HARDIN CR (0920-03-081)
Items: 32
County: HARDIN
Length: N/A
Highway: CR
District: BEAUMONT
Control Number: 0920-03-081
DBE Goal: N/A
Project: BR 2021(530)
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $812,356.76
Date: 10/05/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
DAVE COLLINS
RICHARD BRADLEY
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$812,356.76 | |||
| $775,736.52 |
-4.51%
-$36,620.24
|
|||
| $941,075.60 |
15.85%
$128,718.84
|
21.31%
$165,339.08
|
||
| $966,492.00 |
18.97%
$154,135.24
|
24.59%
$190,755.48
|
-2.70%
-$25,416.40
|
|
| $1,173,361.75 |
44.44%
$361,004.99
|
51.26%
$397,625.23
|
-21.40%
-$206,869.75
|
|
| $1,393,881.40 |
71.58%
$581,524.64
|
79.68%
$618,144.88
|
-18.79%
-$220,519.65
|
E
Engineer's Estimate
$812,356.76
1
Awarded
$775,736.52
Over/Under Est:
-4.51%
-$36,620.24
$941,075.60
Over/Under Est:
15.85%
$128,718.84
Amt Left:
21.31%
$165,339.08
$966,492.00
Over/Under Est:
18.97%
$154,135.24
Amt Left:
24.59%
$190,755.48
Delta:
-2.70%
-$25,416.40
$1,173,361.75
Over/Under Est:
44.44%
$361,004.99
Amt Left:
51.26%
$397,625.23
Delta:
-21.40%
-$206,869.75
$1,393,881.40
Over/Under Est:
71.58%
$581,524.64
Amt Left:
79.68%
$618,144.88
Delta:
-18.79%
-$220,519.65
| Subcontractor | Percentage | Amount |
|---|---|---|
| GUERRA CONCRETE CONTRACTORS, LLC | 12.99% | $94,468.44 |
| HEMPHILL WBE PILE DRIVING CO. | 10.23% | $74,396.62 |
| HAZMAT INTERNATIONAL, INC. | 3.63% | $26,398.80 |
| TSTAR DRILLING & SAWING INC | 3.03% | $22,035.36 |
| BARRICADES UNLIMITED | 0.75% | $5,454.30 |
| SEMARCK LANDSCAPE SERVICES, INC. | 0.69% | $5,017.95 |
| HOUSTON SAWING & DRILLING | 0.45% | $3,272.58 |
| A1 EROSION CONTROL | 0.27% | $1,963.55 |
| Total: | 32.04% | $233,007.60 |
Bid Items & Bid Tabulations
32
Total
0 of 32