GRIMES BS 6S (0050-11-027)

Items: 62

County: GRIMES
Length: 0.0000 MILES
Highway: BS 6S
District: BRYAN
Control Number: 0050-11-027
DBE Goal: 0.0%
Project: BR 2026(079)
Guaranty: $104,000.00
Time: 73 WORKING DAYS
Engineer's Estimate: $2,599,473.65
Date: 01/06/2026 (5 months ago)
Contract Number: 1263022
Type: BRIDGE MAINTENANCE
Project ID: A00211861
Contract Type: Federal
Project Description: PAINTING, RAIL RETROFIT, DECK OVERLAY, AND CLEAN AND SEAL JOINTS
Mail/Deliver Bids To: N/A
JAMES ROBBINS
JOSEPH GREIVE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$2,599,473.65
$2,838,056.16
Over/Under Est: 9.18% $238,582.51
Over/Under Est: 17.14% $445,432.85
Amt Left: 7.29% $206,850.34
Over/Under Est: 21.37% $555,522.25
Amt Left: 11.17% $316,939.74
Delta: -3.62% -$110,089.40
Over/Under Est: 25.23% $655,812.90
Amt Left: 14.7% $417,230.39
Delta: -3.18% -$100,290.65
Over/Under Est: 31.81% $827,021.31
Amt Left: 20.73% $588,438.80
Delta: -5.26% -$171,208.41
Over/Under Est: 62.41% $1,622,437.60
Amt Left: 48.76% $1,383,855.09
Delta: -23.21% -$795,416.29
Over/Under Est: 75.42% $1,960,393.60
Amt Left: 60.67% $1,721,811.09
Delta: -8.00% -$337,956.00
$4,682,431.35
Over/Under Est: 80.13% $2,082,957.70
Amt Left: 64.99% $1,844,375.19
Delta: -2.69% -$122,564.10

Bid Items & Bid Tabulations

62 Total 0 of 62
GRIMES  |  BS 6S  |  BRYAN  |  0050-11-027  |  01/06/2026  |  $2,599,473.65  |  BR 2026(079)  |  BRIDGE MAINT  |  73 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GIBSON & ASSOCIATES, INC.
GARRET SHIELDS INFRASTRUCTURE
RAGLE CONSTRUCTION, INC.
STRUCTURAL INTEGRITY GROUP LLC
MB WESTERN INDUSTRIAL CONTRACTING CO.
SOUTHERN ROAD & BRIDGE, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
BRAZOS PAVING, INC.
PREPARING ROW
STA 1.000 $2,000.000 $6,500.000 $5,000.000 $50,000.000 $32,750.000 $125,000.000 $25,000.000 $90,000.000 $25,000.000
REMOV CONC (RIPRAP)
SY 63.000 $50.000 $75.000 $100.000 $18.000 $40.000 $50.000 $250.000 $50.000 $90.000
REMOV CONC (CURB)
LF 589.000 $25.000 $35.000 $10.000 $13.000 $23.000 $6.000 $65.000 $10.000 $20.000
EMBANK (VEH)(OC)(TY C)
CY 50.000 $65.000 $182.000 $40.000 $58.000 $45.000 $105.000 $65.000 $100.000 $65.000
FURN & PLACE TOPSOIL (4")
SY 278.000 $5.750 $10.000 $5.000 $8.000 $8.000 $17.000 $15.000 $4.000 $12.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 278.000 $0.750 $14.850 $0.500 $1.000 $2.000 $8.000 $5.000 $10.000 $8.100
VEGETATIVE WATERING
TGL 25.000 $52.000 $50.000 $10.000 $55.000 $50.000 $160.000 $55.000 $1.000 $650.000
ASPH (AC-20-5TR)
GAL 601.000 $7.000 $8.250 $10.000 $10.000 $7.500 $42.000 $10.000 $15.000 $12.500
AGGR (TY-PB OR PL, GR-4)(SAC-B)
CY 12.000 $205.000 $990.000 $320.000 $400.000 $900.000 $355.000 $485.000 $1,000.000 $850.000
SP MIXES SP-C SAC-A PG70-22
TON 1,646.000 $118.000 $187.000 $220.000 $220.000 $170.000 $322.000 $355.000 $190.000 $185.000
TACK COAT
GAL 1,799.000 $4.000 $6.600 $8.000 $8.000 $6.000 $12.000 $15.000 $6.000 $8.000
PLANE ASPH CONC PAV(0" TO 8")
SY 8,384.000 $3.500 $9.900 $8.000 $6.500 $12.750 $18.000 $10.000 $10.000 $6.500
PLANE ASPH CONC PAV (1" TO 2")
SY 2,772.000 $5.000 $6.600 $7.000 $5.250 $10.500 $7.000 $20.000 $12.000 $4.500
CEM STABIL BKFL
CY 17.000 $265.000 $440.000 $200.000 $160.000 $340.000 $100.000 $550.000 $300.000 $150.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 365.000 $45.000 $1.000 $60.000 $100.000 $1.000 $286.000 $300.000 $180.000 $130.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 1,165.000 $160.000 $20.000 $150.000 $35.000 $140.000 $350.000 $285.000 $320.000 $307.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 553.000 $170.000 $50.000 $200.000 $75.000 $190.000 $550.000 $385.000 $450.000 $383.500
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 30.000 $350.000 $325.000 $200.000 $350.000 $818.000 $350.000 $1,500.000 $400.000 $991.200
RIPRAP (CONC)(CL B)(5 IN)
CY 10.000 $650.000 $1,077.000 $1,000.000 $680.000 $775.000 $800.000 $1,250.000 $2,000.000 $1,005.000
RIPRAP (MOW STRIP)(4 IN)
CY 42.000 $750.000 $742.500 $700.000 $570.000 $675.000 $800.000 $1,250.000 $800.000 $1,200.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 15.000 $250.000 $550.000 $300.000 $310.000 $400.000 $350.000 $600.000 $400.000 $350.000
CLEANING AND SEALING EXISTING JOINTS
LF 928.000 $60.000 $33.000 $40.000 $25.000 $28.000 $55.000 $55.000 $60.000 $47.200
POLYESTER POLYMER CONC OVERLAY (3/4")
SY 8,813.000 $108.000 $109.000 $115.000 $135.000 $120.650 $14.000 $95.000 $160.000 $132.200
MISC NON-BRIDGE (NBIS)
LB 168.000 $25.000 $35.000 $30.000 $38.000 $55.000 $34.000 $25.000 $50.000 $295.000
CLEAN & PAINT EXIST STR (SYSTEM I)
LS 1.000 $157,000.000 $194,700.000 $250,000.000 $325,000.000 $261,120.000 $338,500.000 $385,000.000 $310,000.000 $336,300.000
RETROFIT RAIL (TY SSTR)
LF 698.000 $260.000 $162.000 $180.000 $115.000 $270.000 $250.000 $295.000 $180.000 $472.000
HEADER TYPE EXPANSION JOINT
CF 153.000 $400.000 $424.000 $400.000 $230.000 $380.000 $385.000 $385.000 $500.000 $708.000
MOBILIZATION
LS 1.000 $257,000.000 $247,000.000 $200,000.000 $310,000.000 $320,000.000 $250,000.000 $400,000.000 $380,000.000 $620,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $5,000.000 $19,400.000 $5,000.000 $20,000.000 $13,750.000 $2,500.000 $10,000.000 $44,000.000 $12,150.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 197.000 $95.000 $74.000 $10.000 $60.000 $50.000 $300.000 $65.000 $100.000 $300.000
TMA (STATIONARY)
DAY 134.000 $300.000 $250.000 $300.000 $240.000 $250.000 $300.000 $300.000 $300.000 $1,900.000
TMA (MOBILE OPERATION)
DAY 21.000 $500.000 $100.000 $300.000 $570.000 $250.000 $350.000 $950.000 $300.000 $710.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 468.000 $20.000 $113.190 $10.000 $45.000 $45.000 $23.000 $35.000 $5.000 $235.000
CONSTRUCTION EXITS (REMOVE)
SY 468.000 $10.000 $60.500 $1.000 $12.000 $15.000 $5.000 $22.000 $5.000 $31.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,602.000 $4.000 $7.870 $5.000 $4.000 $3.000 $4.000 $5.000 $1.000 $11.800
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,602.000 $1.000 $3.850 $1.000 $1.250 $1.000 $1.000 $2.000 $1.000 $3.150
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $31.000 $28.600 $35.000 $22.750 $22.750 $38.000 $37.000 $25.000 $28.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,450.000 $2,090.000 $2,500.000 $1,830.000 $1,830.000 $2,000.000 $3,500.000 $1,800.000 $2,300.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,620.000 $1,705.000 $1,500.000 $1,550.000 $1,550.000 $1,200.000 $1,500.000 $1,400.000 $1,600.000
REMOVE METAL BEAM GUARD FENCE
LF 600.000 $6.000 $3.300 $5.000 $5.000 $5.000 $5.000 $5.000 $2.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $275.000 $302.500 $500.000 $175.000 $175.000 $350.000 $320.000 $500.000 $300.000
RM MTL BM GD FEN TRANS (T101)
EA 4.000 $600.000 $236.500 $500.000 $200.000 $200.000 $350.000 $360.000 $500.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,400.000 $3,520.000 $4,000.000 $2,880.000 $2,880.000 $3,000.000 $4,250.000 $3,000.000 $3,600.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $530.000 $302.500 $500.000 $250.000 $250.000 $500.000 $430.000 $500.000 $300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 4.000 $25.000 $45.000 $20.000 $21.000 $25.000 $100.000 $34.000 $40.000 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 2.000 $35.000 $44.000 $30.000 $45.000 $45.000 $100.000 $40.000 $40.000 $27.250
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB
EA 4.000 $26.000 $45.000 $20.000 $21.000 $25.000 $100.000 $34.000 $40.000 $25.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 3.000 $30.000 $44.000 $30.000 $45.000 $45.000 $100.000 $40.000 $40.000 $27.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 180.000 $2.000 $10.000 $1.000 $1.000 $5.000 $2.000 $15.000 $5.000 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 138.000 $1.500 $10.000 $1.000 $1.000 $5.000 $2.000 $15.000 $5.000 $1.500
RE PM TY II (W) 6" (BRK)
LF 520.000 $0.650 $1.100 $15.000 $1.000 $0.750 $2.500 $3.500 $3.500 $1.200
RE PM TY II (W) 6" (SLD)
LF 2,088.000 $0.650 $1.100 $3.000 $1.000 $0.750 $2.500 $3.500 $3.250 $1.200
RE PM TY II (Y) 6" (SLD)
LF 2,083.000 $0.650 $1.100 $3.000 $1.000 $0.750 $2.500 $3.500 $3.250 $1.200
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 672.000 $1.000 $1.100 $2.500 $1.000 $1.150 $2.500 $4.000 $3.000 $1.800
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 6,126.000 $1.000 $1.050 $2.500 $0.950 $0.850 $2.500 $4.000 $3.000 $1.800
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 360.000 $1.000 $1.650 $20.000 $1.500 $1.150 $2.500 $4.000 $3.000 $1.800
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 3,296.000 $1.000 $1.050 $2.500 $0.950 $1.150 $2.500 $4.000 $3.000 $1.800
REFL PAV MRKR TY II-A-A
EA 26.000 $7.000 $8.800 $12.000 $8.000 $9.000 $10.000 $14.000 $15.000 $7.100
REFL PAV MRKR TY II-C-R
EA 36.000 $6.000 $8.800 $200.000 $8.000 $9.000 $10.000 $13.000 $15.000 $7.100
PAV SURF PREP FOR MRK (6")
LF 4,691.000 $0.500 $0.550 $1.500 $0.500 $0.550 $0.060 $0.250 $0.500 $0.600
REP STL BRIDGE MEMBER(REPL RIVET/BOLT)
EA 18.000 $300.000 $425.000 $300.000 $500.000 $500.000 $3,500.000 $385.000 $5,000.000 $1,770.000
STEEL BRIDGE ZONE PAINTING
LS 1.000 $103,000.000 $249,700.000 $275,000.000 $200,000.000 $247,680.000 $354,350.000 $335,000.000 $300,000.000 $168,150.000
Totals: $2,599,473.650 $2,838,056.160 $3,044,906.500 $3,154,995.900 $3,255,286.550 $3,426,494.960 $4,221,911.250 $4,559,867.250 $4,682,431.350