HARRIS IH 45 (0110-05-136)

Items: 24

County: HARRIS
Length: 1.2530 MILES
Highway: IH 45
District: HOUSTON
Control Number: 0110-05-136
DBE Goal: 0.0%
Project: F 2026(600)
Guaranty: $20,000.00
Time: 19 WORKING DAYS
Engineer's Estimate: $1,080,682.20
Date: 05/07/2026 (4 weeks ago) Changed
Contract Number: 5263031
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00140550
Contract Type: Federal
Project Description: CLEAN AND SEAL JOINTS, FULL DEPTH REPAIR (CONTINUOUSLY REINFORCED CONCRETE PAVEMENT), METAL BEAM GUARD FENCE, AND PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
PHILLIP GARLIN
NYEMB NYEMB
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$1,080,682.20
$798,249.46
Over/Under Est: -26.13% -$282,432.74
$850,333.00
Over/Under Est: -21.32% -$230,349.20
Amt Left: 6.52% $52,083.54

Bid Items & Bid Tabulations

24 Total 0 of 24
HARRIS  |  IH 45  |  HOUSTON  |  0110-05-136  |  05/07/2026  |  $1,080,682.20  |  F 2026(600)  |  SURF/ROADWAY RESTOR  |  19 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
MC2 CIVIL, LLC
REMOV CONC (MOWSTRIP)
SY 156.000 $32.000 $32.000 $35.000
FULL - DEPTH REPAIR CRCP (14")
CY 534.000 $1,100.000 $760.000 $990.000
RIPRAP (MOW STRIP)(4 IN)
CY 19.000 $800.000 $450.000 $900.000
CLEANING AND SEALING EXISTING JOINTS
LF 6,437.000 $32.000 $15.000 $15.000
MOBILIZATION
LS 1.000 $88,340.200 $50,000.000 $40,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $10,000.000 $13,500.000 $2,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $15,000.000 $5,000.000
TMA (STATIONARY)
DAY 12.000 $220.000 $6,800.000 $250.000
TMA (MOBILE OPERATION)
DAY 2.000 $170.000 $1,500.000 $600.000
MTL W-BEAM GD FEN (TIM POST)
LF 175.000 $26.000 $15.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 3.000 $1,700.000 $1,340.000 $1,975.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,400.000 $1,003.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 175.000 $5.000 $1.000 $3.500
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $350.000 $6.000 $240.000
RM MTL BM GD FENCE TRANS (TL-2)
EA 2.000 $160.500 $6.000 $280.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,400.000 $2,507.000 $4,050.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $300.000 $11.000 $360.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $2,500.000 $5.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 12.000 $25.000 $48.450 $33.000
RE PM TY III (W)(6")(SLD)
LF 6,130.000 $1.500 $2.110 $2.500
RE PM TY III (W)(8")(SLD)
LF 235.000 $2.000 $4.230 $5.000
PREFAB PM TY B (W)(6")(BRK)CONTRAST
LF 850.000 $10.000 $21.130 $25.000
REFL PAV MRKR TY II-C-R
EA 53.000 $5.000 $10.570 $16.500
SPALLING REPAIR (POLYMERIC) (SEMIRIGID)
GAL 1,591.000 $60.000 $25.000 $45.000
Totals: $1,080,682.200 $798,249.460 $850,333.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $7,000.00