HARRIS IH 45 (0500-03-665)

Items: 39

County: HARRIS
Length: 0.0000 MILES
Highway: IH 45
District: HOUSTON
Control Number: 0500-03-665
DBE Goal: 0.0%
Project: F 2B25(335)
Guaranty: $62,000.00
Time: 82 WORKING DAYS
Engineer's Estimate: $3,094,755.46
Date: 12/03/2025 (6 months ago)
Contract Number: 12253207
Type: LANDSCAPE DEVELOPMENT
Project ID: A00217521
Contract Type: Federal
Project Description: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
JAMAL ELAHI
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$3,094,755.46
Over/Under Est: -27.05% -$837,161.45
Over/Under Est: -23.41% -$724,580.22
Amt Left: 4.99% $112,581.23
$3,196,353.35
Over/Under Est: 3.28% $101,597.89
Amt Left: 41.58% $938,759.34
Delta: -34.86% -$826,178.11
$3,586,118.00
Over/Under Est: 15.88% $491,362.54
Amt Left: 58.85% $1,328,523.99
Delta: -12.19% -$389,764.65

Bid Items & Bid Tabulations

39 Total 0 of 39
HARRIS  |  IH 45  |  HOUSTON  |  0500-03-665  |  12/03/2025  |  $3,094,755.46  |  F 2B25(335)  |  LANDSCAPE DEVELOPMENT  |  82 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
CENTRAL NORTH CONSTRUCTION, LLC
TEXAS WALL & LANDSCAPE
JFO SERVICES, LLC
PREP ROW (TREE REMOVE) (0"-12" DIA)
EA 78.000 $750.000 $341.880 $200.000 $350.000 $515.570
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 78.000 $1,050.000 $982.906 $300.000 $500.000 $832.940
PREP ROW (TREE REMOVE) (24"-36" DIA)
EA 78.000 $1,550.000 $1.033 $400.000 $800.000 $1,106.160
FURN & PLACE TOPSOIL (VEH)
CY 390.000 $45.000 $68.376 $40.000 $80.000 $77.570
EROSION CONTROL COMPOST (VEH)
CY 926.500 $30.000 $44.073 $40.000 $45.000 $77.570
GENERAL USE COMPOST (VEH)
CY 444.250 $30.000 $45.020 $40.000 $60.000 $77.570
BLOCK SODDING
SY 720.000 $6.000 $5.787 $6.000 $10.000 $7.760
FERTILIZER
AC 0.149 $1,258.000 $1,454.139 $1,500.000 $2,400.000 $5,206.650
VEGETATIVE WATERING
TGL 17.880 $42.000 $60.589 $25.000 $200.000 $258.600
SOIL AMEND (TY I)
SY 7,200.000 $0.150 $0.246 $0.500 $0.500 $8.790
PLANT BED PREP (TY III)
SY 7,200.000 $0.500 $0.463 $1.500 $8.000 $5.180
PLANT MATERIAL (3 GAL)
EA 364.000 $21.000 $31.136 $25.000 $40.000 $56.890
PLANT MATERIAL (30 GAL) (TREE)
EA 762.000 $300.000 $170.604 $225.000 $300.000 $429.270
PLANT MATERIAL (45 GAL) (TREE)
EA 107.000 $500.000 $514.019 $500.000 $520.000 $646.490
PLANT MATERIAL (65 GAL) (TREE)
EA 788.000 $650.000 $592.217 $550.000 $700.000 $739.590
PLANT MATERIAL (MIN 10' TRNK HT)(PALM)
EA 20.000 $1,150.000 $1,041.667 $1,200.000 $1,650.000 $1,499.870
PLANT MATERIAL (MIN 12' TRNK HT)(PALM)
EA 20.000 $1,450.000 $1,166.667 $1,800.000 $1,880.000 $1,706.750
PLANT MATERIAL (MIN 14' TRNK HT)(PALM)
EA 21.000 $1,700.000 $1,269.841 $2,100.000 $2,300.000 $1,913.630
SOIL AMEND (TY II)
SY 7,200.000 $0.130 $0.145 $0.500 $0.500 $3.160
LANDSCAPE ESTABLISH
MO 18.000 $3,850.000 $6,666.667 $10,000.000 $22,000.000 $22,239.380
LANDSCAPE ESTABLISH
CYC 4.000 $47,500.000 $66,666.667 $20,000.000 $27,000.000 $8,792.320
LANDSCAPE TREAT (TY I)
EA 1,657.000 $1.000 $1.084 $4.000 $11.000 $15.520
LANDSCAPE TREAT (TY II)
EA 8,285.000 $0.350 $0.335 $4.000 $11.000 $15.520
LANDSCAPE TREAT (TY II)
CYC 2.000 $8,800.000 $13,033.333 $25,000.000 $23,000.000 $12,929.870
LANDSCAPE TREAT (TY III)
EA 2,021.000 $2.000 $3.165 $1.000 $0.250 $20.690
LANDSCAPE TREAT (TY IV)
EA 788.000 $75.000 $48.933 $180.000 $120.000 $87.920
LANDSCAPE TREAT (TY V)
EA 869.000 $55.000 $36.700 $150.000 $115.000 $67.240
LANDSCAPE TREAT (TY VI)
EA 1,657.000 $45.000 $2.414 $15.000 $70.000 $36.200
LANDSCAPE TREAT (TY VII)
EA 1,657.000 $1.250 $23.933 $5.000 $75.000 $20.690
LANDSCAPE TREAT (TY IX)
EA 117.000 $125.000 $123.000 $250.000 $480.000 $77.570
LANDSCAPE TREAT (TY X)
EA 117.000 $250.000 $239.658 $300.000 $680.000 $181.020
LANDSCAPE TREAT (TY III)
CYC 4.000 $90,500.000 $45,833.333 $18,000.000 $16,000.000 $22,756.570
LANDSCAPE TREAT (TY VII)
CYC 252.000 $2,250.000 $628.307 $685.000 $1,100.000 $2,120.500
MOBILIZATION
LS 1.000 $279,384.560 $217,563.531 $165,005.740 $130,000.000 $349,961.630
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $6,500.000 $2,393.333 $67,250.000 $14,000.000 $19,181.460
TMA (STATIONARY)
DAY 110.000 $900.000 $1,230.000 $200.000 $1,200.000 $181.020
TMA (MOBILE OPERATION)
DAY 25.000 $750.000 $1,230.000 $500.000 $800.000 $501.160
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 2,050.000 $3.500 $2.668 $0.100 $4.500 $8.280
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,050.000 $1.000 $0.325 $0.100 $2.000 $4.130
Totals: $3,094,755.462 $2,257,593.998 $2,370,175.240 $3,196,353.350 $3,586,117.996