HARDIN SH 105 (0339-04-035)

Items: 30

County: HARDIN
Length: N/A
Highway: SH 105
District: BEAUMONT
Control Number: 0339-04-035
DBE Goal: N/A
Project: NH 1702(265)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $2,928,646.90
Date: 06/06/2017 (9 years ago)
Contract Number: N/A
Type: PAVEMENT REPAIR, MILL, OCST, PFC
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,928,646.90
$2,678,096.51
Over/Under Est: -8.56% -$250,550.39
Over/Under Est: -4.05% -$118,499.15
Amt Left: 4.93% $132,051.24
$2,888,905.08
Over/Under Est: -1.36% -$39,741.82
Amt Left: 7.87% $210,808.57
Delta: -2.80% -$78,757.33
$2,939,047.34
Over/Under Est: 0.36% $10,400.44
Amt Left: 9.74% $260,950.83
Delta: -1.74% -$50,142.26

Bid Items & Bid Tabulations

30 Total 0 of 30
HARDIN  |  SH 105  |  BEAUMONT  |  0339-04-035  |  06/06/2017  |  $2,928,646.90  |  NH 1702(265)  |  PAVMT REPAIR, MILL, OCST, PFC  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANGEL BROTHERS HOLDINGS CORP.
OLDCASTLE MATERIALS TEXAS, INC.
A. L. HELMCAMP, INC.
SMITH & COMPANY
FL BS (CMP IN PLACE)(TYD GR1-2)(IN VEH)
CY 178.000 $80.000 $50.000 $130.000 $165.000 $132.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 17,273.000 $120.000 $116.000 $120.000 $122.000 $115.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 374.000 $100.000 $40.000 $90.000 $147.000 $94.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(16")
SY 200.000 $150.000 $100.000 $125.000 $278.000 $183.000
PLANE ASPH CONC PAV (1.5")
SY 196,959.000 $1.500 $1.600 $1.500 $1.500 $2.250
FULL - DEPTH REPAIR CPJR (15")
SY 200.000 $250.000 $250.000 $550.000 $400.000 $778.000
MOBILIZATION
LS 1.000 $250,000.000 $115,000.000 $123,800.000 $136,000.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $4,000.000 $5,000.000 $1,500.000 $6,000.000 $750.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 200.000 $5.000 $30.000 $5.500 $10.000 $14.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $1.000 $12.000 $1.000 $3.000 $1.000
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 26,643.000 $1.500 $0.300 $0.450 $0.300 $0.220
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 75,460.000 $0.600 $0.500 $0.450 $0.350 $0.570
WK ZN PAV MRK REMOV (W)8"(DOT)
LF 395.000 $1.000 $2.000 $1.500 $1.400 $2.650
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 2,230.000 $1.000 $1.300 $1.250 $1.150 $1.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 21,212.000 $0.600 $0.600 $0.500 $0.400 $0.580
WK ZN PAV MRK REMOV (Y)4"(BKN W/MRKR)
LF 8,592.000 $0.600 $0.600 $0.500 $0.400 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 214.000 $1.000 $1.000 $1.400 $0.700 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,621.000 $1.000 $1.000 $1.450 $0.700 $1.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 2,230.000 $1.000 $0.750 $0.700 $0.750 $0.560
REFL PAV MRK TY I (W)(BIKE DOT)(090MIL)
EA 395.000 $1.000 $1.050 $1.000 $1.100 $2.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 75,460.000 $0.350 $0.320 $0.320 $0.330 $0.280
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 8,592.000 $0.400 $0.350 $0.330 $0.350 $0.280
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 21,212.000 $0.350 $0.330 $0.320 $0.340 $0.280
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 166.000 $10.000 $15.000 $12.100 $13.000 $16.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 15.000 $200.000 $200.000 $185.000 $190.000 $245.000
PREFAB PAV MRK TY C (W) (WORD)
EA 6.000 $250.000 $260.000 $250.000 $265.000 $350.000
PREFAB PAV MRK TY C (W)(BIKE ARROW)
EA 4.000 $250.000 $150.000 $145.000 $154.000 $155.000
PREFAB PAV MRK TY C (W)(BIKE SYMBOL)
EA 4.000 $250.000 $700.000 $660.000 $700.000 $245.000
REFL PAV MRKR TY I-C
EA 149.000 $3.500 $3.600 $3.600 $3.800 $3.250
REFL PAV MRKR TY II-A-A
EA 1,149.000 $3.000 $3.200 $3.050 $3.200 $3.250
Totals: $2,928,646.900 $2,678,096.510 $2,810,147.750 $2,888,905.080 $2,939,047.340