Show Job Controls
Bid Cobra

GREGG US0271 (6386-04-001)

Items: 29

County: GREGG
Length: N/A
Highway: US0271
District: TYLER
Control Number: 6386-04-001
DBE Goal: N/A
Project: BPM - 638604001
Guaranty: N/A
Time: 151 CALENDAR DAYS
Engineer's Estimate: $471,744.35
Date: 10/07/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (1)
E
Engineer's Estimate
$471,744.35
$432,432.20
Over/Under Est: -8.33% -$39,312.15

Bid Items & Bid Tabulations

29 Total 0 of 29
GREGG  |  US0271  |  TYLER  |  6386-04-001  |  10/07/2021  |  $471,744.35  |  BPM - 638604001  |  BRIDGE PREVENT MAINT  |  151 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RED BARON BUILDING COMPANY, LLC
REMOVING CONC (RIPRAP)
SY 83.000 $40.000 $30.000
EXCAVATION (CHANNEL)
CY 322.000 $35.000 $30.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 394.000 $30.000 $26.000
BOND FBR MTRX SEED (PERM) (URBAN)(SAND)
SY 1,845.000 $1.500 $2.250
VEGETATIVE WATERING
MG 20.295 $30.000 $10.000
FLOWABLE BACKFILL
CY 48.000 $250.000 $200.000
TEMPORARY SPL SHORING
SF 200.000 $25.000 $100.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 65.000 $200.000 $200.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 58.000 $150.000 $165.000
RIPRAP (CONC)(4 IN)
CY 15.000 $500.000 $400.000
RIPRAP (CONC)(5 IN)
CY 22.000 $600.000 $425.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 621.000 $250.000 $250.000
CLEANING AND SEALING EXISTING JOINTS
LF 2,268.000 $40.000 $30.000
CLEANING EXISTING JOINTS
LF 336.000 $8.000 $24.000
GABIONS (3' X 3')(GALV)
CY 24.000 $250.000 $250.000
GABION (1.5' X 3')(GALV)
CY 12.000 $250.000 $250.000
WINGWALL (FW - 0) (HW=11 FT)
EA 1.000 $12,000.000 $7,500.000
REMOV STR (WINGWALL)
EA 1.000 $1,500.000 $1,500.000
ADJUST STL SHOES
EA 2.000 $6,000.000 $10,000.000
MOBILIZATION
LS 1.000 $40,000.000 $35,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $2,500.000 $1,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 800.000 $3.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 800.000 $1.500 $1.500
TREE AND BRUSH REMOVAL
AC 3.200 $3,000.000 $1,000.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 150.000 $10.000 $20.000
REPAIR (EXISTING METAL PED. RAIL)
LF 70.000 $150.000 $70.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 32.000 $50.000 $30.000
BRIDGE JOINT REPAIR (FINGER JNT)
LF 24.000 $250.000 $150.000
TMA (STATIONARY)
DAY 47.000 $300.000 $150.000
Totals: $471,744.350 $432,432.200