HARRIS IH 69 (0177-11-167)

Items: 33

County: HARRIS
Length: 0.0000 MILES
Highway: IH 69
District: HOUSTON
Control Number: 0177-11-167
DBE Goal: 0.0%
Project: F 2025(928)
Guaranty: $45,000.00
Time: 135 WORKING DAYS
Engineer's Estimate: $2,247,555.26
Date: 08/08/2025 (10 months ago)
Contract Number: 8253214
Type: LANDSCAPE DEVELOPMENT
Project ID: A00211270
Contract Type: Federal
Project Description: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMAL ELAHI
VANESSA BOSQUES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$2,247,555.26
$1,815,000.00
Over/Under Est: -19.25% -$432,555.26
Over/Under Est: -18.39% -$413,231.16
Amt Left: 1.06% $19,324.10
Over/Under Est: -2.32% -$52,077.76
Amt Left: 20.96% $380,477.50
Delta: -19.69% -$361,153.40
$2,375,769.50
Over/Under Est: 5.7% $128,214.24
Amt Left: 30.9% $560,769.50
Delta: -8.21% -$180,292.00
Over/Under Est: 26.23% $589,621.23
Amt Left: 56.32% $1,022,176.49
Delta: -19.42% -$461,406.99

Bid Items & Bid Tabulations

33 Total 0 of 33
HARRIS  |  IH 69  |  HOUSTON  |  0177-11-167  |  08/08/2025  |  $2,247,555.26  |  F 2025(928)  |  LANDSCAPE DEVELOPMENT  |  135 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CENTRAL NORTH CONSTRUCTION, LLC
APEX LANDSCAPE & IRRIGATION, LLC
GREEN SAGE SERVICES LLC
TEXAS WALL & LANDSCAPE
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
FURN & PLACE TOPSOIL (VEH)
CY 118.000 $45.000 $35.000 $50.000 $55.000 $250.000 $152.542
EROSION CONTROL COMPOST (VEH)
CY 387.500 $22.000 $35.000 $40.000 $44.000 $156.000 $98.065
GENERAL USE COMPOST (VEH)
CY 193.750 $25.000 $35.000 $36.000 $50.000 $165.000 $103.199
BLOCK SODDING
SY 100.000 $4.500 $8.000 $5.000 $6.000 $60.000 $12.000
FERTILIZER
AC 0.020 $1,800.000 $65,000.000 $3,000.000 $3,500.000 $35,000.000 $2,800.000
VEGETATIVE WATERING
TGL 2.400 $36.000 $400.000 $35.000 $2,000.000 $850.000 $83.333
SOIL AMEND (TY I)
SY 3,100.000 $0.150 $2.000 $0.450 $0.650 $0.500 $0.839
PLANT BED PREP (TY III)
SY 3,100.000 $1.250 $10.000 $4.000 $5.500 $20.000 $6.452
LANDSCAPE EDGE
LF 30,986.000 $12.000 $5.500 $8.850 $15.500 $15.000 $14.523
PLANT MATERIAL (30 GAL)
EA 400.000 $425.000 $600.000 $330.000 $360.000 $356.000 $250.000
PLANT MATERIAL (65 GAL)
EA 204.000 $950.000 $750.000 $660.000 $670.000 $666.000 $1,053.922
PLANT MATERIAL (30 GAL) (TREE)
EA 72.000 $425.000 $550.000 $330.000 $360.000 $356.000 $222.222
PLANT MATERIAL (65 GAL) (TREE)
EA 48.000 $950.000 $750.000 $660.000 $670.000 $666.000 $1,050.000
PLANT MATERIAL (200 GAL) (TREE)
EA 51.000 $3,800.000 $2,500.000 $2,695.000 $2,300.000 $2,100.000 $3,686.275
SOIL AMEND (TY II)
SY 3,100.000 $0.200 $2.000 $0.400 $0.750 $0.200 $0.419
LANDSCAPE ESTABLISH (LOC A)
MO 20.000 $10,000.000 $15,000.000 $2,650.000 $3,500.000 $4,700.000 $1,600.000
LANDSCAPE ESTABLISH (LOC B)
MO 12.000 $10,000.000 $10,000.000 $2,800.000 $3,500.000 $4,800.000 $1,666.667
LANDSCAPE TREAT (TY I)
EA 775.000 $1.250 $4.000 $4.000 $2.850 $5.500 $1.419
LANDSCAPE TREAT (TY II)
EA 2,325.000 $0.300 $4.000 $4.000 $1.000 $5.500 $0.439
LANDSCAPE TREAT (TY III)
EA 775.000 $2.250 $4.000 $1.000 $2.550 $0.250 $0.465
LANDSCAPE TREAT (TY IV)
EA 472.000 $55.000 $50.000 $120.000 $48.000 $88.000 $67.797
LANDSCAPE TREAT (TY V)
EA 252.000 $75.000 $60.000 $150.000 $65.000 $100.000 $95.238
LANDSCAPE TREAT (TY VI)
EA 51.000 $115.000 $70.000 $180.000 $95.000 $167.000 $156.863
LANDSCAPE TREAT (TY VII)
EA 775.000 $45.000 $15.000 $40.000 $40.000 $14.000 $15.484
LANDSCAPE TREAT (TY VIII)
EA 604.000 $1.250 $5.000 $12.480 $22.000 $17.000 $17.219
LANDSCAPE TREAT (TY IX)
EA 171.000 $1.250 $5.000 $12.480 $28.000 $32.000 $38.596
LANDSCAPE TREAT (TY VI)
CYC 276.000 $568.680 $700.000 $1,100.000 $1,080.000 $1,000.000 $2,323.603
LANDSCAPE TREAT (TY VII)
CYC 192.000 $666.290 $400.000 $1,100.000 $950.000 $1,000.000 $1,364.583
MOBILIZATION
LS 1.000 $219,100.000 $74,210.250 $182,500.000 $145,000.000 $200,000.000 $284,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $12,000.000 $6,852.000 $12,500.000 $12,500.000 $15,000.000 $7,111.111
TMA (STATIONARY)
DAY 270.000 $700.000 $250.000 $0.100 $880.000 $700.000 $1,155.556
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,500.000 $3.500 $6.250 $1.500 $6.000 $5.000 $3.333
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,500.000 $1.000 $1.000 $0.250 $2.000 $2.000 $0.413
Totals: $2,247,555.260 $1,815,000.000 $1,834,324.100 $2,195,477.500 $2,375,769.500 $2,837,176.451
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $875.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $12,600.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $14,475.00