GRIMES SH 30 (0212-04-049)
Items: 55
County: GRIMES
Length: 0.0000 MILES
Highway: SH 30
District: BRYAN
Control Number: 0212-04-049
DBE Goal: 0.0%
Project: C 212-4-49
Guaranty: $28,000.00
Time: 113 WORKING DAYS
Engineer's Estimate: $1,381,357.00
Date: 03/04/2025 (1 year ago)
Contract Number: 3253028
Type: DRAINAGE IMPROVEMENTS
Project ID: A00180383
Project Description: DRAINAGE IMPROVEMENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ROBBINS
JOSEPH GREIVE
GRIMES SH 30 (0212-04-049)
Project Name: N/A
Project: C 212-4-49
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: CR 171
Limits To: 0.1 MI E OF FM 244
Project Description: DRAINAGE IMPROVEMENTS
Informational
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,381,357.00 | |||
| $954,997.80 |
-30.87%
-$426,359.20
|
|||
| $1,166,333.95 |
-15.57%
-$215,023.05
|
22.13%
$211,336.15
|
||
| $1,172,553.20 |
-15.12%
-$208,803.80
|
22.78%
$217,555.40
|
-0.53%
-$6,219.25
|
|
| $1,240,578.80 |
-10.19%
-$140,778.20
|
29.9%
$285,581.00
|
-5.80%
-$68,025.60
|
|
| $1,325,176.65 |
-4.07%
-$56,180.35
|
38.76%
$370,178.85
|
-6.82%
-$84,597.85
|
|
| $1,374,186.47 |
-0.52%
-$7,170.53
|
43.89%
$419,188.67
|
-3.70%
-$49,009.82
|
|
| $1,435,589.25 |
3.93%
$54,232.25
|
50.32%
$480,591.45
|
-4.47%
-$61,402.78
|
|
| $1,499,777.78 |
8.57%
$118,420.78
|
57.05%
$544,779.98
|
-4.47%
-$64,188.53
|
|
| $1,559,921.64 |
12.93%
$178,564.64
|
63.34%
$604,923.84
|
-4.01%
-$60,143.86
|
E
Engineer's Estimate
$1,381,357.00
1
Awarded
$954,997.80
Over/Under Est:
-30.87%
-$426,359.20
$1,166,333.95
Over/Under Est:
-15.57%
-$215,023.05
Amt Left:
22.13%
$211,336.15
$1,172,553.20
Over/Under Est:
-15.12%
-$208,803.80
Amt Left:
22.78%
$217,555.40
Delta:
-0.53%
-$6,219.25
$1,240,578.80
Over/Under Est:
-10.19%
-$140,778.20
Amt Left:
29.9%
$285,581.00
Delta:
-5.80%
-$68,025.60
$1,325,176.65
Over/Under Est:
-4.07%
-$56,180.35
Amt Left:
38.76%
$370,178.85
Delta:
-6.82%
-$84,597.85
$1,374,186.47
Over/Under Est:
-0.52%
-$7,170.53
Amt Left:
43.89%
$419,188.67
Delta:
-3.70%
-$49,009.82
$1,435,589.25
Over/Under Est:
3.93%
$54,232.25
Amt Left:
50.32%
$480,591.45
Delta:
-4.47%
-$61,402.78
$1,499,777.78
Over/Under Est:
8.57%
$118,420.78
Amt Left:
57.05%
$544,779.98
Delta:
-4.47%
-$64,188.53
$1,559,921.64
Over/Under Est:
12.93%
$178,564.64
Amt Left:
63.34%
$604,923.84
Delta:
-4.01%
-$60,143.86
| Subcontractor | Percentage | Amount |
|---|---|---|
| CEN TEX HYDROSEED, INC. | 6.99% | $66,754.35 |
| DIIBS SPECIALISTS, LLC | 4.72% | $45,075.90 |
| CEN-TREE SOLUTIONS LLC | 1.26% | $12,032.97 |
| LONESTAR TRAFFIC SAFETY, LLC | 0.78% | $7,448.98 |
| Total: | 13.75% | $131,312.20 |
Bid Items & Bid Tabulations
55
Total
0 of 55
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $70,000.00 |
| Total: | $85,000.00 |