HARRIS SH 249 (0720-03-153)

Items: 86

County: HARRIS
Length: 0.0000 MILES
Highway: SH 249
District: HOUSTON
Control Number: 0720-03-153
DBE Goal: 0.0%
Project: STP 2026(724)HES
Guaranty: $35,000.00
Time: 218 WORKING DAYS
Engineer's Estimate: $1,692,028.04
Date: 06/03/2026 (7 days ago)
Contract Number: 6263217
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193911
Contract Type: Federal
Project Description: IMPROVE TRAFFIC SIGNAL
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
EUGENE AMPOMAH
KIALEE GBOSI
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (10)
E
Engineer's Estimate
$1,692,028.04
$1,523,084.25
Over/Under Est: -9.98% -$168,943.79
Over/Under Est: -6.32% -$106,954.83
Amt Left: 4.07% $61,988.96
$1,629,033.04
Over/Under Est: -3.72% -$62,995.00
Amt Left: 6.96% $105,948.79
Delta: -2.77% -$43,959.83
Over/Under Est: -3.07% -$51,967.74
Amt Left: 7.68% $116,976.05
Delta: -0.68% -$11,027.26
$1,716,952.95
Over/Under Est: 1.47% $24,924.91
Amt Left: 12.73% $193,868.70
Delta: -4.69% -$76,892.65
Over/Under Est: 3.74% $63,222.82
Amt Left: 15.24% $232,166.61
Delta: -2.23% -$38,297.91
$1,773,896.46
Over/Under Est: 4.84% $81,868.42
Amt Left: 16.47% $250,812.21
Delta: -1.06% -$18,645.60
Over/Under Est: 7.71% $130,524.87
Amt Left: 19.66% $299,468.66
Delta: -2.74% -$48,656.45
Over/Under Est: 29.32% $496,161.98
Amt Left: 43.67% $665,105.77
Delta: -20.06% -$365,637.11
Over/Under Est: 46.92% $793,867.37
Amt Left: 63.21% $962,811.16
Delta: -13.61% -$297,705.39

Bid Items & Bid Tabulations

86 Total 0 of 86
HARRIS  |  SH 249  |  HOUSTON  |  0720-03-153  |  06/03/2026  |  $1,692,028.04  |  STP 2026(724)HES  |  HAZARD ELIM & SAFETY  |  218 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DECO CONTRACTORS, INC.
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SICE, INC.
VACA UNDERGROUND UTILITIES INC
TRAF-TEX, INC.
STATEWIDE TRAFFIC SIGNAL COMPANY
CREACOM, INC.
THIRD COAST SERVICES LLC
SELECT MAINTENANCE, L.L.C.
STRUCTURAL INTEGRITY GROUP LLC
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 210.000 $65.000 $95.000 $32.760 $51.392 $18.000 $94.550 $31.000 $109.630 $33.850 $40.000 $50.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 8.000 $280.000 $185.000 $206.000 $162.531 $290.000 $307.000 $255.000 $281.090 $161.500 $360.000 $546.000
DRILL SHAFT (TRF SIG POLE) (48 IN)
LF 264.000 $475.000 $425.000 $410.000 $491.215 $337.000 $663.000 $530.000 $366.600 $396.750 $450.000 $716.000
MOBILIZATION
LS 1.000 $148,366.190 $150,000.000 $107,389.000 $156,897.386 $40,000.000 $54,418.000 $166,000.000 $124,174.260 $182,255.290 $226,700.000 $248,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $4,000.000 $1,750.000 $1,964.200 $2,040.434 $2,000.000 $591.000 $1,000.000 $3,550.790 $2,583.840 $23,750.000 $10,000.000
TMA (STATIONARY)
DAY 218.000 $250.000 $100.000 $200.000 $78.120 $75.000 $291.000 $50.000 $369.740 $378.430 $50.000 $1.000
CURB RAMPS (TY 1)
EA 14.000 $3,500.000 $1,900.000 $3,475.000 $4,199.028 $2,250.000 $5,560.000 $6,150.000 $6,909.550 $6,769.190 $4,000.000 $3,580.000
CURB RAMPS (TY 5)
EA 3.000 $4,800.000 $2,750.000 $3,475.000 $4,512.388 $3,200.000 $5,560.000 $6,150.000 $6,448.910 $6,769.190 $5,000.000 $4,775.000
CURB RAMPS (TY 21)
EA 4.000 $4,000.000 $3,500.000 $3,475.000 $5,452.469 $2,800.000 $5,560.000 $6,150.000 $8,061.140 $6,769.190 $5,000.000 $4,775.000
CURB RAMPS (TY 22)
EA 4.000 $5,500.000 $5,000.000 $3,475.000 $5,703.158 $3,300.000 $5,560.000 $6,150.000 $8,061.140 $6,769.190 $5,000.000 $5,967.000
IN RD IL (TY SA) 30T-8-8 (250W EQ) LED
EA 1.000 $6,750.000 $7,500.000 $8,645.000 $4,455.288 $9,000.000 $8,301.000 $8,600.000 $9,578.010 $5,297.360 $10,000.000 $9,578.000
CONDT (PVC) (SCH 80) (2")
LF 220.000 $10.000 $10.000 $10.370 $17.490 $13.000 $19.950 $15.000 $13.570 $14.850 $15.000 $28.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 545.000 $18.000 $19.000 $14.370 $17.056 $12.000 $26.200 $15.000 $23.060 $24.890 $16.000 $40.000
CONDT (PVC) (SCH 80) (3")
LF 130.000 $23.000 $16.000 $13.380 $19.107 $16.000 $29.350 $16.000 $15.640 $16.100 $17.000 $27.000
CONDT (PVC) (SCH 80) (3") (BORE)
LF 1,035.000 $28.000 $26.000 $18.880 $18.642 $14.000 $43.400 $16.000 $20.610 $26.150 $18.000 $45.000
CONDT (PVC) (SCH 80) (4")
LF 135.000 $25.000 $19.000 $19.630 $26.647 $18.000 $50.400 $18.000 $18.200 $19.220 $19.000 $28.000
CONDT (PVC) (SCH 80) (4") (BORE)
LF 1,625.000 $33.000 $30.000 $21.630 $22.721 $20.000 $48.000 $18.000 $21.520 $34.900 $21.000 $48.000
ELEC CONDR (NO.8) BARE
LF 3,610.000 $1.800 $1.950 $2.060 $1.249 $2.000 $2.000 $1.620 $1.420 $1.910 $1.900 $3.710
ELEC CONDR (NO.8) INSULATED
LF 1,505.000 $2.000 $2.200 $2.170 $1.565 $2.150 $2.200 $1.710 $2.080 $2.070 $2.000 $5.440
TRAY CABLE (4 CONDR) (12 AWG)
LF 5,560.000 $3.000 $2.300 $3.450 $2.621 $3.500 $4.050 $3.000 $2.840 $3.420 $2.250 $4.660
GROUND BOX TY D (162922)
EA 21.000 $915.000 $1,350.000 $720.000 $1,540.533 $975.000 $1,280.000 $7,000.000 $834.680 $830.720 $2,000.000 $1,525.000
GROUND BOX TY D (162922)W/APRON
EA 8.000 $1,200.000 $1,400.000 $1,022.500 $1,934.428 $1,400.000 $1,381.000 $1,600.000 $1,141.250 $1,240.960 $3,200.000 $2,125.000
REMOVE GROUND BOX
EA 36.000 $275.000 $200.000 $50.000 $250.689 $400.000 $104.000 $1,000.000 $396.140 $188.320 $275.000 $315.000
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 2.000 $8,000.000 $5,500.000 $6,810.000 $8,217.393 $7,500.000 $8,554.000 $6,710.000 $6,960.280 $9,101.310 $25,000.000 $8,900.000
ALUMINUM SIGNS (TY A)
SF 168.000 $40.000 $25.000 $69.370 $32.247 $37.000 $24.250 $65.000 $46.570 $54.840 $38.000 $84.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $800.000 $795.000 $1,250.000 $1,071.693 $1,000.000 $874.500 $900.000 $1,102.760 $760.680 $1,250.000 $1,945.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 1,108.000 $2.150 $2.000 $1.050 $0.978 $1.250 $0.900 $0.800 $1.010 $2.260 $0.780 $2.980
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 6,112.000 $1.500 $2.850 $1.310 $1.881 $1.550 $1.700 $1.530 $1.930 $3.210 $1.500 $2.690
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 1,297.000 $5.000 $4.850 $3.410 $4.388 $3.850 $3.900 $3.580 $4.510 $5.470 $3.500 $4.780
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,752.000 $9.000 $9.150 $9.350 $7.672 $10.500 $6.800 $6.240 $7.890 $10.330 $6.120 $9.550
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 33.000 $170.000 $205.000 $194.250 $31.337 $230.000 $28.000 $26.000 $32.240 $231.280 $25.000 $119.390
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 18.000 $290.000 $250.000 $315.000 $31.337 $375.000 $28.000 $26.000 $32.240 $282.050 $25.000 $125.360
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 8.000 $175.000 $285.000 $315.000 $31.337 $375.000 $28.000 $26.000 $32.240 $321.540 $25.000 $125.360
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 58.000 $200.000 $215.000 $199.500 $31.337 $230.000 $28.000 $26.000 $32.240 $242.560 $25.000 $131.320
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 910.000 $3.000 $3.000 $2.630 $1.505 $3.000 $1.350 $1.230 $1.550 $3.380 $1.200 $1.050
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 995.000 $1.500 $1.450 $1.050 $1.505 $1.250 $1.350 $1.230 $1.550 $1.640 $1.200 $1.050
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 2,154.000 $1.000 $1.450 $1.050 $0.941 $1.250 $0.850 $0.770 $0.970 $1.640 $0.750 $1.050
PREFAB PM TY C (W)(ARROW)
EA 33.000 $275.000 $235.000 $236.250 $263.223 $275.000 $234.000 $215.000 $270.850 $265.130 $210.000 $438.650
PREFAB PM TY C (W)(DBL ARROW)
EA 18.000 $400.000 $360.000 $446.250 $282.025 $500.000 $250.000 $230.000 $290.200 $406.150 $225.000 $587.790
PREFAB PM TY C (W)(UTURN ARROW)
EA 8.000 $400.000 $480.000 $446.250 $282.025 $500.000 $250.000 $230.000 $290.200 $541.530 $225.000 $637.500
PREFAB PM TY C (W)(WORD)
EA 58.000 $300.000 $305.000 $357.000 $269.490 $410.000 $239.000 $220.000 $277.300 $344.100 $215.000 $529.960
REFL PAV MRKR TY I-C
EA 616.000 $5.500 $6.500 $5.510 $7.521 $6.250 $6.700 $6.120 $7.740 $7.330 $6.000 $7.160
ELIM EXT PM & MRKS (6")
LF 6,060.000 $0.500 $0.400 $0.530 $0.314 $0.750 $0.300 $0.260 $0.320 $0.450 $0.250 $0.580
ELIM EXT PM & MRKS (8")
LF 5,445.000 $1.500 $0.700 $0.680 $0.377 $0.850 $0.350 $0.310 $0.390 $0.790 $0.300 $0.820
ELIM EXT PM & MRKS (12")
LF 2,229.000 $2.000 $1.000 $1.580 $0.565 $2.000 $0.500 $0.460 $0.580 $1.130 $0.450 $1.530
ELIM EXT PM & MRKS (24")
LF 1,061.000 $5.000 $2.050 $3.150 $0.828 $3.750 $0.750 $0.680 $0.850 $2.310 $0.660 $3.060
ELIM EXT PM & MRKS (ARROW)
EA 25.000 $70.000 $40.000 $36.750 $31.337 $41.000 $28.000 $26.000 $32.240 $45.130 $25.000 $77.600
ELIM EXT PM & MRKS (DBL ARROW)
EA 18.000 $110.000 $45.000 $73.500 $43.871 $82.000 $39.000 $36.000 $45.140 $50.770 $35.000 $77.600
ELIM EXT PM & MRKS (UTURN ARROW)
EA 8.000 $60.000 $45.000 $73.500 $56.405 $82.000 $50.000 $46.000 $58.040 $50.770 $45.000 $77.600
ELIM EXT PM & MRKS (WORD)
EA 58.000 $85.000 $40.000 $36.750 $31.337 $41.000 $28.000 $26.000 $32.240 $45.130 $25.000 $77.600
PAV SURF PREP FOR MRK (6")
LF 5,440.000 $0.100 $0.050 $0.080 $0.013 $0.100 $0.050 $0.020 $0.010 $0.050 $0.010 $0.100
PAV SURF PREP FOR MRK (8")
LF 6,112.000 $0.200 $0.150 $0.110 $0.026 $0.150 $0.050 $0.030 $0.030 $0.170 $0.020 $0.120
PAV SURF PREP FOR MRK (12")
LF 1,247.000 $0.750 $0.400 $0.160 $0.063 $0.200 $0.100 $0.060 $0.060 $0.450 $0.050 $0.190
PAV SURF PREP FOR MRK (24")
LF 1,752.000 $1.000 $0.800 $0.320 $0.151 $0.400 $0.150 $0.130 $0.150 $0.900 $0.120 $0.380
PAV SURF PREP FOR MRK (ARROW)
EA 25.000 $15.000 $20.000 $73.500 $12.535 $9.000 $11.000 $11.000 $12.900 $22.560 $10.000 $53.720
PAV SURF PREP FOR MRK (DBL ARROW)
EA 18.000 $15.000 $25.000 $15.750 $12.535 $19.000 $11.000 $11.000 $12.900 $28.200 $10.000 $53.720
PAV SURF PREP FOR MRK (UTURN ARR)
EA 8.000 $25.000 $25.000 $15.750 $12.535 $19.000 $11.000 $11.000 $12.900 $28.200 $10.000 $53.720
PAV SURF PREP FOR MRK (WORD)
EA 55.000 $10.000 $20.000 $7.350 $12.535 $9.000 $11.000 $11.000 $12.900 $22.560 $10.000 $53.720
INSTALL HWY TRF SIG (SYSTEM)
EA 2.000 $45,000.000 $30,000.000 $29,624.000 $33,566.923 $40,000.000 $45,650.000 $43,000.000 $34,988.430 $37,721.600 $75,000.000 $77,000.000
REMOVING TRAFFIC SIGNALS (DIAMOND)
EA 2.000 $9,500.000 $5,000.000 $5,000.000 $7,182.302 $5,000.000 $7,560.000 $26,000.000 $16,342.920 $5,969.430 $8,500.000 $27,000.000
VEH SIG SEC (12")LED(GRN)
EA 39.000 $290.000 $250.000 $319.000 $247.861 $325.000 $255.000 $321.000 $291.700 $270.240 $310.000 $478.000
VEH SIG SEC (12")LED(GRN ARW)
EA 9.000 $290.000 $250.000 $319.000 $247.861 $325.000 $255.000 $321.000 $291.700 $275.930 $310.000 $413.000
VEH SIG SEC (12")LED(YEL)
EA 39.000 $290.000 $250.000 $319.000 $247.861 $325.000 $255.000 $321.000 $291.700 $270.240 $310.000 $413.000
VEH SIG SEC (12")LED(YEL ARW)
EA 9.000 $290.000 $250.000 $319.000 $247.861 $325.000 $255.000 $321.000 $291.700 $275.930 $310.000 $413.000
VEH SIG SEC (12")LED(RED)
EA 39.000 $290.000 $250.000 $319.000 $247.861 $325.000 $255.000 $321.000 $291.700 $270.240 $310.000 $413.000
VEH SIG SEC (12")LED(RED ARW)
EA 12.000 $290.000 $250.000 $319.000 $247.861 $325.000 $255.000 $321.000 $291.700 $275.930 $310.000 $413.000
PED SIG SEC (LED)(COUNTDOWN)
EA 32.000 $600.000 $525.000 $720.000 $631.190 $700.000 $629.000 $762.000 $733.640 $653.070 $750.000 $1,994.000
BACKPLATE W/REFL BRDR(4 SEC)
EA 6.000 $225.000 $200.000 $190.000 $230.624 $125.000 $261.000 $230.000 $237.520 $127.140 $237.000 $137.000
BACKPLATE W/REFL BRDR(5 SEC)
EA 3.000 $275.000 $235.000 $240.000 $261.963 $150.000 $290.000 $270.000 $269.760 $146.470 $275.000 $210.000
BACKPLATE W/REFL BRDR(3 SEC)
EA 36.000 $180.000 $150.000 $140.000 $199.289 $115.000 $231.000 $180.000 $205.280 $113.470 $210.000 $122.000
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 10,325.000 $2.000 $2.100 $1.900 $1.553 $2.050 $2.200 $1.650 $1.430 $1.870 $1.900 $2.540
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 11,940.000 $2.800 $3.000 $2.560 $2.587 $3.250 $3.300 $2.420 $2.150 $3.080 $2.000 $3.540
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 10,220.000 $4.000 $4.400 $3.850 $3.828 $5.000 $4.700 $3.340 $3.830 $4.500 $3.000 $4.740
INS TRF SIG PL AM(S)1 ARM(50')
EA 1.000 $25,000.000 $26,000.000 $26,895.000 $29,882.038 $32,000.000 $25,512.000 $26,000.000 $31,288.810 $27,018.490 $30,000.000 $38,700.000
INS TRF SIG PL AM(S)1 ARM(55')LUM
EA 9.000 $28,000.000 $28,000.000 $31,303.000 $34,150.661 $36,000.000 $29,828.000 $29,000.000 $34,992.210 $31,744.910 $33,500.000 $43,640.000
INS TRF SIG PL AM(S)1 ARM(60')LUM
EA 1.000 $30,000.000 $29,500.000 $32,089.000 $35,130.028 $38,000.000 $30,692.000 $30,000.000 $36,388.610 $32,574.540 $36,500.000 $44,570.000
INS TRF SIG PL AM(S)1 ARM(65')LUM
EA 1.000 $40,000.000 $30,000.000 $32,680.000 $35,879.503 $38,500.000 $31,331.000 $31,000.000 $37,150.870 $33,276.730 $38,500.000 $45,356.000
PED POLE ASSEMBLY
EA 28.000 $2,000.000 $1,875.000 $1,850.000 $2,585.901 $3,250.000 $3,652.000 $2,300.000 $3,131.080 $2,376.590 $2,500.000 $1,445.000
PED DETECT PUSH BUTTON (APS)
EA 28.000 $800.000 $695.000 $726.000 $875.502 $1,700.000 $913.000 $810.000 $1,217.310 $881.820 $1,590.000 $1,042.000
PED DETECTOR CONTROLLER UNIT
EA 2.000 $3,500.000 $3,500.000 $3,465.000 $4,547.024 $5,000.000 $3,975.000 $2,900.000 $4,869.210 $3,189.350 $3,200.000 $4,756.000
SUBSURFACE UTIL LOCATE (NON-PAVED AREA)
EA 24.000 $500.000 $500.000 $1,100.000 $438.705 $500.000 $834.000 $425.000 $389.510 $198.980 $1,500.000 $2,000.000
BBU SYSTEM (EXTERNAL BATTERY CABINET)
EA 2.000 $8,000.000 $7,100.000 $8,929.000 $9,638.296 $8,000.000 $11,200.000 $7,000.000 $8,786.960 $7,992.730 $8,700.000 $21,823.000
RVDS (PRESENCE DETECTION ONLY)
EA 12.000 $6,000.000 $6,250.000 $9,883.000 $6,218.156 $11,000.000 $5,110.000 $5,000.000 $5,823.350 $6,861.770 $7,500.000 $7,804.000
RVDS (ADVANCE DETECTION ONLY)
EA 6.000 $6,000.000 $6,250.000 $8,249.250 $6,279.181 $8,500.000 $5,110.000 $5,200.000 $5,877.090 $6,947.940 $7,650.000 $7,804.000
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 2.000 $1,150.000 $4,500.000 $2,410.000 $836.046 $2,000.000 $441.000 $6,300.000 $724.690 $1,137.540 $1,200.000 $3,608.000
RELOCATE FIBER OPTIC CABLE
LF 70.000 $25.000 $2.000 $40.000 $6.268 $4.000 $24.200 $20.000 $17.280 $0.940 $15.000 $25.000
Totals: $1,692,028.040 $1,523,084.250 $1,585,073.210 $1,629,032.971 $1,640,060.300 $1,716,952.950 $1,755,250.860 $1,773,896.460 $1,822,552.910 $2,188,190.020 $2,485,895.410
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $15,000.00