GRIMES SH 90 (0315-03-070)
Items: 78
County: GRIMES
Length: 0.0000 MILES
Highway: SH 90
District: BRYAN
Control Number: 0315-03-070
DBE Goal: 0.0%
Project: F 2026(081)
Guaranty: $25,000.00
Time: 67 WORKING DAYS
Engineer's Estimate: $1,274,703.96
Date: 06/02/2026 (8 days ago)
Contract Number: 6263024
Type: INSTALL LEFT AND RIGHT TURN LANES
Project ID: A00206629
Contract Type: Federal
Project Description: INSTALL LEFT AND RIGHT TURN LANES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ROBBINS
JOHN SHEPHERD
GRIMES SH 90 (0315-03-070)
Project Name: N/A
Project: F 2026(081)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.16 MI N OF FM 244
Limits To: 0.31 MI S OF FM 244
Project Description: INSTALL LEFT AND RIGHT TURN LANES
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,274,703.96 | |||
| $1,241,182.50 |
-2.63%
-$33,521.46
|
|||
| $1,252,642.25 |
-1.73%
-$22,061.71
|
0.92%
$11,459.75
|
||
| $1,279,779.39 |
0.4%
$5,075.43
|
3.11%
$38,596.89
|
-2.17%
-$27,137.14
|
|
| $1,335,710.68 |
4.79%
$61,006.72
|
7.62%
$94,528.18
|
-4.37%
-$55,931.29
|
|
| $1,396,389.60 |
9.55%
$121,685.64
|
12.5%
$155,207.10
|
-4.54%
-$60,678.92
|
|
| $1,405,647.55 |
10.27%
$130,943.59
|
13.25%
$164,465.05
|
-0.66%
-$9,257.95
|
|
| $1,708,700.71 |
34.05%
$433,996.75
|
37.67%
$467,518.21
|
-21.56%
-$303,053.16
|
E
Engineer's Estimate
$1,274,703.96
$1,241,182.50
Over/Under Est:
-2.63%
-$33,521.46
$1,252,642.25
Over/Under Est:
-1.73%
-$22,061.71
Amt Left:
0.92%
$11,459.75
$1,279,779.39
Over/Under Est:
0.4%
$5,075.43
Amt Left:
3.11%
$38,596.89
Delta:
-2.17%
-$27,137.14
$1,335,710.68
Over/Under Est:
4.79%
$61,006.72
Amt Left:
7.62%
$94,528.18
Delta:
-4.37%
-$55,931.29
$1,396,389.60
Over/Under Est:
9.55%
$121,685.64
Amt Left:
12.5%
$155,207.10
Delta:
-4.54%
-$60,678.92
$1,405,647.55
Over/Under Est:
10.27%
$130,943.59
Amt Left:
13.25%
$164,465.05
Delta:
-0.66%
-$9,257.95
$1,708,700.71
Over/Under Est:
34.05%
$433,996.75
Amt Left:
37.67%
$467,518.21
Delta:
-21.56%
-$303,053.16
Bid Items & Bid Tabulations
78
Total
0 of 78
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $40,000.00 |
| Total: | $45,000.00 |