Show Job Controls
Bid Cobra

HALE IH0027 (6490-31-001)

Items: 44

County: HALE
Length: 0.0100 MILES
Highway: IH0027
District: LUBBOCK
Control Number: 6490-31-001
DBE Goal: 0.0%
Project: RMC - A00217600
Guaranty: $15,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $732,750.00
Date: 10/14/2025 (7 months ago)
Contract Number: 10250501
Type: METAL BEAM GUARD FENCE REPAIR
Project ID: A00217600
Project Description: PLAINVIEW MBGF AND CABLE CALLOUT REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$732,750.00
$467,721.00
Over/Under Est: -36.17% -$265,029.00
$606,597.50
Over/Under Est: -17.22% -$126,152.50
Amt Left: 29.69% $138,876.50
Over/Under Est: -14.94% -$109,506.00
Amt Left: 33.25% $155,523.00
Delta: -2.74% -$16,646.50
$669,363.00
Over/Under Est: -8.65% -$63,387.00
Amt Left: 43.11% $201,642.00
Delta: -7.40% -$46,119.00
Over/Under Est: 47.11% $345,200.00
Amt Left: 130.47% $610,229.00
Delta: -61.04% -$408,587.00

Bid Items & Bid Tabulations

44 Total 0 of 44
HALE  |  IH0027  |  LUBBOCK  |  6490-31-001  |  10/14/2025  |  $732,750.00  |  RMC - A00217600  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROSS SA ENTERPRISE LLC
RHINO EQUITY, LLC
BK FIELD OPERATIONS LLC
E.V.G. ENTERPRISE
ABOVE ALL CONTRACTING LLC
REMOV CONC (RIPRAP)
SY 28.000 $500.000 $1.000 $50.000 $75.000 $1.000 $200.000
BACKFILL (TY A)
LF 80.000 $200.000 $10.000 $70.000 $10.000 $1.000 $150.000
RIPRAP (CONC) (CL B) (6 IN)
CY 12.000 $750.000 $155.000 $500.000 $1,000.000 $1.000 $300.000
MOBILIZATION (CALLOUT)
EA 12.000 $2,000.000 $1.000 $1.000 $1.000 $1.000 $500.000
MOBILIZATION (EMERGENCY)
EA 12.000 $2,500.000 $1.000 $2,500.000 $1.000 $1.000 $1,000.000
TMA (STATIONARY)
DAY 200.000 $100.000 $1.000 $1.000 $1.000 $1.000 $500.000
MTL W-BEAM GD FEN (STEEL POST)
LF 5,000.000 $25.000 $15.000 $40.000 $24.000 $30.000 $45.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $1,000.000 $800.000 $2,000.000 $1,200.000 $1,500.000 $3,000.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,000.000 $1.000 $500.000 $1,500.000 $1.000 $1,000.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $1,000.000 $680.000 $1,200.000 $1,200.000 $850.000 $2,000.000
MTL BM GD FEN TRANS (NON - SYM)
EA 20.000 $750.000 $1.000 $600.000 $400.000 $433.000 $500.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 50.000 $75.000 $10.000 $100.000 $80.000 $1.000 $50.000
MTL BM GD FEN TRANS (31"-28")
EA 20.000 $100.000 $100.000 $100.000 $1.000 $1.000 $500.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 10.000 $500.000 $100.000 $300.000 $300.000 $1.000 $500.000
MTL W-BEAM GD FEN (NESTED)(STEEL POST)
LF 75.000 $50.000 $20.000 $40.000 $30.000 $1.000 $100.000
MBGF (W-BEAM) (MED BAR)
LF 500.000 $50.000 $1.000 $25.000 $25.000 $1.000 $100.000
REMOVE METAL BEAM GUARD FENCE
LF 5,000.000 $5.000 $0.010 $5.000 $10.000 $1.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 10.000 $125.000 $1.000 $1.000 $1.000 $10.000 $250.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 10.000 $750.000 $1.000 $1.000 $1,250.000 $10.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,000.000 $2,500.000 $5,000.000 $6,000.000 $10,000.000 $4,000.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 10.000 $150.000 $1.000 $1.000 $800.000 $100.000 $1,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $100.000 $100.000 $1,000.000 $1.000 $100.000 $500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 450.000 $5.000 $1.000 $1.000 $6.000 $1.000 $40.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 600.000 $5.000 $1.000 $1.000 $6.000 $1.000 $40.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 300.000 $5.000 $1.000 $1.000 $6.000 $1.000 $40.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2(BI)
EA 100.000 $5.000 $1.000 $1.000 $1.000 $1.000 $40.000
REPLACE RAIL ELEMENT (W-BEAM)
LF 5,000.000 $20.000 $10.000 $10.000 $5.000 $13.000 $40.000
REPLACE TIMBER POST W/O CONC FND
EA 250.000 $100.000 $5.000 $5.000 $250.000 $60.000 $50.000
REPLACE STEEL POST W/O CONC FND
EA 250.000 $100.000 $5.000 $5.000 $1.000 $200.000 $75.000
REPLACE TIMBER POST W/ CONC FND
EA 250.000 $100.000 $5.000 $5.000 $50.000 $60.000 $60.000
REPLACE STEEL POST W/ CONC FND
EA 250.000 $100.000 $5.000 $5.000 $1.000 $200.000 $85.000
REALIGN POSTS
EA 100.000 $20.000 $1.000 $1.000 $1.000 $10.000 $20.000
REPLACE BLOCKOUT
EA 100.000 $175.000 $20.000 $300.000 $300.000 $300.000 $50.000
REPAIR STEEL POST WITH BASE PLATE
EA 10.000 $150.000 $20.000 $1.000 $100.000 $600.000 $300.000
RESET SGT IMPACT HEAD
EA 10.000 $250.000 $20.000 $1.000 $100.000 $100.000 $200.000
REPLACE SGT OBJECT MARKER
EA 10.000 $25.000 $20.000 $1.000 $100.000 $100.000 $50.000
REPLACE POSTS (TL-4)(GIBRALTAR)
EA 250.000 $250.000 $750.000 $300.000 $300.000 $300.000 $250.000
REPLACE POSTS (TL-4)(TRINITY)
EA 100.000 $250.000 $500.000 $300.000 $450.000 $300.000 $250.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 5.000 $50.000 $100.000 $100.000 $1,000.000 $500.000 $350.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 5.000 $250.000 $1.000 $0.100 $1.000 $10.000 $3,000.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 5.000 $3,000.000 $6,000.000 $2,000.000 $5,000.000 $5,000.000 $3,000.000
REPLACE CABLE (TL-4)
LF 1,000.000 $5.000 $3.000 $1.000 $1.000 $1.000 $10.000
CHECK / RE-TENSION CABLE (TL-4)
EA 25.000 $750.000 $250.000 $1.000 $1.000 $200.000 $500.000
REPLACE POST HARDWARE (TL-4)
EA 25.000 $50.000 $280.000 $150.000 $200.000 $200.000 $100.000
Totals: $732,750.000 $467,721.000 $606,597.500 $623,244.000 $669,363.000 $1,077,950.000