Show Job Controls
Bid Cobra

HARRIS US 90 (0028-02-092)

Items: 52

County: HARRIS
Length: N/A
Highway: US 90
District: HOUSTON
Control Number: 0028-02-092
DBE Goal: N/A
Project: NH 2018(415)
Guaranty: N/A
Time: 375 WORKING DAYS
Engineer's Estimate: $1,878,041.06
Date: 04/03/2018 (8 years ago)
Contract Number: N/A
Type: INSTALLATION OF ITS EQUIPMENT & INFRASTRUCTURE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$1,878,041.06
$1,782,760.65
Over/Under Est: -5.07% -$95,280.41
Over/Under Est: 13.11% $246,255.78
Amt Left: 19.16% $341,536.19
$2,247,054.03
Over/Under Est: 19.65% $369,012.97
Amt Left: 26.04% $464,293.38
Delta: -5.78% -$122,757.19
Subcontractor Percentage Amount
SPECIALTY DRILLING, LLC 1.54% $29,728.31
Total: 1.54% $29,728.31

Bid Items & Bid Tabulations

52 Total 0 of 52
HARRIS  |  US 90  |  HOUSTON  |  0028-02-092  |  04/03/2018  |  $1,878,041.06  |  NH 2018(415)  |  INSTL OF ITS EQUIPMENT & INFRASTRUCT  |  375 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRAF-TEX, INC.
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SICE, INC.
DRILL SHAFT (42 IN)
LF 135.000 $200.000 $325.000 $483.610 $352.270
DRILL SHAFT (48 IN)
LF 75.000 $200.000 $367.000 $492.170 $461.680
RIPRAP (MOW STRIP)(4 IN)
CY 27.000 $499.770 $405.000 $695.940 $841.610
MOBILIZATION
LS 1.000 $166,670.330 $75,100.000 $86,187.860 $203,747.070
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $2,037.080 $2,940.000 $5,316.590 $7,881.740
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,000.000 $2.300 $3.250 $3.480 $3.310
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,000.000 $1.000 $0.550 $1.160 $1.620
MTL W-BEAM GD FEN (TIM POST)
LF 525.000 $22.410 $25.150 $20.880 $28.860
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,152.510 $1,056.000 $1,275.880 $1,382.640
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,208.640 $2,623.500 $3,131.720 $3,186.090
CONDT (PVC) (SCH 40) (2")
LF 9,010.000 $7.110 $8.300 $13.420 $7.640
CONDT (PVC) (SCH 40) (3") (CONC ENCSE)
LF 10,700.000 $6.760 $7.050 $10.070 $8.290
CONDT (PVC) (SCH 80) (2")
LF 510.000 $6.250 $6.450 $9.020 $4.170
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,785.000 $12.050 $19.900 $52.020 $22.800
CONDT (PVC) (SCH 80) (3")
LF 275.000 $13.600 $10.400 $9.910 $4.940
CONDT (PVC) (SCH 80) (3") (BORE)
LF 665.000 $20.120 $16.750 $25.090 $36.390
CONDT (PVC) (SCH 80) (4")
LF 100.000 $12.560 $13.250 $13.490 $9.090
CONDT (RM) (2")
LF 245.000 $20.300 $26.900 $18.930 $60.680
CONDT (RM) (3")
LF 1,165.000 $29.070 $51.450 $41.810 $37.230
ELEC CONDR (NO.14) INSULATED
LF 38,120.000 $0.700 $0.620 $0.800 $0.710
ELEC CONDR (NO.8) BARE
LF 2,520.000 $0.940 $0.750 $1.000 $0.850
ELEC CONDR (NO.8) INSULATED
LF 2,525.000 $1.280 $0.850 $1.100 $0.990
ELEC CONDR (NO.4) BARE
LF 835.000 $1.520 $1.550 $1.550 $1.230
ELEC CONDR (NO.4) INSULATED
LF 1,670.000 $1.620 $1.700 $1.590 $1.410
ELEC CONDR (NO.2) BARE
LF 7,435.000 $2.910 $1.650 $1.810 $1.610
ELEC CONDR (NO.2) INSULATED
LF 21,535.000 $2.920 $1.850 $1.870 $1.830
TRAY CABLE (3 CONDR) (10 AWG)
LF 6,240.000 $2.000 $2.400 $1.910 $1.330
GROUND BOX TY A (122311)
EA 43.000 $750.000 $534.000 $430.530 $920.880
ELC SRV TY D 120/240 100(NS)SS(N)SP(O)
EA 9.000 $4,839.660 $2,787.000 $3,544.210 $3,228.170
INS OH SN SUP(25 FT BAL TEE)
EA 2.000 $17,000.000 $17,605.000 $17,503.940 $20,120.470
INS OH SN SUP(30 FT BAL TEE)
EA 1.000 $25,000.000 $19,855.000 $19,887.320 $22,549.110
SIGN WALKWAY (36 IN) WITH HNDRL
LF 75.000 $140.000 $234.000 $299.790 $263.300
PED POLE ASSEMBLY
EA 2.000 $1,944.190 $1,857.000 $3,156.470 $3,877.610
ITS SYSTEM SUPPORT EQUIPMENT
LS 1.000 $16,705.000 $15,115.000 $13,076.630 $49,343.550
FIBER OPTIC CBL (SNGLE-MODE)(6 FIBER)
LF 50,695.000 $1.720 $2.200 $3.150 $0.710
FIBER OPTIC CBL (SNGLE-MODE)(144 FIBER)
LF 36,215.000 $4.440 $3.050 $4.180 $2.260
FIBER OPTIC PATCH PANEL (144 POSITION)
EA 5.000 $11,749.070 $5,573.000 $1,451.280 $326.950
FIBER OPTIC FUSION SPLICE
EA 492.000 $25.000 $17.150 $30.340 $44.280
CCTV FIELD EQUIPMENT (ANALOG)
EA 9.000 $9,794.090 $14,120.000 $8,396.180 $8,779.190
ITS MULTI-DUCT CND (PVC-40)(CONC ENCSE)
LF 10,920.000 $12.870 $10.850 $13.760 $22.710
ITS MULTI-DUCT CND (PVC-80)(BORE)
LF 240.000 $30.250 $21.800 $125.910 $34.330
ITS MULTI-DUCT CND (RMC)
LF 1,165.000 $55.140 $63.550 $68.060 $66.870
COMMUNICATION HUB BUILDING
EA 3.000 $15,000.000 $27,745.000 $26,500.210 $40,140.350
CONDUIT (PREPARE)
LF 85,370.000 $1.210 $0.460 $1.090 $1.440
INSTALL DMS (FOUNDATION MTD CABINET)
EA 3.000 $17,313.580 $13,150.000 $7,831.110 $17,066.630
RADAR VEHICLE SENSING DEVICE
EA 2.000 $9,048.070 $9,345.000 $7,967.860 $7,225.820
CTMS RELOCATION (MVD)
EA 1.000 $7,500.000 $3,605.000 $1,686.070 $13,225.290
FIBER OPTIC VIDEO DATA TRANSMITTER
EA 9.000 $1,425.000 $1,375.000 $1,238.350 $1,455.450
FIBER OPTIC VIDEO DATA RECEIVER
EA 9.000 $1,425.000 $1,375.000 $1,238.350 $1,455.450
ITS POLE (55 FT)(110 MPH)
EA 9.000 $14,000.000 $15,973.000 $17,078.060 $18,829.230
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 9.000 $5,726.410 $7,620.000 $5,578.010 $6,913.220
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 10.000 $2,205.440 $2,685.000 $2,671.270 $3,516.720
Totals: $1,878,041.060 $1,782,760.650 $2,124,296.840 $2,247,054.030