Show Job Controls
Bid Cobra

GRIMES BS 6S (0050-11-026)

Items: 15

County: GRIMES
Length: 0.0000 MILES
Highway: BS 6S
District: BRYAN
Control Number: 0050-11-026
DBE Goal: 0.0%
Project: F 2026(021)
Guaranty: $100,000.00
Time: 100 WORKING DAYS
Engineer's Estimate: $7,484,903.06
Date: 09/05/2025 (9 months ago)
Contract Number: 9253213
Type: PROFILE MARKINGS
Project ID: A00208682
Contract Type: Federal
Project Description: PROFILE MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES KREAMER
CHARLIE REED
JASON MAREK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$7,484,903.06
$4,945,869.75
Over/Under Est: -33.92% -$2,539,033.31
Over/Under Est: -30.56% -$2,287,087.41
Amt Left: 5.09% $251,945.90
Over/Under Est: -29.3% -$2,193,425.81
Amt Left: 6.99% $345,607.50
Delta: -1.80% -$93,661.60
$5,373,949.86
Over/Under Est: -28.2% -$2,110,953.20
Amt Left: 8.66% $428,080.11
Delta: -1.56% -$82,472.61
Over/Under Est: -20.32% -$1,520,881.91
Amt Left: 20.59% $1,018,151.40
Delta: -10.98% -$590,071.29
Over/Under Est: -18.58% -$1,390,792.90
Amt Left: 23.22% $1,148,240.41
Delta: -2.18% -$130,089.01
$6,226,389.46
Over/Under Est: -16.81% -$1,258,513.60
Amt Left: 25.89% $1,280,519.71
Delta: -2.17% -$132,279.30
$6,438,868.16
Over/Under Est: -13.98% -$1,046,034.90
Amt Left: 30.19% $1,492,998.41
Delta: -3.41% -$212,478.70
Subcontractor Percentage Amount
AWP SAFETY 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

15 Total 0 of 15
GRIMES  |  BS 6S  |  BRYAN  |  0050-11-026  |  09/05/2025  |  $7,484,903.06  |  F 2026(021)  |  PROFILE MRK  |  100 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPING TECHNOLOGY, L.P.
GREY SKY CONSTRUCTION LLC
D. I. J. CONSTRUCTION, INC.
STRIPE-A-ZONE, LLC
CENTERLINE TECHNOLOGIES, LLC
TRP INFRASTRUCTURE SERVICES, LLC
STRIPE LINES, INC.
PAVEMENT MARKINGS INC.
MOBILIZATION
LS 1.000 $70,000.000 $35,000.000 $500,000.000 $42,000.000 $45,000.000 $100,000.000 $443,400.000 $25,000.000 $132,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $20,000.000 $20,000.000 $8,500.000 $6,500.000 $500.000 $1.000 $23,800.000 $500.000 $50.000
TMA (STATIONARY)
DAY 147.000 $100.000 $125.000 $250.000 $1.000 $1.000 $1.000 $30.000 $10.000 $5.000
TMA (MOBILE OPERATION)
DAY 172.000 $100.000 $125.000 $550.000 $255.000 $1.000 $1.000 $975.000 $10.000 $10.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 1,372.000 $2.550 $1.000 $2.000 $2.000 $1.100 $0.900 $1.500 $0.810 $3.900
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 34,002.000 $2.130 $0.920 $2.000 $0.700 $0.700 $0.900 $0.685 $0.810 $1.400
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 2,245,794.000 $0.750 $0.520 $0.550 $0.620 $0.640 $0.580 $0.645 $0.660 $0.680
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 1,509,070.000 $0.750 $0.520 $0.550 $0.650 $0.640 $0.580 $0.645 $0.670 $0.740
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 168,156.000 $0.750 $0.600 $0.550 $0.650 $0.640 $0.580 $0.725 $0.670 $0.840
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 64,856.000 $0.550 $0.460 $0.550 $0.410 $0.470 $0.500 $0.475 $0.440 $0.720
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 1,861,416.000 $0.550 $0.460 $0.550 $0.400 $0.440 $0.500 $0.435 $0.440 $0.620
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 144,509.000 $0.500 $0.460 $0.550 $0.410 $0.470 $0.500 $0.475 $0.450 $0.680
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 1,184,102.000 $0.550 $0.460 $0.550 $0.410 $0.460 $0.500 $0.435 $0.450 $0.620
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 163,461.000 $5.000 $2.350 $1.000 $2.800 $2.950 $3.950 $2.700 $4.330 $3.200
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 324,910.000 $5.000 $2.350 $1.000 $2.700 $2.600 $3.950 $2.700 $4.330 $2.800
Totals: $7,484,903.060 $4,945,869.750 $5,197,815.650 $5,291,477.250 $5,373,949.860 $5,964,021.150 $6,094,110.155 $6,226,389.460 $6,438,868.160
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $150,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) $20,000.00
Total: $185,000.00