Show Job Controls
Bid Cobra

HARDEMAN US 287 (0043-04-082)

Items: 13

County: HARDEMAN
Length: N/A
Highway: US 287
District: CHILDRESS
Control Number: 0043-04-082
DBE Goal: N/A
Project: NH 2021(103)
Guaranty: N/A
Time: 31 WORKING DAYS
Engineer's Estimate: $2,129,779.61
Date: 11/04/2020 (5 years ago)
Contract Number: N/A
Type: MILL/INLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$2,129,779.61
$1,952,687.34
Over/Under Est: -8.32% -$177,092.27
$1,954,990.65
Over/Under Est: -8.21% -$174,788.96
Amt Left: 0.12% $2,303.31
$1,996,664.72
Over/Under Est: -6.25% -$133,114.89
Amt Left: 2.25% $43,977.38
Delta: -2.13% -$41,674.07
$2,058,510.30
Over/Under Est: -3.35% -$71,269.31
Amt Left: 5.42% $105,822.96
Delta: -3.10% -$61,845.58
$2,587,497.60
Over/Under Est: 21.49% $457,717.99
Amt Left: 32.51% $634,810.26
Delta: -25.70% -$528,987.30
$2,764,510.25
Over/Under Est: 29.8% $634,730.64
Amt Left: 41.57% $811,822.91
Delta: -6.84% -$177,012.65

Bid Items & Bid Tabulations

13 Total 0 of 13
HARDEMAN  |  US 287  |  CHILDRESS  |  0043-04-082  |  11/04/2020  |  $2,129,779.61  |  NH 2021(103)  |  MILL/INLAY  |  31 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
ZACK BURKETT CO.
RK HALL, LLC
DUININCK, INC.
GILVIN-TERRILL, LTD.
J. LEE MILLIGAN, INC.
PLANE ASPH CONC PAV (2")
SY 117,907.000 $1.800 $1.700 $2.500 $1.490 $2.100 $2.000 $2.750
MOBILIZATION
LS 1.000 $144,669.000 $150,000.000 $160,000.000 $60,000.000 $200,000.000 $250,000.000 $270,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $20,000.000 $10,600.000 $7,500.000 $2,775.300 $21,500.000 $40,000.000 $30,000.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 9,302.000 $1.000 $0.700 $1.000 $1.500 $1.400 $4.000 $1.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,135.000 $0.800 $0.740 $1.050 $0.700 $0.790 $0.840 $0.950
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 15,503.000 $0.350 $0.420 $0.600 $0.400 $0.400 $0.420 $0.470
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 62,010.000 $0.350 $0.370 $0.550 $0.350 $0.370 $0.420 $0.470
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 26,400.000 $0.350 $0.380 $0.550 $0.360 $0.400 $0.420 $0.470
REFL PAV MRKR TY I-C
EA 775.000 $3.500 $3.940 $6.000 $3.750 $4.250 $3.500 $3.900
D-GR HMA TY-D SAC-A PG70-28
TON 12,972.000 $125.000 $115.000 $105.000 $126.000 $112.000 $144.000 $153.250
TACK COAT
GAL 11,624.560 $3.500 $3.000 $3.750 $4.000 $3.400 $4.000 $3.650
TMA (STATIONARY)
DAY 40.000 $400.000 $75.000 $125.000 $350.000 $315.000 $425.000 $370.000
TMA (MOBILE OPERATION)
DAY 6.000 $900.000 $250.000 $250.000 $900.000 $1,000.000 $950.000 $85.000
Totals: $2,129,779.610 $1,952,687.340 $1,954,990.650 $1,996,664.720 $2,058,510.304 $2,587,497.600 $2,764,510.254