITY (TY 8)
EA 1.000 $8,000.000 $30,000.000 $22,000.000 $12,000.000 $35,600.000
LANDSCAPE AMENITY (TY 9)
EA 3.000 $12,000.000 $12,000.000 $7,800.000 $4,500.000 $7,000.000
LANDSCAPE AMENITY (TY 10)
EA 12.000 $600.000 $2,000.000 $5,000.000 $3,000.000 $3,100.000
LANDSCAPE AMENITY (TY 11)
EA 3.000 $1,750.000 $5,000.000 $4,000.000 $5,500.000 $8,300.000
LANDSCAPE SOIL AMENDMENT (TYPE IV)
SY 634.000 $30.000 $4.500 $0.270 $0.270 $3.500
PREFAB PED STL TRUSS BRG SPAN (38 FT)
EA 2.000 $70,480.000 $55,000.000 $46,000.000 $80,000.000 $79,000.000
PREFAB PED STL TRUSS BRG SPAN (74 FT)
EA 1.000 $109,290.000 $100,000.000 $82,000.000 $130,000.000 $138,000.000
PREFAB PED STL TRUSS BRG SPAN (100 FT)
EA 1.000 $208,500.000 $150,000.000 $130,000.000 $190,000.000 $213,000.000
RETROFIT DET WARN SURF(CAST IN PLACE)
SF 49.000 $25.000 $40.000 $60.000 $8.000 $50.000
WHEEL STOPS
EA 10.000 $500.000 $350.000 $200.000 $75.000 $500.000
REMOVABLE BOLLARD
EA 4.000 $1,210.000 $650.000 $1,500.000 $1,000.000 $1,900.000
ADJUSTING METER BOX
EA 1.000 $500.000 $500.000 $200.000 $400.000 $948.100
Totals: $5,817,462.350 $5,646,450.500 $5,899,279.538 $6,492,517.680 $6,670,003.580