HARRIS IH 45 (0110-06-144)
Items: 68
County: HARRIS
Length: N/A
Highway: IH 45
District: HOUSTON
Control Number: 0110-06-144
DBE Goal: N/A
Project: STP 2021(187)HES
Guaranty: N/A
Time: 137 WORKING DAYS
Engineer's Estimate: $1,252,362.53
Date: 12/03/2020 (5 years ago)
Contract Number: N/A
Type: INSTALL ADVANCED WARNING SIGNALS AND SIGNS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,252,362.53 | |||
| $1,115,889.75 |
-10.9%
-$136,472.78
|
|||
| $1,198,888.88 |
-4.27%
-$53,473.65
|
7.44%
$82,999.13
|
||
| $1,199,126.59 |
-4.25%
-$53,235.94
|
7.46%
$83,236.84
|
-0.02%
-$237.71
|
|
| $1,373,150.82 |
9.64%
$120,788.29
|
23.05%
$257,261.07
|
-14.51%
-$174,024.23
|
|
| $1,452,615.66 |
15.99%
$200,253.13
|
30.18%
$336,725.91
|
-5.79%
-$79,464.84
|
|
| $1,552,471.94 |
23.96%
$300,109.41
|
39.12%
$436,582.19
|
-6.87%
-$99,856.28
|
E
Engineer's Estimate
$1,252,362.53
1
Awarded
$1,115,889.75
Over/Under Est:
-10.9%
-$136,472.78
$1,198,888.88
Over/Under Est:
-4.27%
-$53,473.65
Amt Left:
7.44%
$82,999.13
$1,199,126.59
Over/Under Est:
-4.25%
-$53,235.94
Amt Left:
7.46%
$83,236.84
Delta:
-0.02%
-$237.71
$1,373,150.82
Over/Under Est:
9.64%
$120,788.29
Amt Left:
23.05%
$257,261.07
Delta:
-14.51%
-$174,024.23
$1,452,615.66
Over/Under Est:
15.99%
$200,253.13
Amt Left:
30.18%
$336,725.91
Delta:
-5.79%
-$79,464.84
$1,552,471.94
Over/Under Est:
23.96%
$300,109.41
Amt Left:
39.12%
$436,582.19
Delta:
-6.87%
-$99,856.28
| Subcontractor | Percentage | Amount |
|---|---|---|
| REDLINE CONSTRUCTION SERVICES LLC | 3.40% | $67,494.65 |
| PROFESSIONAL TRAFFIC CONTROL LLC | 1.65% | $32,754.76 |
| Total: | 5.05% | $100,249.41 |
Bid Items & Bid Tabulations
68