HARRIS PR 138 (0912-70-098)

Items: 44

County: HARRIS
Length: 0.0000 MILES
Highway: PR 138
District: HOUSTON
Control Number: 0912-70-098
DBE Goal: 0.0%
Project: C 912-70-98
Guaranty: $36,000.00
Time: 65 WORKING DAYS
Engineer's Estimate: $1,794,657.75
Date: 12/02/2025 (6 months ago)
Contract Number: 12253031
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00102904
Project Description: REPAIR FAILURES AND RESURFACE PR 138 WITHIN SHELDON LAKE STATE PARK
Mail/Deliver Bids To: N/A
PHILLIP GARLIN
NYEMB NYEMB
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,794,657.75
Over/Under Est: -3.04% -$54,570.25
Over/Under Est: 1.19% $21,358.70
Amt Left: 4.36% $75,928.95
Over/Under Est: 1.46% $26,168.50
Amt Left: 4.64% $80,738.75
Delta: -0.26% -$4,809.80
Over/Under Est: 3.35% $60,186.75
Amt Left: 6.59% $114,757.00
Delta: -1.87% -$34,018.25
$2,154,907.53
Over/Under Est: 20.07% $360,249.78
Amt Left: 23.84% $414,820.03
Delta: -16.18% -$300,063.03

Bid Items & Bid Tabulations

44 Total 0 of 44
HARRIS  |  PR 138  |  HOUSTON  |  0912-70-098  |  12/02/2025  |  $1,794,657.75  |  C 912-70-98  |  SURF/ROADWAY RESTOR  |  65 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
ENVIRONMENTAL ALLIES, INC.
TEXAS MATERIALS GROUP, INC.
DURWOOD GREENE CONSTRUCTION CO.
STX CIVIL
RMV (4") TRT/UNTRT BASE & ASPH PAV
SY 16,550.000 $10.000 $6.000 $4.500 $5.250 $6.000 $3.000
EXCAV (CHANNEL)
CY 7.000 $35.000 $500.000 $25.000 $700.000 $600.000 $50.000
BACKFILL (TY B)
STA 92.500 $205.000 $165.000 $35.000 $295.000 $100.000 $350.000
BLOCK SODDING
SY 8,665.000 $5.000 $4.000 $7.000 $4.900 $5.500 $6.000
VEGETATIVE WATERING
TGL 371.000 $42.000 $43.000 $30.000 $15.650 $35.000 $75.000
RDSIDE AMENITY (WHEEL STOP REMOV&RESET)
EA 50.000 $200.000 $50.000 $150.000 $130.000 $130.000 $250.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 323.000 $320.000 $365.000 $365.000 $352.000 $380.000 $420.000
LIME TRT (EXIST MATL)(8")
SY 17,874.000 $4.500 $9.500 $6.000 $6.500 $4.000 $6.500
ASPHALT TRT BASE (GR 2)(PG 64)
TON 3,642.000 $125.000 $115.000 $135.000 $119.300 $132.000 $160.000
PRIME COAT (PCE)
GAL 3,310.000 $4.000 $5.000 $9.000 $4.750 $2.250 $10.000
ASPH (AC-15P OR AC-10-2TR)
GAL 10,994.000 $5.500 $4.700 $6.500 $3.000 $5.000 $10.000
AGGR (TY-PB OR PL, GR-4)(SAC-B)
CY 264.000 $200.000 $234.000 $350.000 $267.000 $220.000 $175.000
SP MIXES SP-D SAC-A PG70-22
TON 2,834.000 $125.000 $138.000 $155.000 $156.000 $155.000 $150.000
PLANE ASPH CONC PAV(0" TO 2")
SY 2,018.000 $2.500 $6.000 $4.000 $4.000 $8.000 $3.000
CEM STABIL BKFL
CY 74.000 $65.000 $250.000 $75.000 $70.550 $90.000 $145.000
RC PIPE (ARCH)(CL III)(DES 1)
LF 194.000 $245.000 $260.000 $175.000 $196.000 $260.000 $290.000
HEADWALL (CH - PW - 0) (DIA= 18 IN)
EA 2.000 $10,000.000 $6,500.000 $9,500.000 $15,400.000 $9,500.000 $12,500.000
SET (TY II) (DES 1) (RCP) (4: 1) (C)
EA 2.000 $5,000.000 $5,000.000 $5,750.000 $7,425.000 $3,200.000 $3,500.000
MOBILIZATION
LS 1.000 $148,000.000 $62,000.000 $43,850.000 $160,000.000 $110,000.000 $195,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $3,800.000 $1,850.000 $1,187.000 $6,000.000 $2,300.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 64.000 $135.000 $75.000 $120.000 $110.000 $300.000 $65.000
TMA (STATIONARY)
DAY 33.000 $200.000 $120.000 $250.000 $250.000 $350.000 $65.000
TMA (MOBILE OPERATION)
DAY 10.000 $220.000 $120.000 $500.000 $700.000 $350.000 $65.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 100.000 $48.000 $40.200 $40.000 $65.000 $65.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $15.000 $12.450 $15.000 $22.000 $25.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 12,520.000 $3.500 $3.250 $3.500 $1.950 $3.750 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 12,520.000 $1.000 $0.920 $1.500 $0.650 $1.500 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 36.000 $4.500 $6.000 $10.500 $5.450 $22.000 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 36.000 $1.000 $1.000 $3.000 $2.200 $5.000 $1.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 2.000 $5,000.000 $4,500.000 $5,000.000 $3,120.000 $5,400.000 $6,200.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 35.000 $600.000 $625.000 $575.000 $938.750 $600.000 $680.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $710.000 $790.000 $725.000 $993.000 $850.000 $880.000
REMOVE SM RD SN SUP&AM
EA 29.000 $90.000 $125.000 $103.000 $157.350 $110.000 $115.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 76.000 $3.500 $4.000 $5.500 $5.450 $5.000 $6.460
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 1,490.000 $0.400 $0.300 $0.750 $0.550 $0.700 $0.710
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 5,206.000 $0.400 $0.300 $0.750 $0.550 $0.700 $0.710
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 72.000 $4.000 $6.000 $5.500 $5.450 $7.000 $10.330
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,734.000 $2.000 $1.000 $2.000 $0.300 $2.500 $11.950
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 231.000 $7.500 $7.000 $9.000 $8.850 $10.000 $10.140
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 25,447.000 $1.050 $1.000 $1.050 $0.900 $1.100 $1.610
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 3,106.000 $1.000 $1.000 $1.100 $0.900 $1.100 $1.610
ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)
LF 2,490.000 $1.000 $1.000 $1.100 $0.900 $1.100 $1.610
PRE PM TY C(BL&WH)(ACC PRK)(W/BORDR)LG
EA 6.000 $450.000 $455.000 $550.000 $374.450 $550.000 $6.130
DITCH CLEANING AND RESHAPING (FOOT)
LF 1,051.000 $2.000 $12.000 $6.000 $11.150 $5.000 $10.000
Totals: $1,794,657.750 $1,740,087.500 $1,816,016.450 $1,820,826.250 $1,854,844.500 $2,154,907.530