Show Job Controls
Bid Cobra

HARDIN CR (0920-03-081)

Items: 32

County: HARDIN
Length: N/A
Highway: CR
District: BEAUMONT
Control Number: 0920-03-081
DBE Goal: N/A
Project: BR 2021(530)
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $812,356.76
Date: 10/05/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
DAVE COLLINS
RICHARD BRADLEY
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$812,356.76
$775,736.52
Over/Under Est: -4.51% -$36,620.24
Over/Under Est: 15.85% $128,718.84
Amt Left: 21.31% $165,339.08
Over/Under Est: 18.97% $154,135.24
Amt Left: 24.59% $190,755.48
Delta: -2.70% -$25,416.40
Over/Under Est: 44.44% $361,004.99
Amt Left: 51.26% $397,625.23
Delta: -21.40% -$206,869.75
$1,393,881.40
Over/Under Est: 71.58% $581,524.64
Amt Left: 79.68% $618,144.88
Delta: -18.79% -$220,519.65
Subcontractor Percentage Amount
GUERRA CONCRETE CONTRACTORS, LLC 12.99% $94,468.44
HEMPHILL WBE PILE DRIVING CO. 10.23% $74,396.62
HAZMAT INTERNATIONAL, INC. 3.63% $26,398.80
TSTAR DRILLING & SAWING INC 3.03% $22,035.36
BARRICADES UNLIMITED 0.75% $5,454.30
SEMARCK LANDSCAPE SERVICES, INC. 0.69% $5,017.95
HOUSTON SAWING & DRILLING 0.45% $3,272.58
A1 EROSION CONTROL 0.27% $1,963.55
Total: 32.04% $233,007.60

Bid Items & Bid Tabulations

32 Total 0 of 32
HARDIN  |  CR  |  BEAUMONT  |  0920-03-081  |  10/05/2023  |  $812,356.76  |  BR 2021(530)  |  BRIDGE REPL  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
C. E. BARKER, LTD.
PROJECT ALLIED RESOURCES, LLC
TEXAS MATERIALS GROUP, INC.
BLACKSMITH VENTURES LLC
ISI CONTRACTING, INC.
PREP ROW (TREE PRUNING)
EA 5.000 $4,500.000 $703.800 $6,160.000 $3,400.000 $550.000 $4,500.000
EXCAVATION (ROADWAY)
CY 326.000 $35.000 $27.370 $40.300 $55.000 $33.000 $35.000
SUBGRADE WIDENING (ORD COMP)
STA 2.000 $3,200.000 $2,052.750 $4,510.000 $3,500.000 $2,750.000 $6,349.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 31.000 $75.000 $273.700 $166.000 $158.000 $55.000 $30.000
PROOF ROLLING
HR 10.000 $125.000 $313.780 $580.000 $290.000 $192.500 $150.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 80.000 $110.000 $462.160 $188.000 $310.000 $275.000 $362.000
PRIME COAT (AE-P)
GAL 86.000 $22.000 $23.460 $25.000 $26.000 $27.500 $18.000
CEM STABIL BKFL
CY 25.000 $245.000 $199.410 $280.000 $332.000 $330.000 $113.000
PRESTR CONC PIL (18 IN SQ)
LF 676.000 $84.290 $172.190 $155.000 $195.000 $220.000 $693.000
CL C CONC (ABUT)
CY 17.600 $2,400.000 $2,789.880 $3,810.000 $3,700.000 $3,300.000 $2,558.000
CL C CONC (BENT)
CY 13.200 $2,400.000 $2,083.250 $3,880.000 $3,700.000 $5,500.000 $3,133.000
REINF CONC SLAB (SLAB BEAM)
SF 2,340.000 $30.000 $28.490 $43.800 $33.000 $33.000 $53.000
APPROACH SLAB
CY 38.500 $685.000 $513.770 $749.000 $1,000.000 $1,650.000 $2,047.000
PRESTR CONC SLAB BEAM (5SB12)
LF 442.500 $326.530 $149.100 $254.000 $120.000 $302.500 $81.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 683.000 $100.000 $134.800 $49.700 $240.000 $247.500 $248.000
RAIL (TY T223)
LF 204.000 $160.000 $305.970 $237.000 $280.000 $302.500 $250.000
ARMOR JOINT
LF 44.000 $195.000 $180.110 $323.000 $322.000 $150.000 $106.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $35,000.000 $26,392.500 $70,000.000 $52,000.000 $55,000.000 $26,308.000
MOBILIZATION
LS 1.000 $135,392.790 $66,157.200 $103,000.000 $93,000.000 $110,000.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $6,000.000 $2,919.050 $5,240.000 $4,200.000 $5,500.000 $11,096.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 50.000 $60.000 $41.060 $146.000 $50.000 $330.000 $92.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $20.000 $20.530 $41.500 $12.000 $11.000 $24.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 320.000 $5.000 $6.420 $12.400 $5.500 $16.500 $8.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 320.000 $1.500 $3.200 $3.910 $1.000 $5.500 $2.000
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $45.000 $38.240 $91.000 $36.000 $44.000 $41.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,200.000 $2,193.510 $3,660.000 $2,060.000 $4,400.000 $3,731.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,100.000 $3,753.600 $5,320.000 $3,520.000 $5,500.000 $5,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $25.000 $23.460 $42.600 $55.000 $110.000 $17.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $30.000 $46.920 $75.000 $55.000 $110.000 $35.000
TACK COAT
GAL 43.000 $21.300 $29.330 $24.400 $50.000 $165.000 $60.000
D-GR HMA TY-D PG 64-22 (EXEMPT)
TON 47.000 $402.000 $763.620 $461.000 $470.000 $330.000 $360.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $9,518.900 $5,890.000 $5,600.000 $22,000.000 $7,634.000
Totals: $812,356.755 $775,736.533 $941,075.600 $966,492.000 $1,173,361.750 $1,393,881.400