Show Job Controls
Bid Cobra

GREGG CS (0910-07-072)

Items: 147

County: GREGG
Length: N/A
Highway: CS
District: TYLER
Control Number: 0910-07-072
DBE Goal: N/A
Project: BR 2018(505)
Guaranty: N/A
Time: 357 WORKING DAYS
Engineer's Estimate: $7,726,862.00
Date: 03/03/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$7,726,862.00
$9,313,027.96
Over/Under Est: 20.53% $1,586,165.96
Over/Under Est: 21.57% $1,666,671.26
Amt Left: 0.86% $80,505.30
Over/Under Est: 26.64% $2,058,236.74
Amt Left: 5.07% $472,070.78
Delta: -4.17% -$391,565.48
Over/Under Est: 37.77% $2,918,205.09
Amt Left: 14.3% $1,332,039.13
Delta: -8.79% -$859,968.35
Subcontractor Percentage Amount
FARR FOUNDATION, INC. 14.54% $1,401,409.33
HODGES AND SON CONSTRUCTION COMPANY, INC. 2.95% $284,329.95
PEACHTREE CONSTRUCTION, LTD. 2.55% $245,776.74
SNOWHILL CONTRACTING LLC 1.53% $147,466.04
G & L REBAR 1.21% $116,623.47
STRIPE-A-ZONE, LLC 0.41% $39,517.04
J. H. ODEN CONTRACTING COMPANY 0.39% $37,589.38
FLEX SUPPLY, LLC 0.32% $30,842.57
ACT SAW CUTTING & REMOVAL 0.31% $29,878.74
ODUM SERVICES, LLC 0.30% $28,914.91
SOUTHERN LIFTING AND HOISTING, LLC 0.28% $26,987.25
S&S BRIDGE PAINTING 0.20% $19,276.61
JOYCE STEEL ERECTION, LLC 0.14% $13,493.62
TORO BRAVO CONSTRUCTION, LLC 0.14% $13,493.62
TEX OP CONSTRUCTION, LP 0.14% $13,493.62
PENHALL COMPANY 0.13% $12,529.79
CAP RIVER LLC 0.13% $12,529.79
SACE SERVICES, LLC 0.11% $10,602.13
TRENDSETTER CONSTRUCTION, INC. 0.08% $7,710.64
HIGHWAY PAVEMENT SPECIALTIES, INC. 0.05% $4,819.15
A-CORE CONCRETE CUTTING OF TEXAS, INC. 0.05% $4,819.15
Total: 25.96% $2,502,103.54

Bid Items & Bid Tabulations

147 Total 0 of 147
GREGG  |  CS  |  TYLER  |  0910-07-072  |  03/03/2022  |  $7,726,862.00  |  BR 2018(505)  |  BRIDGE REPL  |  357 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
EAST TEXAS BRIDGE, INC.
L. S. EQUIPMENT CO., INC.
LONGVIEW BRIDGE AND ROAD, LTD.
PREPARING ROW
STA 14.000 $3,500.000 $63,400.000 $3,200.000 $3,000.000 $3,240.000
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 2.000 $850.000 $2,500.000 $600.000 $700.000 $1,350.000
PREP ROW (TREE)(GREATER THAN 24" DIA)
EA 1.000 $1,500.000 $4,500.000 $1,500.000 $1,500.000 $2,700.000
REMOVING CONC (SIDEWALKS)
SY 1,053.000 $12.500 $10.500 $12.000 $20.000 $12.800
REMOVING CONC (CURB)
LF 52.000 $8.000 $8.500 $8.000 $15.000 $26.000
REMOVING CONC (CURB AND GUTTER)
LF 2,080.000 $5.000 $5.500 $8.000 $5.000 $17.000
REMOV STAB BASE & ASPH PAV (8"-20")
SY 6,060.000 $3.500 $6.500 $10.000 $6.000 $11.150
EXCAVATION (ROADWAY)
CY 13,646.000 $5.500 $15.000 $12.000 $15.000 $11.000
EXCAVATION (SPECIAL)
CY 1,217.000 $35.000 $20.000 $15.000 $30.000 $41.300
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 7,210.000 $15.000 $8.000 $16.000 $20.000 $20.000
FURNISHING AND PLACING TOPSOIL (4")
SY 11,868.000 $2.000 $1.100 $2.150 $2.000 $3.500
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 5,934.000 $0.500 $0.260 $0.300 $0.400 $0.400
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 5,934.000 $0.850 $1.000 $0.900 $0.750 $0.790
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 2,967.000 $0.700 $0.750 $0.850 $0.750 $0.790
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 2,967.000 $0.700 $0.730 $0.800 $0.750 $0.790
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 5,934.000 $0.250 $0.270 $0.300 $0.500 $0.400
VEGETATIVE WATERING
MG 131.000 $10.000 $25.000 $10.000 $1.000 $30.000
LIME (HYDRATED LIME (DRY))
TON 41.000 $225.000 $199.000 $240.000 $300.000 $273.000
LIME TRT (SUBGRADE)(6")
SY 2,986.000 $5.000 $6.000 $4.000 $5.000 $3.100
CEMENT
TON 41.000 $200.000 $175.000 $210.000 $200.000 $243.500
CEMENT TREAT (SUBGRADE)(6")
SY 2,986.000 $10.500 $4.000 $4.000 $5.000 $2.500
PRIME COAT & BLOTTER (MC-30)
GAL 896.000 $8.000 $10.000 $5.000 $6.000 $6.300
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 1,254.000 $6.000 $6.000 $6.000 $5.000 $5.250
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 30.000 $200.000 $406.000 $300.000 $300.000 $270.000
PLANE ASPH CONC PAV(0" TO 12")
SY 158.000 $25.000 $13.000 $25.000 $30.000 $26.400
CONC PVMT (CONT REINF - CRCP) (9")
SY 5,743.000 $90.000 $75.000 $100.000 $100.000 $85.000
CEM STABIL BKFL
CY 350.200 $150.000 $55.000 $200.000 $90.000 $200.000
FLOWABLE BACKFILL
CY 69.000 $225.000 $220.000 $275.000 $200.000 $275.000
TEMPORARY SPL SHORING
SF 1,428.000 $35.000 $25.000 $35.000 $22.000 $75.000
SOIL NAIL ANCHORS
LF 79,725.000 $14.000 $13.980 $18.000 $14.000 $21.000
DRILL SHAFT (42 IN)
LF 1,324.000 $225.000 $175.000 $300.000 $410.000 $336.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 28.000 $225.000 $278.000 $205.000 $325.000 $244.000
CL C CONC (ABUT)
CY 88.900 $900.000 $900.000 $1,050.000 $1,300.000 $1,225.000
CL C CONC (CAP)
CY 103.000 $1,000.000 $1,100.000 $1,050.000 $1,500.000 $1,135.000
CL C CONC (COLUMN)
CY 98.400 $1,000.000 $1,050.000 $1,050.000 $1,500.000 $1,240.000
CL C CONC (RAIL FOUNDATION)
CY 24.000 $450.000 $500.000 $730.000 $1,000.000 $990.000
CL C CONC (MISC)
CY 12.000 $1,000.000 $1,000.000 $800.000 $1,000.000 $965.000
REINF CONC SLAB
SF 24,259.000 $18.000 $19.000 $27.000 $24.000 $24.500
APPROACH SLAB
CY 125.900 $600.000 $550.000 $630.000 $800.000 $750.000
RETAINING WALL (MSE)
SF 8,243.000 $75.000 $65.000 $75.000 $45.000 $90.000
RETAINING WALL (TEMP WALL)
SF 1,420.000 $35.000 $16.000 $38.000 $20.000 $20.000
RETAINING WALL (SOIL NAIL)(FACIA)
SF 21,125.000 $45.000 $32.000 $55.000 $65.000 $68.000
PRESTR CONC GIRDER (TX62)
LF 3,659.320 $150.000 $205.000 $245.000 $197.000 $270.000
RIPRAP (CONC)(4 IN)
CY 11.000 $775.000 $530.000 $650.000 $600.000 $731.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 95.000 $420.000 $480.000 $650.000 $500.000 $544.000
RIPRAP (CONC) (CL B) (4")
CY 0.700 $500.000 $800.000 $1,200.000 $625.000 $2,040.000
RIPRAP (MOW STRIP)(4 IN)
CY 79.000 $500.000 $470.000 $550.000 $575.000 $600.000
STR STEEL (MISC NON - BRIDGE)
LB 340.000 $8.500 $18.000 $30.000 $15.000 $31.000
RAIL (TY T551)
LF 622.000 $60.000 $67.000 $110.000 $49.000 $63.000
RAIL (TY C221)
LF 2,104.000 $72.000 $83.000 $125.000 $192.000 $85.000
RAIL (HANDRAIL)(TY E)
LF 101.000 $115.000 $125.000 $150.000 $250.000 $205.000
RAIL (CLF-RO)
LF 432.000 $110.000 $75.000 $150.000 $125.000 $155.000
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
LF 158.000 $100.000 $115.000 $120.000 $125.000 $150.000
RC PIPE (CL III)(18 IN)
LF 193.000 $60.000 $60.000 $52.000 $73.000 $70.000
INLET (COMPL)(CCO)(3FT)(BOTH)
EA 4.000 $5,000.000 $4,500.000 $8,000.000 $927.000 $6,820.000
ADJUSTING INLETS
EA 2.000 $2,500.000 $1,350.000 $2,500.000 $2,500.000 $4,420.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $100,000.000 $1,000,000.000 $200,000.000 $275,000.000 $260,000.000
REMOVE STR (JUNCTION BOX)
EA 1.000 $850.000 $1,150.000 $1,000.000 $1,000.000 $2,100.000
MOBILIZATION
LS 1.000 $699,942.000 $890,000.000 $700,000.000 $800,000.000 $950,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 23.000 $8,500.000 $5,000.000 $4,000.000 $4,000.000 $3,200.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 80.000 $35.000 $27.680 $33.000 $35.000 $39.600
ROCK FILTER DAMS (REMOVE)
LF 80.000 $10.000 $10.000 $9.000 $10.000 $10.560
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 565.000 $25.000 $30.000 $30.000 $25.000 $35.640
CONSTRUCTION EXITS (REMOVE)
SY 565.000 $10.000 $10.000 $9.000 $10.000 $13.200
EXCAV (EROSN & SEDMT CONT, IN PLACE)
CY 250.000 $4.500 $10.000 $30.000 $35.000 $67.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 80.000 $75.000 $60.000 $85.000 $150.000 $210.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,084.000 $2.650 $2.850 $3.150 $3.000 $3.760
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,084.000 $0.700 $0.750 $1.000 $1.000 $1.120
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 98.000 $8.000 $6.000 $4.500 $6.000 $5.280
BIODEG EROSN CONT LOGS (REMOVE)
LF 98.000 $2.000 $1.000 $2.500 $2.000 $2.640
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 80.000 $100.000 $80.000 $100.000 $150.000 $210.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 80.000 $75.000 $75.000 $80.000 $60.000 $112.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 510.000 $15.000 $12.000 $20.000 $20.000 $20.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 1,280.000 $14.500 $12.000 $20.000 $12.000 $16.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 360.000 $10.000 $7.000 $15.000 $8.000 $12.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 520.000 $6.500 $7.000 $10.000 $8.000 $11.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 80.000 $10.000 $7.000 $15.000 $15.000 $20.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 510.000 $11.000 $10.000 $10.000 $15.000 $16.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 1,280.000 $13.500 $10.000 $10.000 $8.000 $14.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 80.000 $45.000 $10.000 $10.000 $12.000 $14.000
PCTB(FUR & INST)(F-SHP TO LOW PROF)TY T
LF 20.000 $250.000 $90.000 $175.000 $400.000 $210.000
PORT CTB(MOVE)(F-SHAPE)(TY T)
LF 20.000 $15.000 $15.000 $15.000 $10.000 $30.000
PORT CTB(REMOVE)(F-SHAPE)(TY T)
LF 20.000 $25.000 $15.000 $10.000 $100.000 $30.000
CONC CURB (TY II)
LF 1,878.000 $20.000 $10.000 $16.000 $40.000 $10.500
CONC CURB & GUTTER (TY II)
LF 196.000 $40.000 $27.500 $34.000 $25.000 $86.000
CONC SIDEWALKS (4")
SY 1,311.000 $55.000 $48.000 $70.000 $70.000 $50.000
CURB RAMPS (TY 2)
EA 2.000 $2,500.000 $1,600.000 $2,000.000 $500.000 $3,820.000
CURB RAMPS (TY 5)
EA 1.000 $3,400.000 $1,550.000 $2,500.000 $3,000.000 $3,900.000
MTL W-BEAM GD FEN (STEEL POST)
LF 225.000 $27.500 $33.500 $36.000 $45.000 $42.900
MTL BEAM GD FEN TRANS (TL2)
EA 2.000 $1,350.000 $1,525.000 $1,500.000 $1,600.000 $1,782.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,300.000 $1,600.000 $1,500.000 $1,750.000 $1,848.000
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $750.000 $950.000 $1,100.000 $1,250.000 $1,320.000
REMOVE METAL BEAM GUARD FENCE
LF 2,122.000 $2.500 $3.000 $2.500 $5.000 $2.970
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $200.000 $150.000 $220.000 $250.000 $264.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,600.000 $3,140.000 $3,450.000 $3,500.000 $4,125.000
PIPE UNDERDRAINS (TY 8) (6")
LF 525.000 $45.000 $10.000 $45.000 $45.000 $20.000
IN RD IL (TY SA) 50B-12 (400W EQ) LED
EA 3.000 $3,600.000 $4,858.000 $8,300.000 $5,692.000 $9,966.000
IN RD IL (TY SA) 50T-12 (400W EQ) LED
EA 2.000 $3,500.000 $5,240.000 $6,700.000 $6,100.000 $7,986.000
CONDT (PVC) (SCH 40) (2")
LF 563.000 $9.500 $14.500 $10.000 $16.500 $11.880
CONDT (PVC) (SCH 80) (2") (BORE)
LF 157.000 $45.000 $26.000 $34.000 $30.000 $40.920
CONDT (RM) (2")
LF 984.000 $30.000 $57.240 $38.500 $65.000 $46.200
ELEC CONDR (NO.8) BARE
LF 1,779.000 $1.850 $2.000 $2.000 $4.000 $2.310
ELEC CONDR (NO.8) INSULATED
LF 3,558.000 $1.850 $2.000 $2.000 $4.000 $2.310
GROUND BOX TY A (122311)W/APRON
EA 4.000 $700.000 $980.000 $1,045.000 $1,200.000 $1,254.000
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 2.000 $6,000.000 $6,959.000 $7,100.000 $8,200.000 $8,553.000
REMOVE SM RD SN SUP&AM
EA 4.000 $150.000 $145.880 $100.000 $500.000 $132.000
IN SRSS & AM (RAIL)(90 MPH)(T MOUNT)
EA 3.000 $2,600.000 $5,473.700 $1,500.000 $7,500.000 $4,620.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 82.000 $75.000 $71.080 $50.000 $125.000 $59.400
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 4.000 $110.000 $75.590 $50.000 $100.000 $59.400
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 61.000 $6.000 $8.000 $4.400 $5.000 $5.280
WK ZN PAV MRK REMOV (REFL) TY I-A
EA 205.000 $3.750 $3.750 $5.500 $6.000 $6.600
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 1,384.000 $4.250 $3.750 $5.500 $6.000 $6.600
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 463.000 $5.000 $3.750 $5.500 $6.000 $6.600
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 1,518.000 $3.500 $3.250 $3.300 $4.000 $3.960
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 1,987.000 $3.500 $3.250 $3.300 $3.500 $3.960
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 550.000 $1.000 $1.000 $1.100 $1.000 $1.320
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 249.000 $6.500 $6.000 $6.500 $6.000 $7.920
REFL PAV MRK TY II (W) 4" (BRK)
LF 1,121.000 $0.200 $0.170 $1.100 $1.000 $1.320
REFL PAV MRK TY II (W) 8" (SLD)
LF 550.000 $1.000 $0.200 $1.100 $1.000 $1.320
REFL PAV MRK TY II (W) 24" (SLD)
LF 249.000 $3.000 $2.000 $3.300 $3.000 $3.960
REFL PAV MRK TY II (Y) 4" (SLD)
LF 5,848.000 $0.750 $0.170 $1.100 $1.250 $1.320
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,121.000 $0.600 $0.500 $1.100 $1.250 $1.320
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 5,848.000 $1.500 $0.500 $1.100 $1.250 $1.320
PREFAB PAV MRK TY C (W) (ARROW)
EA 6.000 $250.000 $2.200 $220.000 $200.000 $264.000
PREFAB PAV MRK TY C (W) (WORD)
EA 5.000 $350.000 $225.000 $275.000 $300.000 $330.000
PREFAB PAV MRK TY C (Y) (4") (SLD)
LF 243.000 $1.500 $3.500 $3.750 $4.000 $4.620
REFL PAV MRKR TY I-C
EA 86.000 $4.000 $4.500 $4.400 $4.000 $5.280
REFL PAV MRKR TY II-A-A
EA 306.000 $3.750 $4.500 $4.400 $4.000 $5.280
ELIM EXT PAV MRK & MRKS (4")
LF 5,983.000 $0.750 $1.000 $0.650 $0.750 $0.790
ELIM EXT PAV MRK & MRKS (8")
LF 376.000 $3.000 $2.000 $1.100 $1.000 $1.320
ELIM EXT PAV MRK & MRKS (12")
LF 281.000 $2.500 $2.000 $2.200 $3.000 $2.640
ELIM EXT PAV MRK & MRKS (24")
LF 107.000 $6.500 $3.000 $3.300 $3.000 $3.960
ELIM EXT PAV MRK & MRKS (ARROW)
EA 6.000 $100.000 $30.000 $85.000 $85.000 $99.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 4.000 $100.000 $40.000 $85.000 $85.000 $99.000
PAV SURF PREP FOR MRK (4")
LF 1,121.000 $0.200 $0.100 $0.110 $0.100 $0.130
PAV SURF PREP FOR MRK (8")
LF 550.000 $0.250 $0.200 $0.350 $0.300 $0.400
PAV SURF PREP FOR MRK (24")
LF 249.000 $0.750 $1.000 $1.100 $1.000 $0.320
PAV SURF PREP FOR MRK (ARROW)
EA 6.000 $50.000 $10.000 $55.000 $60.000 $66.000
PAV SURF PREP FOR MRK (WORD)
EA 5.000 $50.000 $10.000 $55.000 $60.000 $66.000
REMOVAL OF TIMBER POLES
EA 1.000 $350.000 $625.000 $600.000 $500.000 $660.000
ANTI - GRAFFITI COATING(PERMNENT-TY II)
SF 29,368.000 $0.650 $0.650 $1.750 $1.500 $1.820
SP MIXES SP-C PG70-22
TON 1,375.000 $145.000 $150.000 $140.000 $200.000 $136.000
TACK COAT
GAL 604.000 $6.000 $3.100 $4.000 $5.000 $5.600
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $15,000.000 $18,500.000 $8,889.000 $19,000.000
JUNCTION BOX (INSTALL)
EA 6.000 $450.000 $1,200.000 $550.000 $2,000.000 $660.000
TMA (STATIONARY)
DAY 722.000 $175.000 $185.000 $100.000 $546.000 $330.000
TMA (MOBILE OPERATION)
DAY 68.000 $150.000 $185.000 $100.000 $173.000 $330.000
Totals: $7,726,862.000 $9,313,027.960 $9,393,533.260 $9,785,098.740 $10,645,067.090