HARRIS IH 45 (0500-03-655)

Items: 28

County: HARRIS
Length: 0.0000 MILES
Highway: IH 45
District: HOUSTON
Control Number: 0500-03-655
DBE Goal: 0.0%
Project: BR 2026(508)
Guaranty: $100,000.00
Time: 56 WORKING DAYS
Engineer's Estimate: $8,850,867.80
Date: 05/07/2026 (4 weeks ago)
Contract Number: 5263209
Type: REHABILITATE BRIDGE
Project ID: A00208023
Contract Type: Federal
Project Description: REPLACE BENT CAP FOR SB MCKINNEY EXIT RAMP NBI NO.121020050003210
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMAL ELAHI
VANESSA BOSQUES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$8,850,867.80
$3,899,831.00
Over/Under Est: -55.94% -$4,951,036.80
Over/Under Est: -50.85% -$4,500,538.60
Amt Left: 11.55% $450,498.20
Over/Under Est: -50.81% -$4,497,338.80
Amt Left: 11.63% $453,698.00
Delta: -0.07% -$3,199.80
Over/Under Est: -19.21% -$1,699,816.80
Amt Left: 83.37% $3,251,220.00
Delta: -64.26% -$2,797,522.00
Over/Under Est: -16.57% -$1,466,780.80
Amt Left: 89.34% $3,484,256.00
Delta: -3.26% -$233,036.00
$7,684,676.49
Over/Under Est: -13.18% -$1,166,191.31
Amt Left: 97.05% $3,784,845.49
Delta: -4.07% -$300,589.49
Over/Under Est: 19.15% $1,695,334.20
Amt Left: 170.43% $6,646,371.00
Delta: -37.24% -$2,861,525.51
$23,883,149.70
Over/Under Est: 169.84% $15,032,281.90
Amt Left: 512.41% $19,983,318.70
Delta: -126.46% -$13,336,947.70

Bid Items & Bid Tabulations

28 Total 0 of 28
HARRIS  |  IH 45  |  HOUSTON  |  0500-03-655  |  05/07/2026  |  $8,850,867.80  |  BR 2026(508)  |  REHAB BRIDGE  |  56 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MC2 CIVIL, LLC
GIBSON & ASSOCIATES, INC.
RAGLE CONSTRUCTION, INC.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
STRUCTURAL INTEGRITY GROUP LLC
ALTUS CONSTRUCTION LLC
R CONSTRUCTION CIVIL, LLC
ISI CONTRACTING, INC.
REMOV CONC (RIPRAP)
CY 4.000 $60.000 $700.000 $2,250.000 $500.000 $1,000.000 $100.000 $266.360 $1,000.000 $20,771.000
FLOWABLE BACKFILL
CY 4.000 $100.000 $1,200.000 $1,500.000 $1,500.000 $1,000.000 $1,125.000 $853.978 $3,000.000 $14,426.000
DRILL SHAFT (42 IN)
LF 380.000 $360.000 $3,150.000 $2,440.000 $1,300.000 $5,500.000 $2,130.000 $6,370.821 $3,300.000 $8,952.000
CL C CONC (CAP)
CY 18.400 $2,100.000 $4,000.000 $5,040.000 $2,300.000 $7,500.000 $2,020.000 $2,721.358 $7,000.000 $14,992.000
CL C CONC (COLUMN)
CY 21.400 $2,000.000 $3,000.000 $5,040.000 $1,800.000 $7,500.000 $1,470.000 $3,104.745 $5,000.000 $11,205.000
CLASS K CONCRETE (MISC)
CY 4.600 $5,000.000 $5,000.000 $3,700.000 $3,650.000 $25,000.000 $5,000.000 $3,049.829 $7,000.000 $63,480.000
RIPRAP (CONC)(4 IN)
CY 4.000 $1,600.000 $600.000 $2,500.000 $1,950.000 $4,000.000 $2,000.000 $890.046 $1,500.000 $21,941.000
ELASTOMERIC BEARING (LAMINATED)
EA 10.000 $5,000.000 $1,000.000 $1,250.000 $2,500.000 $25,000.000 $2,000.000 $11,083.477 $7,500.000 $2,652.000
STR STEEL (BOX GIRDER)
LB 68,980.000 $60.000 $11.950 $21.000 $8.350 $25.000 $22.000 $14.688 $13.000 $34.000
ARMOR JOINT (SEALED)
LF 60.000 $235.000 $200.000 $219.000 $141.000 $1,000.000 $355.000 $12,761.877 $225.000 $460.000
SUPPORT EXIST STRUCT
LS 1.000 $600,000.000 $200,000.000 $412,500.000 $1,535,000.000 $500,000.000 $2,220,000.000 $419,089.338 $2,200,000.000 $3,064,209.000
REMOV STR (BENT)
EA 1.000 $900,000.000 $50,000.000 $197,500.000 $535,000.000 $250,000.000 $180,000.000 $362,626.317 $1,000,000.000 $407,862.000
MOBILIZATION
LS 1.000 $720,000.000 $390,000.000 $400,000.000 $430,000.000 $700,000.000 $1,563,000.000 $764,628.546 $1,100,000.000 $2,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $400,000.000 $202,000.000 $218,750.000 $120,000.000 $20,000.000 $163,000.000 $192,117.725 $1,250,000.000 $5,170,581.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 1,968.000 $500.000 $100.000 $25.000 $55.000 $250.000 $60.000 $200.936 $200.000 $282.000
TMA (STATIONARY)
DAY 528.000 $500.000 $250.000 $100.000 $200.000 $300.000 $250.000 $803.744 $350.000 $404.000
TMA (MOBILE OPERATION)
DAY 300.000 $200.000 $800.000 $150.000 $300.000 $750.000 $825.000 $304.739 $1,000.000 $1,120.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 420.000 $32.000 $25.000 $57.000 $50.000 $100.000 $61.000 $212.972 $100.000 $29.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 420.000 $32.000 $10.000 $52.000 $18.000 $100.000 $61.000 $212.972 $100.000 $19.000
PORT CTB (CONNECTION HARDWARE)
EA 14.000 $40.000 $50.000 $200.000 $100.000 $1,000.000 $100.000 $401.872 $3,000.000 $205.000
CCA (INSTL)(N)(TL3)(WORK ZONE)
EA 1.000 $30,000.000 $30,000.000 $29,000.000 $25,000.000 $75,000.000 $38,500.000 $153,134.614 $150,000.000 $41,263.000
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
EA 1.000 $1,500.000 $1,000.000 $600.000 $500.000 $3,000.000 $500.000 $1,004.680 $1,500.000 $1,063.000
RE PM TY II (Y) 6" (SLD)
LF 3,410.000 $1.400 $0.700 $2.400 $2.000 $2.500 $2.000 $6.711 $2.000 $1.300
RE PM TY III (W)(6")(BRK)
LF 748.000 $2.200 $3.000 $8.400 $7.000 $6.000 $7.000 $16.758 $3.000 $1.300
RE PM TY III (BLK)(6")(SHADOW)
LF 748.000 $1.400 $3.000 $8.400 $7.000 $6.000 $7.000 $16.758 $5.000 $2.700
REFL PAV MRKR TY II-C-R
EA 38.000 $4.500 $7.500 $12.000 $10.000 $15.000 $10.000 $20.093 $1.000 $9.300
ELIM EXT PM & MRKS (6")
LF 360.000 $1.000 $1.000 $2.280 $1.900 $3.000 $1.900 $6.510 $2.000 $1.700
CONCRETE RAIL REPLACEMENT (IN-KIND)
LF 9.500 $500.000 $2,000.000 $1,220.000 $2,000.000 $3,000.000 $1,550.000 $411.557 $5,000.000 $5,735.000
Totals: $8,850,867.800 $3,899,831.000 $4,350,329.200 $4,353,529.000 $7,151,051.000 $7,384,087.000 $7,684,676.506 $10,546,202.000 $23,883,149.700
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $20,000.00