HARRIS US 90 (0028-02-100)

Items: 27

County: HARRIS
Length: N/A
Highway: US 90
District: HOUSTON
Control Number: 0028-02-100
DBE Goal: N/A
Project: C 28-2-100
Guaranty: N/A
Time: 135 WORKING DAYS
Engineer's Estimate: $2,322,074.75
Date: 06/04/2020 (6 years ago)
Contract Number: N/A
Type: LANDSCAPE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$2,322,074.75
$1,486,713.95
Over/Under Est: -35.97% -$835,360.80
Over/Under Est: -14.34% -$333,039.53
Amt Left: 33.79% $502,321.27
Over/Under Est: -7.84% -$182,007.88
Amt Left: 43.95% $653,352.92
Delta: -7.59% -$151,031.65
Over/Under Est: 20.8% $483,060.30
Amt Left: 88.68% $1,318,421.10
Delta: -31.08% -$665,068.18

Bid Items & Bid Tabulations

27 Total 0 of 27
HARRIS  |  US 90  |  HOUSTON  |  0028-02-100  |  06/04/2020  |  $2,322,074.75  |  C 28-2-100  |  LANDSCAPE  |  135 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS WALL & LANDSCAPE
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
CENTRAL NORTH CONSTRUCTION, LLC
APEX LANDSCAPE & IRRIGATION, LLC
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 267.000 $425.000 $204.000 $233.333 $700.000 $1,000.000
PREP ROW (TREE) (2" TO 12" DIA)
EA 9.000 $200.000 $57.000 $233.333 $750.000 $800.000
EROSION CONTROL COMPOST
CY 11,695.000 $35.000 $19.000 $19.462 $19.000 $22.000
GENERAL USE COMPOST
CY 5,847.000 $30.000 $22.000 $19.710 $21.000 $24.000
FERTILIZER
AC 13.880 $1,450.000 $1,036.000 $2,164.395 $950.000 $1,000.000
VEGETATIVE WATERING
MG 83.500 $30.000 $74.000 $78.531 $125.000 $50.000
WILDFLOWER SEEDING (MIX 1)
AC 13.880 $1,250.000 $1,219.000 $1,244.663 $1,250.000 $2,000.000
WILDFLOWER SEEDING (MIX 2)
AC 21.700 $1,250.000 $1,097.000 $886.483 $1,250.000 $2,000.000
PLANT MATERIAL (3-GAL)
EA 3,226.000 $15.000 $14.000 $10.417 $15.000 $26.000
PLANT MATERIAL (5 GAL) (TREE)
EA 9,664.000 $18.000 $16.000 $17.387 $22.000 $30.000
PLANT MATERIAL (15 GAL) (TREE)
EA 1,927.000 $108.000 $119.000 $80.819 $85.000 $140.000
PLANT BED PREP (TYPE III)
SY 105,042.000 $0.950 $1.000 $0.487 $1.420 $1.500
PLANT MAINTENANCE
MO 18.000 $16,000.000 $1,156.000 $20,151.323 $20,000.000 $20,000.000
PLANT MAINTENANCE
CYC 8.000 $20,000.000 $9,684.000 $21,753.443 $18,005.000 $9,000.000
MOBILIZATION
LS 1.000 $205,000.000 $77,826.000 $198,688.525 $100,000.000 $240,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $3,500.000 $4,360.000 $5,712.838 $4,000.000 $5,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 4,500.000 $5.000 $7.000 $3.825 $4.300 $2.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 4,500.000 $1.500 $1.000 $0.328 $1.000 $1.000
PRUNING AND TRIMMING TREES AND SHRUBS
CYC 1.000 $52,000.000 $35,638.000 $54,383.607 $65,000.000 $190,000.000
LANDSCAPE SOIL AMENDMENT (TYPE I)
SY 105,042.000 $0.400 $0.250 $0.147 $0.210 $0.450
LANDSCAPE SOIL AMENDMENT (TYPE II)
SY 105,042.000 $0.300 $0.400 $0.133 $0.180 $0.350
LANDSCAPE TREATMENT(TY 1)
EA 14,817.000 $1.500 $1.000 $0.871 $1.250 $1.600
LANDSCAPE TREATMENT(TY 2)
EA 74,085.000 $0.400 $1.000 $0.613 $0.600 $0.750
LANDSCAPE TREATMENT(TY 3)
EA 1.000 $90,000.000 $9,600.000 $109,283.180 $60,000.000 $100,000.000
LANDSCAPE TREATMENT(TY 4)
EA 1.000 $37,000.000 $21,000.000 $36,255.738 $60,000.000 $50,000.000
LANDSCAPE TREATMENT (TY 5)
EA 14,817.000 $0.350 $0.550 $0.235 $0.300 $0.500
TMA (STATIONARY)
DAY 7.000 $198.000 $365.000 $494.902 $300.000 $250.000
Totals: $2,322,074.750 $1,486,713.950 $1,989,035.221 $2,140,066.870 $2,805,135.050