Show Job Controls
Bid Cobra

GUADALUPE FM0775 (6481-17-001)

Items: 18

County: GUADALUPE
Length: 0.0100 MILES
Highway: FM0775
District: SAN ANTONIO
Control Number: 6481-17-001
DBE Goal: 0.0%
Project: BPM - A00214344
Guaranty: $0.00
Time: 10 WORKING DAYS
Engineer's Estimate: $39,973.75
Date: 12/17/2025 (5 months ago) Changed
Contract Number: 12251502
Type: EROSION REPAIR
Project ID: A00214344
Project Description: SCOUR REPAIR BY INSTALLING GABIONS AND WINGWALL REPAIR
Mail/Deliver Bids To: N/A
HENRY FOJTIK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$39,973.75
$33,340.00
Over/Under Est: -16.6% -$6,633.75
$37,988.00
Over/Under Est: -4.97% -$1,985.75
Amt Left: 13.94% $4,648.00
Over/Under Est: 6.51% $2,603.25
Amt Left: 27.71% $9,237.00
Delta: -12.08% -$4,589.00
Over/Under Est: 13.78% $5,510.25
Amt Left: 36.42% $12,144.00
Delta: -6.83% -$2,907.00
Over/Under Est: 48.43% $19,360.25
Amt Left: 77.97% $25,994.00
Delta: -30.45% -$13,850.00

Bid Items & Bid Tabulations

18 Total 0 of 18
GUADALUPE  |  FM0775  |  SAN ANTONIO  |  6481-17-001  |  12/17/2025  |  $39,973.75  |  BPM - A00214344  |  EROSION REPAIR  |  10 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BK FIELD OPERATIONS LLC
TAYLOR BRIDGE LLC
GARRET SHIELDS INFRASTRUCTURE
DIAMOND R CONTRACTING, LLC
TEXAS ROAD CONSTRUCTION, LLC
REMOV CONC (RIPRAP)
SY 28.000 $16.480 $100.000 $100.000 $50.000 $120.000 $125.000
EXCAV (CHANNEL)
CY 10.000 $9.860 $1.000 $150.000 $50.000 $100.000 $600.000
COMPOST MANUF TOPSOIL (4")
SY 250.000 $3.000 $1.000 $2.000 $5.000 $1.000 $12.000
BROADCAST SEED (PERM_URBAN_CLAY)
SY 250.000 $1.060 $1.000 $2.500 $1.500 $1.000 $2.000
SOIL RET BLKT(SL_MOD_CLAY_SHORT)
SY 250.000 $6.620 $5.000 $5.000 $3.000 $1.000 $2.000
FLOWABLE BACKFILL
CY 5.000 $50.500 $1.000 $500.000 $500.000 $150.000 $500.000
RIPRAP (CONC)(5 IN)
CY 8.000 $450.130 $850.000 $500.000 $600.000 $1,000.000 $1,000.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 10.000 $40.180 $1.000 $200.000 $300.000 $500.000 $1,000.000
TYPE A JOINT
LF 17.000 $55.750 $70.000 $100.000 $100.000 $100.000 $40.000
GABION MATTRESSES (GALV)(12 IN)
SY 95.000 $113.830 $130.000 $140.000 $100.000 $100.000 $100.000
MOBILIZATION
LS 1.000 $10,000.000 $4,000.000 $5,000.000 $5,000.000 $10,000.000 $8,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $3,500.000 $1.000 $1.000 $5,000.000 $2,500.000 $500.000
TMA (STATIONARY)
DAY 10.000 $73.780 $1.000 $1.000 $300.000 $1.000 $1.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $21.270 $1.000 $10.000 $10.000 $1.000 $42.000
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $5.140 $1.000 $1.000 $1.000 $1.000 $5.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 95.000 $4.640 $1.000 $5.000 $5.000 $1.000 $3.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 95.000 $0.950 $1.000 $1.000 $1.000 $1.000 $1.000
DRIFTWOOD REMOVAL
LS 1.000 $3,000.000 $4,000.000 $1,000.000 $2,000.000 $2,500.000 $1,000.000
Totals: $39,973.750 $33,340.000 $37,988.000 $42,577.000 $45,484.000 $59,334.000