Show Job Controls
Bid Cobra

GRIMES SH 6 (0050-03-100)

Items: 41

County: GRIMES
Length: N/A
Highway: SH 6
District: BRYAN
Control Number: 0050-03-100
DBE Goal: N/A
Project: C 50-3-100
Guaranty: N/A
Time: 72 WORKING DAYS
Engineer's Estimate: $6,519,921.25
Date: 07/10/2018 (7 years ago)
Contract Number: N/A
Type: OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$6,519,921.25
$5,798,125.91
Over/Under Est: -11.07% -$721,795.34
Over/Under Est: -5.09% -$331,983.56
Amt Left: 6.72% $389,811.78
Over/Under Est: -2.81% -$183,140.48
Amt Left: 9.29% $538,654.86
Delta: -2.41% -$148,843.08
Subcontractor Percentage Amount
DUSTROL, INC. 3.39% $243,892.23
CPAVE, INC. 2.90% $208,639.37
BATTERSON, LLP 2.45% $176,264.29
CEN TEX HYDROSEED, INC. 0.40% $28,777.84
SURFACE PREPARATION TECHNOLOGIES, LLC 0.29% $20,863.94
AREA WIDE PROTECTIVE, INC. 0.10% $7,194.46
Total: 9.53% $685,632.13

Bid Items & Bid Tabulations

41 Total 0 of 41
GRIMES  |  SH 6  |  BRYAN  |  0050-03-100  |  07/10/2018  |  $6,519,921.25  |  C 50-3-100  |  OVERLAY  |  72 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
BIG CREEK CONSTRUCTION, LTD.
ANGEL BROTHERS HOLDINGS CORP.
BACKFILL (TY A OR B)
STA 1,454.650 $150.000 $77.000 $100.000 $90.000
ASPH (SPG 73-19)
GAL 42,849.000 $3.000 $3.300 $3.500 $3.500
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
CY 952.000 $100.000 $137.000 $115.000 $90.000
PFC (ASPHALT) PG76-22
TON 2,086.000 $101.000 $111.000 $111.000 $108.250
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 31,035.000 $101.000 $111.000 $111.000 $108.250
SUPERPAVE MIXTURES SP-C PG70-22
TON 3,238.000 $85.000 $85.000 $85.000 $99.000
SUPERPAVE MIXTURES SP-D SAC-A PG76-22
TON 1,388.000 $90.000 $88.000 $90.000 $104.000
PLANE ASPH CONC PAV (3")
SY 11,246.000 $1.500 $4.600 $5.000 $5.750
PLANE ASPH CONC PAV(MICRO-MLLING)(1")
SY 281,999.000 $1.250 $0.600 $1.250 $1.300
PLANE ASPH CONC PAV(1.25" MICRO-MILL)
SY 298,521.000 $1.250 $0.700 $1.250 $1.300
HEADER TYPE EXPANSION JOINT
CF 668.000 $385.000 $352.000 $300.000 $285.000
JOINT SEALANT
LF 2,864.000 $20.000 $7.000 $10.000 $10.000
MOBILIZATION
LS 1.000 $600,000.000 $97,000.000 $80,000.000 $287,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $7,000.000 $1,900.000 $2,500.000 $4,500.000
DRIVEWAYS (SURF TREAT)
SY 4,085.000 $2.500 $8.000 $5.000 $7.250
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 232,775.000 $0.280 $0.100 $0.120 $0.210
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 15,057.000 $1.150 $1.000 $1.000 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 102.000 $1.150 $1.000 $1.000 $0.500
REFL PAV MRK TY I (W)4"(DOT)(060MIL)
LF 1,848.000 $0.850 $0.240 $0.230 $1.150
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 528.000 $0.850 $0.360 $0.340 $1.250
REFL PAV MRK TY I (W)8"(SLD)(060MIL)
LF 38,930.000 $0.850 $0.450 $0.420 $0.540
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 29,335.000 $0.850 $0.480 $0.450 $0.700
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 203.000 $2.000 $11.000 $10.000 $5.500
REFL PAV MRK TY I (W)(ARROW)(060MIL)
EA 19.000 $70.000 $59.000 $55.000 $95.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 66.000 $108.000 $69.000 $65.000 $95.000
REFL PAV MRK TY I(W)(LNDP ARW)(060MIL)
EA 18.000 $300.000 $90.000 $85.000 $160.000
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 18.000 $365.000 $100.000 $95.000 $160.000
REF PAV MRK TY I(W)36"(YLD TRI)(060MIL)
EA 18.000 $33.000 $27.000 $25.000 $37.550
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 324.000 $33.000 $32.000 $30.000 $38.350
RE PM W/RET REQ TY I (W)4"(BRK)(060MIL)
LF 760.000 $0.300 $0.280 $0.260 $1.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 38,036.000 $0.300 $0.300 $0.280 $0.320
RE PM W/RET REQ TY I (W)4"(SLD)(060MIL)
LF 23,930.000 $0.300 $0.280 $0.260 $0.220
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 129,405.000 $0.300 $0.300 $0.280 $0.310
RE PM W/RET REQ TY I (Y)4"(SLD)(060MIL)
LF 36,330.000 $0.300 $0.280 $0.260 $0.220
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 115,245.000 $0.300 $0.300 $0.280 $0.310
REFL PAV MRKR TY II-A-A
EA 41.000 $3.250 $3.200 $3.000 $5.000
REFL PAV MRKR TY II-C-R
EA 8,046.000 $3.250 $3.200 $3.000 $3.150
MEMBRANE UNDERSEAL
GAL 110,298.000 $2.500 $2.370 $3.000 $2.400
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $2,500.000 $5,000.000 $3,500.000
TMA (STATIONARY)
EA 2.000 $10,000.000 $2,000.000 $10,000.000 $6,000.000
TMA (MOBILE OPERATION)
DAY 42.000 $250.000 $600.000 $200.000 $55.000
Totals: $6,519,921.250 $5,798,125.910 $6,187,937.690 $6,336,780.770