Show Job Controls
Bid Cobra

HARRIS SH 3 (0051-02-108)

Items: 105

County: HARRIS
Length: N/A
Highway: SH 3
District: HOUSTON
Control Number: 0051-02-108
DBE Goal: N/A
Project: STP 2022(405)HES
Guaranty: N/A
Time: 223 WORKING DAYS
Engineer's Estimate: $5,618,935.99
Date: 03/04/2022 (4 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$5,618,935.99
$5,450,259.58
Over/Under Est: -3% -$168,676.41
Over/Under Est: 23.97% $1,346,976.31
Amt Left: 27.81% $1,515,652.72
$7,013,146.14
Over/Under Est: 24.81% $1,394,210.15
Amt Left: 28.68% $1,562,886.56
Delta: -0.68% -$47,233.84
Subcontractor Percentage Amount
GMJ PAVING CO. 14.04% $951,978.01
TRAFFIC SIGNS & LINES, LLC 11.28% $764,837.03
SOUTHERN EROSION, LLC 2.05% $138,999.64
CURB PLANET INC. 1.64% $111,199.71
TRM SERVICES LLC 0.16% $10,848.75
PROFESSIONAL TRAFFIC CONTROL LLC 0.11% $7,458.52
Total: 29.28% $1,985,321.66

Bid Items & Bid Tabulations

105 Total 0 of 105
HARRIS  |  SH 3  |  HOUSTON  |  0051-02-108  |  03/04/2022  |  $5,618,935.99  |  STP 2022(405)HES  |  HAZARD ELIM & SAFETY  |  223 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
MAIN LANE INDUSTRIES LTD.
ALTUS CONSTRUCTION LLC
PREPARING ROW
AC 5.110 $9,200.000 $5,007.000 $20,000.000 $14,695.110
REMOVING CONC (MEDIANS)
SY 6,025.000 $11.000 $23.000 $10.000 $4.830
REMOVING CONC (CURB)
LF 381.200 $4.000 $3.500 $9.000 $16.160
REMOVING STAB BASE & ASPH PAV (0-6")
SY 649.000 $10.000 $17.000 $15.000 $14.800
SUBGRADE WIDENING (DENS CONT)
STA 114.500 $750.000 $1,250.000 $2,500.000 $1,170.440
BLOCK SODDING
SY 24,800.000 $4.000 $5.000 $4.600 $3.020
VEGETATIVE WATERING
MG 614.880 $18.000 $15.000 $25.000 $7.390
ASPHALT STAB BASE (GR 2)(PG 64)
TON 6,637.390 $71.000 $124.000 $110.000 $135.670
CEM STABIL BKFL
CY 11.130 $38.000 $45.000 $45.000 $75.940
CEMENT STAB BACKFILL (INLET OR MH)
CY 72.500 $39.400 $45.000 $45.000 $58.870
CUT AND RESTORE PAV (FLEX BASE)
SY 82.000 $96.180 $96.000 $115.000 $84.130
RIPRAP (CONC)(5 IN)
CY 232.000 $700.000 $591.000 $600.000 $396.990
RIPRAP (CONC)(6 IN)
CY 4,477.990 $400.000 $273.000 $370.000 $367.820
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 9.000 $135.000 $265.000 $700.000 $204.960
CONC BOX CULV (7 FT X 5 FT)(EXTEND)
LF 23.000 $600.000 $798.000 $2,500.000 $1,100.020
RC PIPE (CL III)(18 IN)
LF 17.000 $62.500 $250.000 $200.000 $306.100
RC PIPE (CL III)(24 IN)
LF 106.000 $71.660 $159.000 $225.000 $106.280
RC PIPE (CL III)(30 IN)
LF 41.000 $80.000 $176.000 $250.000 $193.000
RC PIPE (CL III)(36 IN)
LF 131.000 $99.500 $209.000 $300.000 $157.910
MANH (COMPL)(TY A)
EA 4.000 $5,000.000 $6,000.000 $6,800.000 $5,809.040
INLET (STG II)(TY AD)
EA 4.000 $1,884.420 $5,500.000 $5,000.000 $6,758.710
WINGWALL (PW - 1) (HW=11 FT)
EA 2.000 $45,657.220 $32,815.000 $50,000.000 $45,857.920
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 1.000 $1,200.000 $921.000 $1,800.000 $3,397.860
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 7.000 $1,170.000 $1,193.000 $1,700.000 $1,522.300
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 4.000 $4,392.000 $4,305.000 $5,200.000 $4,822.370
ADJUSTING INLET (CAP)
EA 1.000 $480.000 $1,500.000 $1,500.000 $3,950.720
REMOV STR (SET)
EA 1.000 $400.000 $2,500.000 $800.000 $1,152.840
REMOV STR (WINGWALL)
EA 2.000 $2,100.000 $2,512.000 $2,000.000 $2,775.020
REMOV STR (HEADWALL)
EA 2.000 $2,200.000 $2,512.000 $5,000.000 $2,775.020
REMOV STR (PIPE)
LF 134.000 $19.000 $26.000 $35.000 $23.260
REMOV STR (BOX CULVERT)
LF 26.000 $49.000 $160.000 $150.000 $65.990
MOBILIZATION
LS 1.000 $510,812.000 $560,000.000 $690,000.000 $696,838.030
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $12,000.000 $2,500.000 $10,000.000 $14,800.100
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,024.000 $2.340 $1.500 $5.000 $1.870
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,024.000 $0.740 $0.600 $1.000 $0.700
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 333.000 $3.160 $2.750 $4.000 $3.470
BIODEG EROSN CONT LOGS (REMOVE)
LF 333.000 $0.820 $1.000 $1.500 $1.140
CONC CURB (DOWEL)
LF 61,527.000 $5.600 $7.000 $10.000 $16.650
DRIVEWAYS (ACP)
SY 123.690 $200.000 $154.000 $130.000 $178.830
INTERSECTIONS (CONC) (FAST TRACK)
SY 6.600 $100.000 $1,500.000 $500.000 $379.430
RUMBLE STRIPS (CENTERLINE)
LF 13,681.000 $0.390 $1.000 $2.000 $0.360
CONC DIRECTIONAL ISLAND (12")
LF 22,493.000 $22.000 $22.000 $37.000 $27.700
CONC DIRECTIONAL ISLAND (24")
LF 1,143.000 $25.000 $32.000 $43.000 $34.030
MTL W-BEAM GD FEN (TIM POST)
LF 975.000 $20.000 $20.000 $22.000 $39.710
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,500.000 $1,196.000 $1,300.000 $3,165.820
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,601.250 $3,500.000 $3,000.000 $4,170.590
ALUMINUM SIGNS (TY A)
SF 1,034.560 $20.000 $20.000 $18.450 $37.420
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 13.000 $500.000 $479.000 $470.000 $603.780
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 43.000 $700.000 $479.000 $470.000 $999.450
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $900.000 $627.000 $615.000 $958.320
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 23.000 $400.000 $505.000 $495.000 $644.300
IN SM RD SN SUP&AM TY10BWG(1)SB(P-BM)
EA 31.000 $500.000 $505.000 $495.000 $768.130
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 291.000 $0.300 $1.530 $1.000 $1.230
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 11,714.000 $0.500 $0.660 $0.730 $0.840
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 33,396.000 $1.040 $0.870 $0.880 $0.760
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 7,163.000 $2.900 $1.480 $2.580 $2.590
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,634.000 $6.070 $3.570 $5.880 $4.670
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 238.000 $3.450 $1.840 $2.580 $2.960
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 36,757.000 $0.690 $0.450 $0.630 $0.590
REFL PAV MRK TY II (Y) 12" (SLD)
LF 37,490.000 $1.120 $0.820 $1.250 $0.490
PAVEMENT SEALER 4"
LF 18,104.000 $0.200 $0.050 $0.120 $0.040
PAVEMENT SEALER 6"
LF 10,552.000 $0.200 $0.080 $0.160 $0.060
PAVEMENT SEALER 8"
LF 3,480.000 $0.230 $0.120 $0.200 $0.110
PAVEMENT SEALER 12"
LF 4,573.000 $0.680 $0.160 $0.260 $0.150
PAVEMENT SEALER 24"
LF 303.000 $1.200 $0.330 $0.500 $0.250
PAVEMENT SEALER (ARROW)
EA 23.000 $38.000 $7.100 $12.000 $12.330
PAVEMENT SEALER (WORD)
EA 20.000 $37.000 $7.100 $12.000 $12.330
PAVEMENT SEALER (BIKE ARROW)
EA 6.000 $22.000 $7.100 $12.000 $12.330
PAVEMENT SEALER (BIKE SYMBOL)
EA 6.000 $22.000 $7.100 $12.000 $12.330
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,830.000 $0.790 $0.510 $0.450 $0.330
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 136,013.000 $0.500 $0.410 $0.430 $0.300
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 36,757.000 $0.530 $0.460 $0.520 $0.380
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 1,608.000 $0.450 $0.460 $0.620 $0.380
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 95,918.000 $0.480 $0.410 $0.520 $0.380
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 131,520.000 $0.650 $0.360 $0.650 $0.570
PREFAB PAV MRK TY C (W) (ARROW)
EA 202.000 $204.000 $219.000 $180.000 $222.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 1.000 $350.000 $438.000 $350.000 $493.340
PREFAB PAV MRK TY C (W) (WORD)
EA 202.000 $250.000 $291.000 $180.000 $271.340
PREFAB PAV MRK TY C (W) (RR XING)
EA 1.000 $575.000 $438.000 $500.000 $801.670
PREFAB PAV MRK TY C (W)(BIKE ARROW)
EA 113.000 $165.000 $219.000 $70.000 $148.000
PREFAB PAV MRK TY C (W)(BIKE SYMBOL)
EA 113.000 $165.000 $1.940 $160.000 $160.330
REFL PAV MRKR TY II-A-A
EA 1,409.000 $4.000 $3.820 $4.200 $3.820
REFL PAV MRKR TY II-C-R
EA 3,513.000 $3.870 $3.820 $4.150 $3.820
ELIM EXT PAV MRK & MRKS (4")
LF 402,859.000 $0.320 $0.250 $0.180 $0.220
ELIM EXT PAV MRK & MRKS (6")
LF 131,423.000 $0.400 $0.310 $0.200 $0.250
ELIM EXT PAV MRK & MRKS (8")
LF 9,880.000 $0.520 $0.460 $0.250 $0.350
ELIM EXT PAV MRK & MRKS (12")
LF 6,672.000 $1.230 $0.760 $0.280 $1.170
ELIM EXT PAV MRK & MRKS (24")
LF 1,284.000 $2.100 $1.430 $0.330 $104.830
ELIM EXT PAV MRK & MRKS (ARROW)
EA 89.000 $46.000 $30.600 $20.000 $18.500
ELIM EXT PAV MRK & MRKS (WORD)
EA 87.000 $50.000 $30.600 $20.000 $24.670
PAV SURF PREP FOR MRK (4")
LF 281,368.000 $0.050 $0.040 $0.010 $0.010
PAV SURF PREP FOR MRK (6")
LF 171,040.000 $0.070 $0.060 $0.010 $0.020
PAV SURF PREP FOR MRK (8")
LF 33,396.000 $0.150 $0.080 $0.050 $0.050
PAV SURF PREP FOR MRK (12")
LF 44,891.000 $0.190 $0.100 $0.100 $0.070
PAV SURF PREP FOR MRK (24")
LF 1,634.000 $0.500 $0.200 $0.200 $0.150
PAV SURF PREP FOR MRK (ARROW)
EA 203.000 $9.460 $5.100 $5.000 $3.700
PAV SURF PREP FOR MRK (WORD)
EA 202.000 $10.500 $5.100 $5.000 $4.930
PAV SURF PREP FOR MRK (RR XING)
EA 1.000 $18.500 $10.000 $5.000 $30.830
PAV SURF PREP FOR MRK (BIKE ARROW)
EA 113.000 $5.000 $10.000 $5.000 $2.470
PAV SURF PREP FOR MRK (BIKE SYMBOL)
EA 113.000 $5.000 $10.000 $5.000 $2.470
TACK COAT
GAL 324.910 $3.350 $3.700 $5.000 $4.320
D-GR HMA TY-D SAC-A PG70-22 (EXEMPT)
TON 485.960 $109.000 $159.000 $250.000 $185.000
D-GR HMA TY-D PG70-22(LEVEL-UP)(EXEMPT)
TON 564.580 $161.000 $159.000 $250.000 $185.000
TMA (STATIONARY)
DAY 190.000 $200.000 $346.000 $600.000 $123.330
TMA (MOBILE OPERATION)
DAY 9.000 $350.000 $750.000 $600.000 $148.000
Totals: $5,618,935.988 $5,450,259.587 $6,965,912.302 $7,013,146.175