Show Job Controls
Bid Cobra

GREGG VA (0910-07-085)

Items: 9

County: GREGG
Length: N/A
Highway: VA
District: TYLER
Control Number: 0910-07-085
DBE Goal: 0.0%
Project: STP 2024(983)HESG
Guaranty: N/A
Time: 27 WORKING DAYS
Engineer's Estimate: $359,075.00
Date: 05/02/2024 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$359,075.00
$240,950.00
Over/Under Est: -32.9% -$118,125.00
$324,733.20
Over/Under Est: -9.56% -$34,341.80
Amt Left: 34.77% $83,783.20
Over/Under Est: 7.04% $25,275.00
Amt Left: 59.51% $143,400.00
Delta: -18.36% -$59,616.80
Over/Under Est: 8.56% $30,725.00
Amt Left: 61.78% $148,850.00
Delta: -1.42% -$5,450.00
Over/Under Est: 9.87% $35,425.00
Amt Left: 63.73% $153,550.00
Delta: -1.21% -$4,700.00
Over/Under Est: 10.19% $36,575.00
Amt Left: 64.2% $154,700.00
Delta: -0.29% -$1,150.00
Over/Under Est: 12.59% $45,216.00
Amt Left: 67.79% $163,341.00
Delta: -2.18% -$8,641.00
Over/Under Est: 23.98% $86,095.00
Amt Left: 84.76% $204,220.00
Delta: -10.11% -$40,879.00
Subcontractor Percentage Amount
J-W TREE SERVICE 6.23% $15,011.19
HDZ CONSTRUCTION 2.08% $5,011.76
Total: 8.31% $20,022.95

Bid Items & Bid Tabulations

9 Total 0 of 9
GREGG  |  VA  |  TYLER  |  0910-07-085  |  05/02/2024  |  $359,075.00  |  STP 2024(983)HESG  |  HAZARD ELIM & SAFETY  |  27 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SYNERGY SIGNS & SERVICES LLC
H. V. CAVER, INC.
VACA UNDERGROUND UTILITIES INC
MARCOM'S MOWING SERVICE, LLC
GARRET SHIELDS INFRASTRUCTURE
MB WESTERN INDUSTRIAL CONTRACTING CO.
RISE UP CONSTRUCTION LLC
WG ENGINEERING & CONSTRUCTION, LLC
PREPARING ROW
STA 19.000 $4,300.000 $1,000.000 $2,000.000 $4,500.000 $6,300.000 $8,000.000 $5,000.000 $3,699.000 $2,725.000
MOBILIZATION
LS 1.000 $32,640.000 $10,000.000 $20,000.000 $65,000.000 $5,000.000 $20,000.000 $20,000.000 $34,000.000 $50,275.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $6,000.000 $10,000.000 $10,000.000 $3,500.000 $2,300.000 $4,000.000 $1,500.000 $3,500.000 $6,285.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 40.000 $625.000 $475.000 $726.080 $650.000 $450.000 $600.000 $900.000 $750.000 $852.000
REMOVE SM RD SN SUP&AM
EA 5.000 $115.000 $150.000 $150.000 $250.000 $100.000 $100.000 $150.000 $122.000 $250.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $190.000 $150.000 $175.000 $100.000 $200.000 $100.000 $75.000 $50.000 $350.000
TMA (STATIONARY)
DAY 24.000 $200.000 $150.000 $250.000 $200.000 $300.000 $300.000 $200.000 $2,300.000 $305.000
LEAD LED CHEVRON
EA 12.000 $3,670.000 $2,700.000 $3,295.000 $3,500.000 $4,100.000 $2,500.000 $4,500.000 $3,400.000 $6,250.000
LED CHEVRON
EA 60.000 $2,550.000 $2,200.000 $2,775.000 $2,500.000 $3,000.000 $2,500.000 $3,000.000 $2,750.000 $3,385.000
Totals: $359,075.000 $240,950.000 $324,733.200 $384,350.000 $389,800.000 $394,500.000 $395,650.000 $404,291.000 $445,170.000