HARRIS IH 10 (0508-01-354)

Items: 58

County: HARRIS
Length: N/A
Highway: IH 10
District: HOUSTON
Control Number: 0508-01-354
DBE Goal: N/A
Project: C 508-1-354
Guaranty: N/A
Time: 254 WORKING DAYS
Engineer's Estimate: $6,769,458.90
Date: 04/06/2022 (4 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (2)
E
Engineer's Estimate
$6,769,458.90
$5,653,887.52
Over/Under Est: -16.48% -$1,115,571.38
Over/Under Est: -8.42% -$570,282.68
Amt Left: 9.64% $545,288.70

Bid Items & Bid Tabulations

58 Total 0 of 58
HARRIS  |  IH 10  |  HOUSTON  |  0508-01-354  |  04/06/2022  |  $6,769,458.90  |  C 508-1-354  |  SURF/ROADWAY RESTOR  |  254 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SALV, HAUL & STKPL RCL APH PV (1 1/2")
SY 264,556.000 $3.800 $2.900 $3.680
ASPH (AC-20-5TR OR AC-20XP)
GAL 84,676.000 $5.000 $3.600 $5.050
AGGR (TY-B GR-4)
CY 2,066.000 $175.000 $125.000 $259.720
FLEX PAVEMENT STRUCTURE REPAIR (8"-12")
SY 5,000.000 $75.000 $85.000 $109.090
FULL - DEPTH REPAIR CRCP (10.5")
SY 500.000 $500.000 $371.000 $238.250
ADJUSTING MANHOLES & INLETS
EA 2.000 $1,485.000 $3,200.000 $2,553.080
MOBILIZATION
LS 1.000 $615,405.000 $440,000.000 $171,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $15,000.000 $2,200.000 $14,140.610
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 163,588.000 $0.350 $0.210 $0.290
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 384.000 $1.500 $1.550 $1.310
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 157.000 $3.000 $2.050 $2.380
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 8.000 $77.000 $41.000 $113.170
WK ZN PAV MRK NON-REMOV (W)(DBL ARW)
EA 22.000 $150.000 $86.000 $131.040
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 8.000 $85.000 $46.000 $113.170
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 162,183.000 $0.350 $0.210 $0.300
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 3,025.000 $1.650 $1.550 $1.520
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 2,170.000 $1.700 $1.550 $1.610
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,048.000 $1.250 $1.500 $2.870
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 13,984.000 $1.000 $0.820 $1.160
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 1,244.000 $3.000 $3.300 $2.560
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 386.000 $6.500 $6.600 $7.000
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 6,238.000 $2.000 $0.820 $1.160
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 3,232.000 $2.600 $3.300 $2.560
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 17,678.000 $0.800 $0.820 $0.740
REFL PAV MRK TY II (W) 6" (BRK)
LF 17,678.000 $0.700 $0.360 $0.290
REFL PAV MRK TY II (W) 6" (SLD)
LF 92,360.000 $0.700 $0.360 $0.260
REFL PAV MRK TY II (W) 8" (SLD)
LF 13,984.000 $1.500 $0.520 $0.710
REFL PAV MRK TY II (W) 12" (SLD)
LF 1,244.000 $2.250 $0.760 $1.490
REFL PAV MRK TY II (W) 24" (SLD)
LF 386.000 $4.150 $1.300 $2.380
REFL PAV MRK TY II (Y) 6" (SLD)
LF 76,463.000 $0.700 $0.360 $0.260
REFL PAV MRK TY II (Y) 8" (SLD)
LF 6,238.000 $1.750 $0.520 $0.770
REFL PAV MRK TY II (Y) 12" (SLD)
LF 3,232.000 $2.250 $0.760 $1.490
REFL PAV MRK TY II (BLACK) 6"(SHADOW)
LF 17,678.000 $0.600 $0.420 $0.330
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 17,678.000 $0.700 $0.460 $0.620
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 92,360.000 $0.550 $0.440 $0.620
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 76,463.000 $0.550 $0.440 $0.620
PREFAB PAV MRK TY C (W) (ARROW)
EA 13.000 $280.000 $205.000 $228.720
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 9.000 $485.000 $355.000 $446.710
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 12.000 $485.000 $355.000 $452.670
PREFAB PAV MRK TY C (W) (WORD)
EA 19.000 $365.000 $230.000 $321.630
PREFAB PAV MRK TY C (W) (EXIT GORE)
EA 4.000 $3,300.000 $810.000 $655.180
REFL PAV MRKR TY I-A
EA 260.000 $7.000 $5.600 $5.960
REFL PAV MRKR TY II-C-R
EA 1,567.000 $4.500 $5.100 $5.960
ELIM EXT PAV MRK & MRKS (6")
LF 80,712.000 $0.300 $0.210 $0.260
ELIM EXT PAV MRK & MRKS (8")
LF 4,364.000 $0.580 $0.310 $0.390
ELIM EXT PAV MRK & MRKS (12")
LF 4,610.000 $1.100 $0.620 $0.540
ELIM EXT PAV MRK & MRKS (ARROW)
EA 6.000 $37.000 $36.000 $29.780
ELIM EXT PAV MRK & MRKS (WORD)
EA 4.000 $39.000 $41.000 $29.780
ELIM EXT PAV MRK & MRKS (ENTR GORE)
EA 14.000 $330.000 $186.000 $29.780
ELIM EXT PAV MRK & MRKS (EXIT GORE)
EA 12.000 $330.000 $186.000 $29.780
PAV SURF PREP FOR MRK (6")
LF 300.000 $0.050 $0.020 $0.020
PAV SURF PREP FOR MRK (8")
LF 442.000 $0.090 $0.040 $0.040
PAV SURF PREP FOR MRK (12")
LF 435.000 $0.110 $0.070 $0.040
PAV SURF PREP FOR MRK (24")
LF 95.000 $0.200 $0.120 $0.060
PAV SURF PREP FOR MRK (ARROW)
EA 4.000 $4.850 $5.100 $5.960
PAV SURF PREP FOR MRK (DBL ARROW)
EA 2.000 $15.000 $10.200 $5.960
PAV SURF PREP FOR MRK (UTURN ARR)
EA 1.000 $15.000 $10.200 $5.960
SP MIXES SP-D SAC-A PG70-22
TON 19,873.000 $150.000 $145.000 $141.870
Totals: $6,769,458.900 $5,653,887.520 $6,199,176.220