REMOVING CONC (PAV)
|
SY
|
806.000
|
$24.650
|
$12.000
|
$15.000
|
$8.300
|
|
|
REMOVING STAB BASE AND ASPH PAV (2"-6")
|
SY
|
13,986.000
|
$7.750
|
$2.360
|
$10.000
|
$3.600
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
8,832.000
|
$10.800
|
$5.000
|
$14.000
|
$11.500
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
68,013.000
|
$32.000
|
$10.000
|
$20.000
|
$24.500
|
|
|
EMB(FNL)(DC)(TYE)(CSBE)(RWALL FND IMPR
|
CY
|
2,512.000
|
$35.000
|
$73.000
|
$89.000
|
$61.000
|
|
|
BLADING
|
HR
|
25.111
|
$87.000
|
$110.000
|
$150.000
|
$130.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
70,527.000
|
$1.300
|
$3.000
|
$2.500
|
$1.500
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
|
SY
|
70,527.000
|
$0.300
|
$0.300
|
$0.280
|
$0.290
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
35,264.000
|
$0.250
|
$0.330
|
$0.260
|
$0.270
|
|
|
CELL FBR MLCH SEED(TEMP)(COOL)
|
SY
|
35,264.000
|
$0.250
|
$0.330
|
$0.260
|
$0.270
|
|
|
VEGETATIVE WATERING
|
MG
|
1,777.000
|
$16.000
|
$20.000
|
$21.000
|
$17.000
|
|
|
PROOF ROLLING
|
HR
|
32.000
|
$65.000
|
$70.000
|
$125.000
|
$84.000
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
8.000
|
$38.500
|
$145.000
|
$85.000
|
$65.000
|
|
|
CEMENT
|
TON
|
1,302.000
|
$208.000
|
$180.000
|
$160.000
|
$159.000
|
|
|
CEMENT TREAT (NEW BASE) (8")
|
SY
|
23,962.000
|
$2.570
|
$22.000
|
$2.000
|
$20.500
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
26,779.000
|
$2.500
|
$3.000
|
$2.000
|
$2.800
|
|
|
PRIME COAT (AE-P)
|
GAL
|
400.000
|
$3.300
|
$9.000
|
$4.500
|
$10.000
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
9,410.000
|
$3.000
|
$6.750
|
$4.000
|
$3.800
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
234.000
|
$79.000
|
$110.000
|
$210.000
|
$185.000
|
|
|
D-GR HMA(SQ) TY-D SAC-A PG76-22
|
TON
|
2,735.000
|
$115.000
|
$125.000
|
$95.000
|
$98.000
|
|
|
CONC PVMT (JOINTED - CPCD) (6")
|
SY
|
2,490.000
|
$60.000
|
$58.000
|
$63.000
|
$75.500
|
|
|
CONC PAV (JOINT REINF) (8")
|
SY
|
181.000
|
$60.000
|
$90.000
|
$130.000
|
$135.000
|
|
|
STRUCT EXCAV
|
CY
|
2,512.000
|
$10.000
|
$10.000
|
$18.000
|
$10.000
|
|
|
CEM STABIL BKFL
|
CY
|
424.000
|
$77.000
|
$70.000
|
$90.000
|
$83.000
|
|
|
TEMPORARY SPL SHORING (COFFERDAM)
|
SF
|
1,009.000
|
$65.000
|
$460.000
|
$110.000
|
$100.000
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
5,182.000
|
$230.000
|
$295.000
|
$430.000
|
$275.000
|
|
|
CL C CONC (ABUT)
|
CY
|
108.400
|
$1,150.000
|
$900.000
|
$1,200.000
|
$1,200.000
|
|
|
CL C CONC (CAP)
|
CY
|
239.400
|
$1,100.000
|
$1,750.000
|
$2,500.000
|
$2,000.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
181.200
|
$1,000.000
|
$2,000.000
|
$2,000.000
|
$1,220.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
77.200
|
$204.000
|
$500.000
|
$500.000
|
$445.000
|
|
|
REINF CONC SLAB
|
SF
|
49,600.000
|
$17.000
|
$25.000
|
$17.000
|
$31.000
|
|
|
APPROACH SLAB
|
CY
|
128.400
|
$460.000
|
$440.000
|
$500.000
|
$518.000
|
|
|
RETAINING WALL (MSE)
|
SF
|
7,437.000
|
$42.000
|
$83.000
|
$50.000
|
$64.000
|
|
|
PRESTR CONC GIRDER (TX40)
|
LF
|
6,160.330
|
$150.000
|
$192.000
|
$180.000
|
$139.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
86.000
|
$479.000
|
$400.000
|
$400.000
|
$582.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
202.000
|
$450.000
|
$440.000
|
$575.000
|
$560.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
22.000
|
$150.000
|
$330.000
|
$135.000
|
$180.000
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
136.000
|
$150.000
|
$350.000
|
$180.000
|
$190.000
|
|
|
BEDDING MATERIAL (6 IN)
|
CY
|
18.000
|
$100.000
|
$210.000
|
$130.000
|
$110.000
|
|
|
RIPRAP (CONC)(FLUME)
|
CY
|
35.000
|
$410.000
|
$440.000
|
$750.000
|
$620.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
18.900
|
$540.000
|
$500.000
|
$500.000
|
$610.000
|
|
|
STR STEEL (MISCELLANEOUS BRIDGE)
|
LB
|
47,200.000
|
$3.610
|
$5.000
|
$4.000
|
$8.750
|
|
|
RAIL (TY T552)
|
LF
|
3,111.000
|
$50.000
|
$45.000
|
$42.000
|
$54.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
|
LF
|
360.000
|
$95.000
|
$75.000
|
$100.000
|
$140.000
|
|
|
CONC BOX CULV (6 FT X 3 FT)
|
LF
|
95.000
|
$300.000
|
$260.000
|
$250.000
|
$345.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
485.000
|
$86.500
|
$60.000
|
$85.000
|
$59.000
|
|
|
INLET (COMPL)(PSL)(SL)(3FTX5FT)
|
EA
|
3.000
|
$3,370.000
|
$5,200.000
|
$4,600.000
|
$5,824.000
|
|
|
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(P)
|
EA
|
2.000
|
$5,400.000
|
$7,500.000
|
$6,500.000
|
$8,320.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$1,200.000
|
$1,600.000
|
$4,000.000
|
$1,080.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
3.000
|
$1,160.000
|
$2,100.000
|
$3,500.000
|
$1,195.000
|
|
|
REMOV STR (INLET)
|
EA
|
2.000
|
$900.000
|
$1,500.000
|
$950.000
|
$580.000
|
|
|
REMOV STR (MANHOLE)
|
EA
|
1.000
|
$1,100.000
|
$800.000
|
$2,000.000
|
$580.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
5.000
|
$1,300.000
|
$1,200.000
|
$1,200.000
|
$1,160.000
|
|
|
REMOV STR (PIPE)
|
LF
|
121.000
|
$16.000
|
$27.000
|
$25.000
|
$24.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$880,000.000
|
$1,060,000.000
|
$1,080,000.000
|
$1,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$4,800.000
|
$800.000
|
$8,500.000
|
$2,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
180.000
|
$26.500
|
$31.550
|
$32.000
|
$30.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
180.000
|
$9.000
|
$11.000
|
$8.000
|
$8.300
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$25.000
|
$32.510
|
$30.000
|
$27.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$13.000
|
$10.000
|
$7.000
|
$7.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
360.000
|
$2.750
|
$5.000
|
$3.000
|
$3.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
360.000
|
$0.750
|
$3.000
|
$0.500
|
$0.520
|
|
|
CONSTRUCTING DETOURS
|
SY
|
140.000
|
$50.000
|
$80.000
|
$145.000
|
$95.000
|
|
|
CONC SIDEWALKS (5")
|
SY
|
19.170
|
$50.000
|
$70.000
|
$80.000
|
$116.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,800.000
|
$1,535.000
|
$1,325.000
|
$1,378.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,100.000
|
$2,350.000
|
$2,050.000
|
$2,132.000
|
|
|
IN RD IL (U/P) (TY 1) (150W EQ) LED
|
EA
|
3.000
|
$1,600.000
|
$1,375.000
|
$1,050.000
|
$1,872.000
|
|
|
IN RD IL (U/P) (TY 2) (150W EQ) LED
|
EA
|
2.000
|
$1,400.000
|
$1,510.000
|
$1,120.000
|
$2,080.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
377.000
|
$8.250
|
$10.000
|
$9.500
|
$10.400
|
|
|
CONDT (RM) (1")
|
LF
|
332.000
|
$23.000
|
$9.250
|
$19.000
|
$33.000
|
|
|
CONDT (RM) (2")
|
LF
|
37.000
|
$29.000
|
$30.000
|
$12.500
|
$52.000
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
816.000
|
$1.250
|
$1.200
|
$0.800
|
$2.000
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
1,632.000
|
$1.250
|
$1.300
|
$1.200
|
$1.700
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
3.000
|
$900.000
|
$970.000
|
$750.000
|
$1,144.000
|
|
|
ELC SRV TY A 120/240 100(NS)SS(E)SP(O)
|
EA
|
1.000
|
$7,000.000
|
$6,580.000
|
$7,200.000
|
$6,240.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
6.000
|
$24.000
|
$31.000
|
$25.000
|
$26.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
25.000
|
$500.000
|
$485.000
|
$600.000
|
$450.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
1.000
|
$1,500.000
|
$1,700.000
|
$1,500.000
|
$2,080.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
16.000
|
$100.000
|
$75.000
|
$220.000
|
$57.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
17.000
|
$19.000
|
$20.000
|
$15.000
|
$15.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
14.000
|
$20.000
|
$20.000
|
$15.000
|
$15.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
8.000
|
$52.000
|
$49.000
|
$48.000
|
$49.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
37.000
|
$2.100
|
$1.370
|
$1.250
|
$5.200
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
467.000
|
$0.200
|
$0.120
|
$1.000
|
$0.520
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
699.000
|
$0.600
|
$0.680
|
$1.200
|
$2.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
296.000
|
$0.900
|
$0.710
|
$0.500
|
$1.200
|
|
|
PAVEMENT SEALER 4"
|
LF
|
1,796.000
|
$0.100
|
$0.040
|
$0.100
|
$0.050
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
3.000
|
$0.300
|
$14.720
|
$12.000
|
$5.200
|
|
|
PAVEMENT SEALER (SYMBOL)
|
EA
|
3.000
|
$650.000
|
$1.000
|
$15.000
|
$5.200
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
|
LF
|
1,618.000
|
$1.000
|
$0.290
|
$0.900
|
$0.470
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
9,365.000
|
$0.350
|
$0.260
|
$1.000
|
$0.420
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
7,973.000
|
$0.300
|
$0.270
|
$0.300
|
$0.420
|
|
PREFAB PAV MRK TY B (W)(ARROW)
|
EA
|
3.000
|
$100.000
|
$325.050
|
$200.000
|
$192.000
|
|
PREFAB PAV MRK TY B (W)(SYMBOL)
|
EA
|
3.000
|
$775.000
|
$600.000
|
$240.000
|
$260.000
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
45.000
|
$11.000
|
$12.930
|
$8.000
|
$14.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
2.000
|
$180.000
|
$212.480
|
$200.000
|
$187.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
2.000
|
$260.000
|
$290.920
|
$270.000
|
$239.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
100.000
|
$4.000
|
$3.100
|
$3.500
|
$3.650
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
50.000
|
$0.300
|
$0.340
|
$0.500
|
$1.040
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
2.000
|
$45.000
|
$37.260
|
$35.000
|
$26.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
1,796.000
|
$0.300
|
$0.010
|
$0.050
|
$0.010
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
3.000
|
$15.000
|
$4.770
|
$10.000
|
$5.200
|
|
|
PAV SURF PREP FOR MRK (ACC PRK)(LRG)
|
EA
|
3.000
|
$500.000
|
$185.310
|
$25.000
|
$10.400
|
|
|
WHEEL STOPS
|
EA
|
23.000
|
$150.000
|
$170.000
|
$25.000
|
$62.000
|
|
Totals: |
$9,307,320.097
|
$10,637,780.190
|
$10,892,412.740
|
$10,999,133.230
|