HARRIS US 290 (0114-12-017)
Items: 57
County: HARRIS
Length: 0.0970 MILES
Highway: US 290
District: HOUSTON
Control Number: 0114-12-017
DBE Goal: 0.0%
Project: C 114-12-17
Guaranty: $39,000.00
Time: 75 WORKING DAYS
Engineer's Estimate: $1,925,151.90
Date: 12/03/2024 (1 year ago)
Contract Number: 12243018
Type: TRANSPORTATION NON-ROADWAY
Project ID: A00198078
Project Description: CONSTRUCT TRUCK PARKING
Mail/Deliver Bids To: N/A
HAMOON BAHRAMI
HARRIS US 290 (0114-12-017)
Project Name: N/A
Project: C 114-12-17
Length: 0.0970 MILES
Project Type: TRANSPORTATION NON-ROADWAY
Limits From: AT FM 2920
Limits To: .
Project Description: CONSTRUCT TRUCK PARKING
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,925,151.90 | |||
| $1,523,997.55 |
-20.84%
-$401,154.35
|
|||
| $1,557,772.00 |
-19.08%
-$367,379.90
|
2.22%
$33,774.45
|
||
| $1,577,252.05 |
-18.07%
-$347,899.85
|
3.49%
$53,254.50
|
-1.25%
-$19,480.05
|
|
| $1,718,162.40 |
-10.75%
-$206,989.50
|
12.74%
$194,164.85
|
-8.93%
-$140,910.35
|
|
| $1,796,593.00 |
-6.68%
-$128,558.90
|
17.89%
$272,595.45
|
-4.56%
-$78,430.60
|
|
| $1,805,000.00 |
-6.24%
-$120,151.90
|
18.44%
$281,002.45
|
-0.47%
-$8,407.00
|
E
Engineer's Estimate
$1,925,151.90
1
Awarded
$1,523,997.55
Over/Under Est:
-20.84%
-$401,154.35
$1,557,772.00
Over/Under Est:
-19.08%
-$367,379.90
Amt Left:
2.22%
$33,774.45
$1,577,252.05
Over/Under Est:
-18.07%
-$347,899.85
Amt Left:
3.49%
$53,254.50
Delta:
-1.25%
-$19,480.05
$1,718,162.40
Over/Under Est:
-10.75%
-$206,989.50
Amt Left:
12.74%
$194,164.85
Delta:
-8.93%
-$140,910.35
$1,796,593.00
Over/Under Est:
-6.68%
-$128,558.90
Amt Left:
17.89%
$272,595.45
Delta:
-4.56%
-$78,430.60
$1,805,000.00
Over/Under Est:
-6.24%
-$120,151.90
Amt Left:
18.44%
$281,002.45
Delta:
-0.47%
-$8,407.00
Bid Items & Bid Tabulations
57
Total
0 of 57