HALE IH 27 (0067-06-057)

Items: 19

County: HALE
Length: N/A
Highway: IH 27
District: LUBBOCK
Control Number: 0067-06-057
DBE Goal: N/A
Project: NH 2019(118)
Guaranty: N/A
Time: 100 WORKING DAYS
Engineer's Estimate: $1,616,675.10
Date: 09/07/2018 (7 years ago)
Contract Number: N/A
Type: IH 27 ILLUMINATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$1,616,675.10
Over/Under Est: 3.8% $61,503.30
Over/Under Est: 15.27% $246,785.90
Amt Left: 11.04% $185,282.60
Over/Under Est: 28.71% $464,175.64
Amt Left: 23.99% $402,672.34
Delta: -11.67% -$217,389.74

Bid Items & Bid Tabulations

19 Total 0 of 19
HALE  |  IH 27  |  LUBBOCK  |  0067-06-057  |  09/07/2018  |  $1,616,675.10  |  NH 2019(118)  |  IH 27 ILLUM  |  100 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AMERICAN LIGHTING AND SIGNALIZATION, LLC
VACA UNDERGROUND UTILITIES INC
FLORIDA TRAFFIC CONTROL DEVICES, INC.
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 984.000 $200.000 $171.180 $200.000 $290.400
RIPRAP (CONC)(4 IN)
CY 20.000 $200.000 $460.570 $550.000 $1,098.000
MOBILIZATION
LS 1.000 $142,800.000 $168,260.440 $250,000.000 $206,330.980
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $10,000.000 $2,908.870 $3,500.000 $15,141.830
REMOVE RD IL ASM (TRANS-BASE)
EA 144.000 $500.000 $624.780 $400.000 $1,181.320
REMOVE RD IL ASM (U/P)
EA 28.000 $330.000 $257.980 $150.000 $259.730
IN RD IL (U/P) (TY 1) (150W EQ) LED
EA 12.000 $1,200.000 $1,198.790 $1,100.000 $855.630
IN RD IL (U/P) (TY 2) (150W EQ) LED
EA 16.000 $1,200.000 $1,325.250 $1,100.000 $1,279.330
IN RD IL (TY ST) 40T-12 (250W EQ) LED
EA 54.000 $3,000.000 $3,239.250 $3,300.000 $3,407.150
IN RD IL (TY ST) 40T-12-12(250W EQ)LED
EA 69.000 $3,500.000 $3,965.250 $4,000.000 $4,366.120
CONDT (PVC) (SCH 80) (2")
LF 30,155.000 $7.200 $5.220 $9.000 $8.090
CONDT (PVC) (SCH 80) (2") (BORE)
LF 6,215.000 $14.000 $15.910 $16.000 $19.310
CONDT (RM) (3/4")
LF 1,560.000 $25.000 $16.710 $18.000 $12.480
ELEC CONDR (NO.6) BARE
LF 39,930.000 $1.150 $1.230 $1.500 $1.140
ELEC CONDR (NO.6) INSULATED
LF 75,860.000 $1.360 $1.190 $1.600 $1.280
GROUND BOX TY A (122311)W/APRON
EA 51.000 $920.000 $808.390 $725.000 $750.310
REMOVE ELECTRICAL SERVICES
EA 14.000 $400.000 $436.410 $1,000.000 $258.080
ELC SRV TY A 240/480 060(SS)SS(E)SP(O)
EA 16.000 $5,000.000 $5,662.630 $5,200.000 $5,623.830
TMA (STATIONARY)
DAY 600.000 $100.000 $284.860 $200.000 $182.550
Totals: $1,616,675.100 $1,678,178.400 $1,863,461.000 $2,080,850.740