GRIMES FM 3090 (0643-05-067)

Items: 64

County: GRIMES
Length: 0.0000 MILES
Highway: FM 3090
District: BRYAN
Control Number: 0643-05-067
DBE Goal: 0.0%
Project: STP 2B24(385)TAPS
Guaranty: $51,000.00
Time: 198 WORKING DAYS
Engineer's Estimate: $2,492,627.40
Date: 05/06/2026 (5 weeks ago)
Contract Number: 5263024
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00206377
Contract Type: Federal
Project Description: CONSTRUCTION OF 2.6-MILES OF 6-FOOT-WIDE SIDEWALKS AND BICYCLE LANES ALONG BOTH SIDES OF FM 3090/BLACKSHEAR ST. FROM N. RAILROAD STREET TO THE SH 6 FRONTAGE ROAD. THE PROJECT WILL ALSO ADD NEW CROSSWALKS AND SIGNAGE.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ROBBINS
JOHN SHEPHERD
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (10)
E
Engineer's Estimate
$2,492,627.40
$1,828,629.00
Over/Under Est: -26.64% -$663,998.40
Over/Under Est: -18.09% -$450,992.55
Amt Left: 11.65% $213,005.85
Over/Under Est: -16.39% -$408,432.89
Amt Left: 13.98% $255,565.51
Delta: -2.08% -$42,559.66
$2,330,750.60
Over/Under Est: -6.49% -$161,876.80
Amt Left: 27.46% $502,121.60
Delta: -11.83% -$246,556.09
$2,462,384.20
Over/Under Est: -1.21% -$30,243.20
Amt Left: 34.66% $633,755.20
Delta: -5.65% -$131,633.60
$2,462,642.44
Over/Under Est: -1.2% -$29,984.96
Amt Left: 34.67% $634,013.44
Delta: -0.01% -$258.24
$2,547,376.50
Over/Under Est: 2.2% $54,749.10
Amt Left: 39.31% $718,747.50
Delta: -3.44% -$84,734.06
Over/Under Est: 4.53% $112,997.10
Amt Left: 42.49% $776,995.50
Delta: -2.29% -$58,248.00
$2,620,509.98
Over/Under Est: 5.13% $127,882.58
Amt Left: 43.3% $791,880.98
Delta: -0.57% -$14,885.48
$2,927,235.97
Over/Under Est: 17.44% $434,608.57
Amt Left: 60.08% $1,098,606.97
Delta: -11.70% -$306,725.99

Bid Items & Bid Tabulations

64 Total 0 of 64
GRIMES  |  FM 3090  |  BRYAN  |  0643-05-067  |  05/06/2026  |  $2,492,627.40  |  STP 2B24(385)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  198 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
LARRY YOUNG PAVING, INC.
TEXAS STEEL INDUSTRIAL PLACING, LLC
STX CIVIL
ICOS MANAGEMENT, LLC
TI-ZACK CONCRETE, LLC
SKYLINE BRIDGE LLC
TIGHT LINE CONSTRUCTION, LLC
TUCAN CONTRACTING, LLC
BRAZOS PAVING, INC.
PREP ROW (TREE REMOVE) (0"-12" DIA)
EA 3.000 $350.000 $500.000 $1,300.000 $1,000.000 $1,192.000 $1,070.000 $1,045.000 $2,000.000 $600.000 $1,100.000 $6,523.000
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 3.000 $900.000 $1,200.000 $1,500.000 $1,200.000 $2,216.000 $2,140.000 $1,942.600 $3,000.000 $1,500.000 $1,320.000 $2,255.000
TREE PROTECTION (INSTALL)
EA 68.000 $250.000 $100.000 $330.000 $260.000 $314.000 $278.000 $1.100 $100.000 $525.000 $286.000 $670.000
TREE PROTECTION (REMOVE)
EA 68.000 $160.000 $1.000 $130.000 $100.000 $69.000 $107.000 $1.100 $50.000 $100.000 $110.000 $160.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 5,384.800 $13.000 $10.000 $13.000 $10.000 $11.000 $13.000 $22.050 $25.000 $20.000 $5.500 $12.600
RMV (6") TRT/UNTRT BASE & ASPH PAV
SY 997.300 $15.000 $30.000 $9.500 $15.000 $14.000 $16.000 $22.900 $20.000 $10.000 $11.000 $30.350
EXCAV (ROADWAY)
CY 2,510.000 $45.000 $30.000 $31.000 $15.000 $26.000 $13.000 $36.390 $25.000 $40.000 $22.000 $30.000
EMBANK (FNL)(OC)(TY A)
CY 186.000 $30.000 $40.000 $37.000 $40.000 $41.000 $64.000 $115.730 $50.000 $75.000 $38.500 $44.500
EMBANK (VEH)(OC)(TY C)
CY 176.300 $55.000 $40.000 $39.000 $40.000 $61.000 $64.000 $121.130 $50.000 $80.000 $27.500 $37.300
FURN & PLACE TOPSOIL (4")
SY 6,976.000 $2.500 $5.000 $3.500 $5.550 $8.500 $6.000 $8.120 $6.500 $5.500 $6.110 $7.000
BLOCK SODDING
SY 6,976.000 $6.000 $8.000 $5.750 $4.650 $7.500 $5.500 $5.500 $7.000 $7.000 $5.120 $7.000
VEGETATIVE WATERING
TGL 69.800 $45.000 $50.000 $37.000 $35.000 $46.000 $35.000 $1.100 $5.000 $100.000 $110.000 $104.750
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 42.000 $150.000 $200.000 $280.000 $1,200.000 $301.000 $235.000 $247.500 $500.000 $275.000 $1,100.000 $270.000
TACK COAT
GAL 36.000 $4.500 $6.000 $17.000 $16.000 $49.000 $160.000 $11.000 $10.000 $20.000 $7.700 $11.400
PLAN & TEXT CONC PAV(0" TO 1.5")
SY 170.800 $7.500 $10.000 $8.750 $40.000 $14.000 $21.000 $13.200 $35.000 $20.000 $22.000 $51.400
CL A CONC (COLLAR)
EA 2.000 $2,000.000 $1,000.000 $1,500.000 $1,500.000 $3,002.000 $1,712.000 $1,375.000 $2,000.000 $1,250.000 $6,160.000 $800.000
RIPRAP (CONC)(4 IN)
CY 7.000 $1,000.000 $600.000 $720.000 $750.000 $637.000 $856.000 $498.090 $2,000.000 $650.000 $1,100.000 $1,496.000
RIPRAP (STONE COMMON)(DRY)(8 IN)
CY 40.000 $200.000 $200.000 $240.000 $220.000 $285.000 $214.000 $220.000 $300.000 $750.000 $302.500 $627.000
RAIL (HANDRAIL)(TY B)
LF 163.000 $175.000 $150.000 $100.000 $117.950 $157.000 $214.000 $154.000 $250.000 $165.000 $132.000 $120.350
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 76.000 $900.000 $500.000 $420.000 $600.000 $912.000 $535.000 $577.500 $2,000.000 $925.000 $770.000 $1,127.300
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 28.000 $1,050.000 $600.000 $520.000 $800.000 $1,365.000 $642.000 $726.000 $3,000.000 $950.000 $1,650.000 $1,210.600
RC PIPE (CL III)(18 IN)
LF 20.000 $85.000 $100.000 $66.000 $120.000 $90.000 $107.000 $184.800 $80.000 $200.000 $88.000 $148.000
RC PIPE (CL III)(24 IN)
LF 73.000 $135.000 $120.000 $81.000 $120.000 $108.000 $128.000 $198.000 $100.000 $200.000 $154.000 $165.000
RC PIPE (CL III)(36 IN)
LF 16.000 $120.000 $250.000 $150.000 $250.000 $194.000 $321.000 $357.500 $275.000 $350.000 $330.000 $350.000
INLET (COMPL)(TY AAD)(HOU)
EA 2.000 $8,250.000 $5,000.000 $6,400.000 $9,000.000 $8,321.000 $10,700.000 $6,435.000 $8,000.000 $8,500.000 $8,800.000 $8,881.000
SET (TY I)(S= 3 FT)(HW= 3 FT)(6:1)(P)
EA 8.000 $10,000.000 $2,500.000 $4,700.000 $11,000.000 $9,862.000 $9,630.000 $9,845.000 $10,000.000 $13,000.000 $4,730.000 $4,910.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1)(P)
EA 2.000 $14,000.000 $5,000.000 $5,800.000 $20,000.000 $12,065.000 $12,840.000 $10,868.000 $22,000.000 $16,000.000 $13,750.000 $5,040.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 5.000 $2,500.000 $2,000.000 $2,700.000 $2,500.000 $2,711.000 $1,926.000 $2,392.500 $2,000.000 $7,500.000 $2,750.000 $2,845.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 1.000 $4,050.000 $5,000.000 $4,900.000 $5,000.000 $6,065.000 $5,350.000 $4,345.000 $5,000.000 $7,500.000 $6,600.000 $5,825.000
REMOV STR (INLET)
EA 2.000 $1,000.000 $1,000.000 $1,300.000 $1,250.000 $1,314.000 $2,140.000 $1,650.000 $2,500.000 $1,500.000 $1,320.000 $4,045.000
REMOV STR (SET)
EA 12.000 $500.000 $500.000 $650.000 $600.000 $650.000 $856.000 $275.000 $1,000.000 $1,500.000 $550.000 $900.000
REMOV STR (PIPE)
LF 4.000 $50.000 $20.000 $58.000 $150.000 $22.000 $21.000 $27.500 $150.000 $650.000 $55.000 $1,080.000
MOBILIZATION
LS 1.000 $200,000.000 $100,000.000 $179,000.000 $208,434.460 $182,000.000 $78,000.000 $246,816.000 $220,000.000 $240,000.000 $200,000.000 $257,165.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $7,500.000 $5,000.000 $3,800.000 $2,150.000 $3,500.000 $1.000 $3,850.000 $3,500.000 $6,500.000 $2,200.000 $35,400.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $8,000.000 $1,000.000 $1,100.000 $24,000.000 $7,000.000 $10,700.000 $1.100 $10,000.000 $2,500.000 $13,200.000 $19,105.000
TMA (STATIONARY)
DAY 120.000 $300.000 $300.000 $250.000 $250.000 $190.000 $214.000 $1.100 $300.000 $325.000 $330.000 $320.000
TMA (MOBILE OPERATION)
HR 4.000 $500.000 $100.000 $64.000 $1.000 $57.000 $535.000 $1,045.000 $50.000 $75.000 $165.000 $320.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 98.000 $50.000 $20.000 $57.000 $40.000 $75.000 $45.000 $1.100 $50.000 $110.000 $49.500 $44.700
ROCK FILTER DAMS (REMOVE)
LF 98.000 $15.000 $10.000 $31.000 $10.000 $25.000 $25.000 $1.100 $10.000 $25.000 $27.500 $12.750
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,300.000 $4.800 $5.000 $5.000 $4.000 $6.000 $4.000 $1.100 $4.000 $8.000 $4.400 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,300.000 $4.800 $1.000 $1.250 $1.000 $1.000 $1.000 $0.110 $2.000 $4.000 $1.100 $1.300
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 1,088.000 $10.000 $5.000 $11.000 $8.000 $6.000 $8.500 $0.110 $12.000 $20.000 $9.350 $4.800
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,088.000 $2.000 $1.000 $2.000 $1.500 $1.000 $2.000 $0.110 $8.000 $10.000 $1.650 $1.300
COLORED TEXTURED CONC (6")
SY 10.500 $300.000 $120.000 $290.000 $250.000 $206.000 $642.000 $229.680 $800.000 $750.000 $660.000 $496.600
CONC CURB (TY I)
LF 111.000 $20.000 $40.000 $5.500 $50.000 $68.000 $54.000 $53.870 $50.000 $65.000 $110.000 $27.000
CONC CURB (TY II)
LF 52.500 $30.000 $40.000 $6.000 $65.000 $71.000 $75.000 $45.580 $100.000 $65.000 $22.000 $30.400
CONC CURB & GUTTER (TY II)
LF 4,092.600 $40.000 $20.000 $38.000 $40.000 $41.000 $56.000 $53.870 $40.000 $40.000 $27.500 $35.700
CONC CURB (TY C1)
LF 573.900 $150.000 $150.000 $140.000 $140.000 $278.000 $161.000 $88.880 $65.000 $160.000 $27.500 $131.000
CONC CURB (TY F1)
LF 182.000 $250.000 $150.000 $250.000 $200.000 $417.000 $214.000 $111.100 $95.000 $260.000 $66.000 $132.500
DRIVEWAYS (CONC)
SY 270.000 $130.000 $100.000 $170.000 $100.000 $119.000 $192.000 $119.330 $175.000 $95.000 $121.000 $133.550
DRIVEWAYS (CONC) (TY 1)
SY 1,452.000 $155.000 $100.000 $110.000 $100.000 $119.000 $171.000 $138.680 $175.000 $100.000 $181.500 $117.750
DRIVEWAYS (CONC) (TY 2)
SY 1,558.000 $160.000 $100.000 $110.000 $100.000 $119.000 $171.000 $138.680 $200.000 $100.000 $187.000 $118.300
CONC SIDEWALKS (6")
SY 4,727.000 $95.000 $75.000 $86.000 $75.000 $94.000 $96.000 $126.290 $65.000 $90.000 $132.000 $115.500
CURB RAMPS (TY 1)
SY 31.000 $350.000 $300.000 $240.000 $125.000 $94.000 $428.000 $141.600 $100.000 $300.000 $385.000 $204.000
CURB RAMPS (TY 3)
SY 24.000 $200.000 $300.000 $230.000 $125.000 $94.000 $481.000 $142.190 $235.000 $300.000 $385.000 $193.500
CURB RAMPS (TY 5)
SY 102.000 $165.000 $300.000 $220.000 $125.000 $94.000 $363.000 $142.190 $75.000 $300.000 $385.000 $210.650
CURB RAMPS (TY 7)
SY 176.000 $168.000 $300.000 $210.000 $125.000 $94.000 $363.000 $142.190 $65.000 $300.000 $385.000 $187.300
CURB RAMPS (TY 10)
SY 308.000 $170.000 $300.000 $200.000 $125.000 $94.000 $406.000 $142.190 $50.000 $300.000 $385.000 $187.300
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 12.000 $275.000 $300.000 $340.000 $250.000 $690.000 $321.000 $275.000 $500.000 $650.000 $385.000 $319.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 12.000 $720.000 $600.000 $990.000 $550.000 $815.000 $620.000 $495.000 $800.000 $750.000 $825.000 $702.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 66.000 $750.000 $600.000 $650.000 $650.000 $564.000 $727.000 $495.000 $900.000 $700.000 $825.000 $829.500
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $1,000.000 $1,000.000 $890.000 $775.000 $701.000 $856.000 $495.000 $900.000 $800.000 $935.000 $990.000
REMOVE SM RD SN SUP&AM
EA 45.000 $550.000 $100.000 $88.000 $75.000 $94.000 $86.000 $220.000 $100.000 $250.000 $110.000 $95.700
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 296.000 $16.000 $30.000 $17.000 $28.500 $25.000 $32.000 $38.500 $35.000 $40.000 $22.000 $36.400
Totals: $2,492,627.400 $1,828,629.000 $2,041,634.850 $2,084,194.510 $2,330,750.600 $2,462,384.200 $2,462,642.443 $2,547,376.500 $2,605,624.500 $2,620,509.980 $2,927,235.965
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $7,250.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $45,000.00
Total: $62,250.00