GREGG SL 281 (2642-01-049)

Items: 22

County: GREGG
Length: N/A
Highway: SL 281
District: TYLER
Control Number: 2642-01-049
DBE Goal: N/A
Project: STP 2B23(070)HES
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $246,509.89
Date: 08/03/2023 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$246,509.89
$225,254.70
Over/Under Est: -8.62% -$21,255.19
$234,149.50
Over/Under Est: -5.01% -$12,360.39
Amt Left: 3.95% $8,894.80
Over/Under Est: 10.54% $25,977.11
Amt Left: 20.97% $47,232.30
Delta: -16.37% -$38,337.50
Over/Under Est: 14.37% $35,423.11
Amt Left: 25.16% $56,678.30
Delta: -3.47% -$9,446.00
$294,033.50
Over/Under Est: 19.28% $47,523.61
Amt Left: 30.53% $68,778.80
Delta: -4.29% -$12,100.50
Over/Under Est: 20.54% $50,632.11
Amt Left: 31.91% $71,887.30
Delta: -1.06% -$3,108.50
Over/Under Est: 34.95% $86,144.11
Amt Left: 47.68% $107,399.30
Delta: -11.95% -$35,512.00
Over/Under Est: 41.37% $101,983.34
Amt Left: 54.71% $123,238.53
Delta: -4.76% -$15,839.23
Subcontractor Percentage Amount
MORRIS COUNTY CONTRACTORS, L.L.C. 12.94% $29,147.96
FLEX SUPPLY, LLC 2.43% $5,473.69
Total: 15.37% $34,621.65

Bid Items & Bid Tabulations

22 Total 0 of 22
GREGG  |  SL 281  |  TYLER  |  2642-01-049  |  08/03/2023  |  $246,509.89  |  STP 2B23(070)HES  |  HAZARD ELIM & SAFETY  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
3LW CIVIL LLC
GARRET SHIELDS INFRASTRUCTURE
TRUE ROADS CONSTRUCTION, LLC
HJC FARMS, INC.
ICOS MANAGEMENT, LLC
EAST TEXAS BRIDGE, INC.
SCOUT 5 CONSTRUCTION LLC
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 200.000 $50.000 $30.000 $35.000 $40.000 $60.000 $55.000 $33.000 $35.000 $60.000
FURNISHING AND PLACING TOPSOIL (4")
SY 269.000 $12.130 $6.000 $4.000 $2.000 $30.000 $6.000 $6.000 $8.000 $35.000
BROADCAST SEED (PERM) (URBAN) (SANDY)
SY 269.000 $0.690 $4.000 $0.500 $1.000 $7.000 $0.500 $1.000 $8.000 $2.000
VEGETATIVE WATERING
MG 1.000 $41.000 $20.000 $10.000 $1,000.000 $100.000 $100.000 $1.000 $500.000 $1,500.000
RIPRAP (MOW STRIP)(4 IN)
CY 49.000 $723.620 $875.000 $500.000 $500.000 $800.000 $650.000 $605.000 $750.000 $900.000
MOBILIZATION
LS 1.000 $31,220.790 $25,000.000 $20,000.000 $25,000.000 $27,500.000 $50,000.000 $25,000.000 $30,000.000 $45,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $11,939.050 $2,000.000 $8,000.000 $4,000.000 $7,500.000 $1,000.000 $1.000 $5,000.000 $0.010
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 5.000 $50.030 $20.000 $30.000 $100.000 $100.000 $75.000 $330.000 $50.000 $470.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 5.000 $119.990 $100.000 $30.000 $200.000 $100.000 $100.000 $550.000 $50.000 $110.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 20.000 $2.020 $5.000 $0.250 $5.000 $25.000 $1.000 $1.000 $5.000 $12.000
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 5.000 $159.750 $100.000 $100.000 $200.000 $100.000 $200.000 $550.000 $60.000 $130.000
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 20.000 $13.360 $20.000 $12.000 $5.000 $25.000 $50.000 $1.000 $20.000 $28.000
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 600.000 $126.680 $165.000 $210.000 $250.000 $205.000 $250.000 $275.000 $305.000 $310.000
MTL W-BEAM GD FEN (STEEL POST)
LF 350.000 $41.970 $28.350 $22.000 $50.000 $30.000 $32.000 $44.000 $30.000 $45.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,375.850 $2,100.000 $2,350.000 $3,000.000 $2,400.000 $2,600.000 $4,400.000 $2,200.000 $2,600.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,421.950 $2,940.000 $2,700.000 $3,500.000 $3,400.000 $3,500.000 $4,400.000 $3,100.000 $3,500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 4.000 $78.410 $18.900 $60.000 $40.000 $30.000 $25.000 $55.000 $25.000 $60.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 4.000 $27.850 $18.900 $71.000 $40.000 $30.000 $25.000 $55.000 $25.000 $60.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 8.000 $41.050 $21.000 $60.000 $40.000 $40.000 $40.000 $55.000 $25.000 $60.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 8.000 $44.350 $21.000 $60.000 $40.000 $40.000 $40.000 $55.000 $25.000 $60.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $339.290 $175.000 $25.000 $1.000 $130.000 $100.000 $220.000 $125.000 $200.000
TMA (STATIONARY)
DAY 20.000 $339.290 $400.000 $25.000 $200.000 $400.000 $250.000 $275.000 $1,000.000 $0.010
Totals: $246,509.890 $225,254.700 $234,149.500 $272,487.000 $281,933.000 $294,033.500 $297,142.000 $332,654.000 $348,493.230