HARRIS IH 45 (0500-03-655)
Items: 28
County: HARRIS
Length: 0.0000 MILES
Highway: IH 45
District: HOUSTON
Control Number: 0500-03-655
DBE Goal: 0.0%
Project: BR 2026(508)
Guaranty: $100,000.00
Time: 56 WORKING DAYS
Engineer's Estimate: $8,850,867.80
Date: 05/07/2026 (4 weeks ago)
Contract Number: 5263209
Type: REHABILITATE BRIDGE
Project ID: A00208023
Contract Type: Federal
Project Description: REPLACE BENT CAP FOR SB MCKINNEY EXIT RAMP NBI NO.121020050003210
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMAL ELAHI
VANESSA BOSQUES
HARRIS IH 45 (0500-03-655)
Project Name: N/A
Project: BR 2026(508)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: AT MCKINNEY RAMP
Limits To: .
Project Description: REPLACE BENT CAP FOR SB MCKINNEY EXIT RAMP NBI NO.121020050003210
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$8,850,867.80 | |||
| $3,899,831.00 |
-55.94%
-$4,951,036.80
|
|||
| $4,350,329.20 |
-50.85%
-$4,500,538.60
|
11.55%
$450,498.20
|
||
| $4,353,529.00 |
-50.81%
-$4,497,338.80
|
11.63%
$453,698.00
|
-0.07%
-$3,199.80
|
|
| $7,151,051.00 |
-19.21%
-$1,699,816.80
|
83.37%
$3,251,220.00
|
-64.26%
-$2,797,522.00
|
|
| $7,384,087.00 |
-16.57%
-$1,466,780.80
|
89.34%
$3,484,256.00
|
-3.26%
-$233,036.00
|
|
| $7,684,676.49 |
-13.18%
-$1,166,191.31
|
97.05%
$3,784,845.49
|
-4.07%
-$300,589.49
|
|
| $10,546,202.00 |
19.15%
$1,695,334.20
|
170.43%
$6,646,371.00
|
-37.24%
-$2,861,525.51
|
|
| $23,883,149.70 |
169.84%
$15,032,281.90
|
512.41%
$19,983,318.70
|
-126.46%
-$13,336,947.70
|
E
Engineer's Estimate
$8,850,867.80
1
Awarded
$3,899,831.00
Over/Under Est:
-55.94%
-$4,951,036.80
$4,350,329.20
Over/Under Est:
-50.85%
-$4,500,538.60
Amt Left:
11.55%
$450,498.20
$4,353,529.00
Over/Under Est:
-50.81%
-$4,497,338.80
Amt Left:
11.63%
$453,698.00
Delta:
-0.07%
-$3,199.80
$7,151,051.00
Over/Under Est:
-19.21%
-$1,699,816.80
Amt Left:
83.37%
$3,251,220.00
Delta:
-64.26%
-$2,797,522.00
$7,384,087.00
Over/Under Est:
-16.57%
-$1,466,780.80
Amt Left:
89.34%
$3,484,256.00
Delta:
-3.26%
-$233,036.00
$7,684,676.49
Over/Under Est:
-13.18%
-$1,166,191.31
Amt Left:
97.05%
$3,784,845.49
Delta:
-4.07%
-$300,589.49
$10,546,202.00
Over/Under Est:
19.15%
$1,695,334.20
Amt Left:
170.43%
$6,646,371.00
Delta:
-37.24%
-$2,861,525.51
$23,883,149.70
Over/Under Est:
169.84%
$15,032,281.90
Amt Left:
512.41%
$19,983,318.70
Delta:
-126.46%
-$13,336,947.70
Bid Items & Bid Tabulations
28
Total
0 of 28
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $20,000.00 |