GRIMES CS (0917-17-081)

Items: 38

County: GRIMES
Length: N/A
Highway: CS
District: BRYAN
Control Number: 0917-17-081
DBE Goal: N/A
Project: STP 2023(205)TAPS
Guaranty: N/A
Time: 144 WORKING DAYS
Engineer's Estimate: $732,188.25
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
JOSEPH GRIEVE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$732,188.25
$854,654.98
Over/Under Est: 16.73% $122,466.73
Over/Under Est: 17.35% $127,011.23
Amt Left: 0.53% $4,544.50
Over/Under Est: 26.16% $191,569.95
Amt Left: 8.09% $69,103.22
Delta: -7.51% -$64,558.72
Over/Under Est: 35.79% $262,014.17
Amt Left: 16.33% $139,547.44
Delta: -7.63% -$70,444.22
Over/Under Est: 46.34% $339,321.96
Amt Left: 25.37% $216,855.23
Delta: -7.78% -$77,307.79
Over/Under Est: 56.83% $416,075.95
Amt Left: 34.35% $293,609.22
Delta: -7.16% -$76,753.99
Subcontractor Percentage Amount
PROMODULAR HARDSCAPES, LLC 15.30% $134,186.27
CEN TEX HYDROSEED, INC. 3.41% $29,906.87
BATTEN DRILLING, INC. 0.75% $6,577.76
BRAZOS PAVING, INC. 0.70% $6,139.24
LONESTAR TRAFFIC SAFETY, LLC 0.47% $4,122.06
AWP SAFETY 0.32% $2,806.51
Total: 20.95% $183,738.71

Bid Items & Bid Tabulations

38 Total 0 of 38
GRIMES  |  CS  |  BRYAN  |  0917-17-081  |  08/02/2023  |  $732,188.25  |  STP 2023(205)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  144 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FUQUA CONSTRUCTION CO., INC.
LARRY YOUNG PAVING, INC.
ENCINO LANDSCAPE, INC.
TI-ZACK CONCRETE, INC.
TEXCON GENERAL CONTRACTORS
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 4.050 $6,500.000 $9,962.428 $1,068.870 $1,000.000 $1,100.000 $4,500.000 $8,400.000
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 3.000 $2,000.000 $951.118 $926.350 $1,000.000 $1,925.000 $2,000.000 $3,000.000
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 2.000 $3,500.000 $2,280.082 $1,710.190 $2,500.000 $3,080.000 $10,000.000 $5,000.000
REMOVING CONC (SIDEWALKS)
SY 218.000 $12.000 $14.994 $25.630 $40.000 $28.450 $46.500 $40.000
REMOVING CONC (DRIVEWAYS)
SY 209.000 $16.000 $19.236 $25.620 $40.000 $37.090 $46.500 $40.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 500.000 $16.000 $6.384 $23.940 $40.000 $31.010 $24.000 $33.000
EXCAVATION (ROADWAY)
CY 25.000 $25.000 $12.012 $80.150 $40.000 $31.010 $50.000 $100.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 387.000 $18.500 $16.282 $81.870 $40.000 $120.560 $30.000 $84.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,473.000 $3.500 $1.596 $8.540 $30.000 $8.420 $9.650 $10.000
BLOCK SODDING
SY 1,473.000 $5.500 $4.998 $8.340 $3.000 $6.600 $6.500 $6.000
VEGETATIVE WATERING
MG 44.200 $25.000 $14.574 $35.680 $1.000 $1.100 $115.000 $36.000
FLEX PAVEMENT STRUCTURE REPAIR (8"-12")
SY 61.000 $85.000 $119.000 $270.180 $200.000 $126.500 $236.000 $190.000
CEM STABIL BKFL
CY 17.000 $75.000 $111.230 $319.900 $200.000 $330.000 $338.000 $300.000
DRILL SHAFT (18 IN)
LF 60.000 $79.000 $168.938 $303.320 $250.000 $440.000 $370.000 $430.000
CL C CONC (ABUT)
CY 12.440 $1,200.000 $1,572.396 $1,761.730 $1,200.000 $4,235.000 $2,000.000 $3,000.000
RETAINING WALL (CONC BLOCK)
SF 1,665.000 $60.000 $66.010 $68.860 $60.000 $60.500 $112.000 $150.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 162.000 $150.000 $210.294 $213.410 $200.000 $220.000 $180.000 $315.000
RAIL (HANDRAIL)(TY E)
LF 57.000 $200.000 $198.184 $136.820 $160.000 $280.500 $262.000 $200.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 2.000 $4,000.000 $7,121.618 $6,011.010 $10,000.000 $9,350.000 $5,000.000 $7,000.000
ADJUSTING MANHOLES
EA 1.000 $1,200.000 $1,089.802 $544.970 $800.000 $487.920 $3,300.000 $1,400.000
REMOVE STR (RAIL)
LF 30.000 $30.000 $37.814 $25.290 $50.000 $27.500 $50.000 $40.000
MOBILIZATION
LS 1.000 $85,000.000 $77,695.800 $85,201.890 $81,000.000 $62,851.260 $125,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $3,000.000 $12,374.278 $1,623.140 $8,500.000 $4,950.000 $5,000.000 $7,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 496.000 $7.500 $3.920 $7.130 $1.000 $5.500 $5.600 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 493.000 $2.500 $0.966 $2.140 $1.000 $1.100 $1.670 $1.500
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,289.000 $5.000 $6.664 $6.410 $1.000 $11.000 $5.000 $4.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,289.000 $1.250 $1.680 $1.430 $1.000 $1.100 $1.150 $1.000
DRIVEWAYS (CONC)
SY 125.000 $75.000 $115.836 $139.170 $120.000 $148.000 $156.000 $130.000
DRIVEWAYS (CONC) (HES)
SY 594.000 $95.000 $110.236 $139.820 $180.000 $154.720 $167.000 $130.000
CONC SIDEWALKS (6")
SY 1,365.000 $72.000 $97.902 $94.650 $110.000 $148.000 $122.000 $125.000
CURB RAMPS (TY 1)
EA 2.000 $2,000.000 $2,695.840 $2,583.350 $2,500.000 $2,790.000 $3,000.000 $2,900.000
CURB RAMPS (TY 7)
EA 8.000 $2,000.000 $2,792.874 $2,524.560 $2,500.000 $2,790.000 $3,000.000 $2,600.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $750.000 $881.258 $961.990 $800.000 $275.000 $800.000 $810.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 3.000 $475.000 $548.842 $705.450 $300.000 $715.000 $590.000 $720.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 87.000 $30.000 $18.676 $64.130 $30.000 $44.000 $26.500 $29.000
THERMO PIPE(18")(HDPE)(TY S)(CSB)
LF 55.000 $60.000 $94.262 $185.480 $200.000 $60.500 $90.000 $120.000
PED STL TRUSS BRG SPAN (60 FT)
EA 1.000 $160,000.000 $109,480.000 $135,406.720 $120,000.000 $137,500.000 $128,720.000 $110,000.000
TMA (MOBILE OPERATION)
DAY 20.000 $350.000 $280.000 $425.120 $300.000 $1.100 $250.000 $300.000
Totals: $732,188.250 $854,655.080 $859,199.491 $923,758.200 $994,202.420 $1,071,510.210 $1,148,264.200