Bid Cobra

GRIMES BS0006S (6375-83-001)

Items: 40

County: GRIMES
Length: N/A
Highway: BS0006S
District: BRYAN
Control Number: 6375-83-001
DBE Goal: N/A
Project: RMC - 637583001
Guaranty: N/A
Time: 23 W
Engineer's Estimate: $1,633,100.51
Date: 06/29/2022 (3 years ago)
Contract Number: N/A
Type: ASPHALT PAVEMENT REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,633,100.51
$1,743,869.29
Over/Under Est: 6.78% $110,768.78
Over/Under Est: 8.3% $135,557.58
Amt Left: 1.42% $24,788.80
Over/Under Est: 9.29% $151,725.97
Amt Left: 2.35% $40,957.19
Delta: -0.91% -$16,168.39
Over/Under Est: 11.27% $184,089.19
Amt Left: 4.2% $73,320.41
Delta: -1.81% -$32,363.22
Subcontractor Percentage Amount
CEN TEX HYDROSEED, INC. 0.00% $0.00
STRIPE LINES, INC. 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

40 Total 0 of 40
GRIMES  |  BS0006S  |  BRYAN  |  6375-83-001  |  06/29/2022  |  $1,633,100.51  |  RMC - 637583001  |  ASPH PAVMT REPAIR  |  23 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
JAMES CONSTRUCTION GROUP, LLC
TEXAS MATERIALS GROUP, INC.
BIG CREEK CONSTRUCTION, LTD.
REMOVING STAB BASE AND ASPH PAV (7")
SY 617.000 $7.250 $91.150 $26.650 $55.000 $7.500
REMOVING STAB BASE & ASPH PAV (0-6")
SY 2,936.000 $9.250 $6.110 $6.800 $9.000 $6.000
PLANE ASPH CONC PAV(0" TO 2")
SY 59,864.000 $2.000 $3.050 $3.350 $2.800 $2.250
ADJUSTING MANHOLES
EA 13.000 $1,600.000 $1,236.000 $420.060 $900.000 $2,500.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 4.000 $700.000 $870.000 $420.060 $650.000 $1,200.000
MOBILIZATION
LS 1.000 $77,766.690 $76,700.000 $100,000.000 $110,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $4,500.000 $24,500.000 $17,500.000 $2,000.000 $10,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $3.500 $4.280 $7.600 $4.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $1.500 $1.650 $5.150 $1.500 $1.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 500.000 $2.000 $1.650 $5.150 $1.500 $2.000
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 500.000 $5.000 $4.400 $7.400 $4.000 $8.000
INTERSECTIONS (ACP)
SY 631.000 $37.000 $29.800 $33.000 $34.000 $30.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $600.000 $832.000 $749.000 $750.000 $800.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 163.000 $0.270 $1.100 $1.200 $0.780 $0.750
WK ZN PAV MRK NON-REMOV (W)8"(LNDP)
LF 309.000 $1.400 $2.200 $2.400 $3.100 $3.000
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 478.000 $0.680 $2.200 $2.400 $2.050 $2.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 779.000 $0.400 $1.100 $1.200 $0.780 $0.750
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 4,589.000 $0.400 $1.100 $1.200 $0.620 $0.600
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,158.000 $1.180 $1.000 $1.000 $1.900 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,537.000 $1.140 $1.000 $1.000 $1.900 $1.500
REFL PAV MRK TY I (W)8"(LNDP)(100MIL)
LF 309.000 $2.100 $2.200 $2.400 $2.050 $2.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,903.000 $1.000 $2.200 $2.400 $1.550 $1.750
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 720.000 $0.500 $1.100 $1.200 $0.680 $0.750
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 730.000 $0.500 $1.100 $1.200 $4.100 $4.250
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,730.000 $0.500 $0.700 $0.780 $0.680 $0.700
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 20,392.000 $0.500 $0.700 $0.780 $0.620 $0.650
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 162.000 $12.500 $7.200 $7.790 $7.700 $7.750
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 940.000 $14.500 $14.400 $15.580 $14.300 $14.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 11.000 $258.000 $212.000 $227.680 $225.000 $225.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 9.000 $378.000 $389.000 $419.400 $320.000 $325.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 6.000 $494.400 $550.000 $599.150 $465.000 $475.000
PREFAB PAV MRK TY C (W) (WORD)
EA 11.000 $300.000 $300.000 $323.540 $280.000 $300.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 10.000 $600.000 $600.000 $641.090 $485.000 $500.000
REFL PAV MRKR TY I-R
EA 142.000 $4.200 $6.700 $7.190 $4.100 $4.500
REFL PAV MRKR TY II-A-A
EA 412.000 $4.200 $6.700 $7.190 $4.100 $4.500
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 7,081.000 $169.000 $157.620 $172.500 $180.000 $175.000
UNDERSEAL COURSE
GAL 12,559.000 $5.000 $6.340 $2.400 $3.900 $5.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $4,500.000 $5,500.000 $1,850.000 $1,000.000 $10,000.000
TMA (STATIONARY)
DAY 15.000 $150.000 $580.000 $337.500 $185.000 $175.000
TMA (MOBILE OPERATION)
DAY 20.000 $150.000 $900.000 $688.000 $185.000 $325.000
Totals: $1,633,100.510 $1,743,869.290 $1,768,658.090 $1,784,826.480 $1,817,189.700