GREGG YOUNG (0910-07-087)
Items: 32
County: GREGG
Length: 0.0000 MILES
Highway: YOUNG
District: TYLER
Control Number: 0910-07-087
DBE Goal: 3.0%
Project: STP 2025(755)HES
Guaranty: $17,000.00
Time: 90 WORKING DAYS
Engineer's Estimate: $834,529.00
Date: 05/01/2025 (1 year ago)
Contract Number: 5253031
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00184614
Contract Type: Federal
Project Description: INSTALL SIDEWALKS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
KYLE DYKES
STACY WILEY
GREGG YOUNG (0910-07-087)
Project Name: N/A
Project: STP 2025(755)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: MOBBERLY AVE
Limits To: MLK BLVD
Project Description: INSTALL SIDEWALKS
Bidders (13)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$834,529.00 | |||
| $620,186.45 |
-25.68%
-$214,342.55
|
|||
| $706,597.45 |
-15.33%
-$127,931.55
|
13.93%
$86,411.00
|
||
| $760,899.00 |
-8.82%
-$73,630.00
|
22.69%
$140,712.55
|
-7.68%
-$54,301.55
|
|
| $769,149.00 |
-7.83%
-$65,380.00
|
24.02%
$148,962.55
|
-1.08%
-$8,250.00
|
|
| $779,160.00 |
-6.63%
-$55,369.00
|
25.63%
$158,973.55
|
-1.30%
-$10,011.00
|
|
| $788,948.00 |
-5.46%
-$45,581.00
|
27.21%
$168,761.55
|
-1.26%
-$9,788.00
|
|
| $816,179.00 |
-2.2%
-$18,350.00
|
31.6%
$195,992.55
|
-3.45%
-$27,231.00
|
|
| $923,367.00 |
10.65%
$88,838.00
|
48.89%
$303,180.55
|
-13.13%
-$107,188.00
|
|
| $956,350.00 |
14.6%
$121,821.00
|
54.2%
$336,163.55
|
-3.57%
-$32,983.00
|
|
| $980,980.00 |
17.55%
$146,451.00
|
58.18%
$360,793.55
|
-2.58%
-$24,630.00
|
|
| $1,019,259.00 |
22.14%
$184,730.00
|
64.35%
$399,072.55
|
-3.90%
-$38,279.00
|
|
| $1,083,875.00 |
29.88%
$249,346.00
|
74.77%
$463,688.55
|
-6.34%
-$64,616.00
|
|
| $1,278,352.50 |
53.18%
$443,823.50
|
106.12%
$658,166.05
|
-17.94%
-$194,477.50
|
E
Engineer's Estimate
$834,529.00
1
Awarded
$620,186.45
Over/Under Est:
-25.68%
-$214,342.55
$706,597.45
Over/Under Est:
-15.33%
-$127,931.55
Amt Left:
13.93%
$86,411.00
$760,899.00
Over/Under Est:
-8.82%
-$73,630.00
Amt Left:
22.69%
$140,712.55
Delta:
-7.68%
-$54,301.55
$769,149.00
Over/Under Est:
-7.83%
-$65,380.00
Amt Left:
24.02%
$148,962.55
Delta:
-1.08%
-$8,250.00
$779,160.00
Over/Under Est:
-6.63%
-$55,369.00
Amt Left:
25.63%
$158,973.55
Delta:
-1.30%
-$10,011.00
$788,948.00
Over/Under Est:
-5.46%
-$45,581.00
Amt Left:
27.21%
$168,761.55
Delta:
-1.26%
-$9,788.00
$816,179.00
Over/Under Est:
-2.2%
-$18,350.00
Amt Left:
31.6%
$195,992.55
Delta:
-3.45%
-$27,231.00
$923,367.00
Over/Under Est:
10.65%
$88,838.00
Amt Left:
48.89%
$303,180.55
Delta:
-13.13%
-$107,188.00
$956,350.00
Over/Under Est:
14.6%
$121,821.00
Amt Left:
54.2%
$336,163.55
Delta:
-3.57%
-$32,983.00
$980,980.00
Over/Under Est:
17.55%
$146,451.00
Amt Left:
58.18%
$360,793.55
Delta:
-2.58%
-$24,630.00
$1,019,259.00
Over/Under Est:
22.14%
$184,730.00
Amt Left:
64.35%
$399,072.55
Delta:
-3.90%
-$38,279.00
$1,083,875.00
Over/Under Est:
29.88%
$249,346.00
Amt Left:
74.77%
$463,688.55
Delta:
-6.34%
-$64,616.00
$1,278,352.50
Over/Under Est:
53.18%
$443,823.50
Amt Left:
106.12%
$658,166.05
Delta:
-17.94%
-$194,477.50
| Subcontractor | Percentage | Amount |
|---|---|---|
| CAP RIVER LLC | 3.71% | $23,008.92 |
| TEXCO SERVICES, LLC | 3.50% | $21,706.53 |
| DIAMOND ELITE BARRICADES, LLC | 1.37% | $8,496.55 |
| Total: | 8.58% | $53,212.00 |
Bid Items & Bid Tabulations
32
Total
0 of 32
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $10,000.00 |