GRAYSON FM0084 (6318-62-001)

Items: 21

County: GRAYSON
Length: N/A
Highway: FM0084
District: PARIS
Control Number: 6318-62-001
DBE Goal: N/A
Project: BPM - 631862001
Guaranty: N/A
Time: 75 W
Engineer's Estimate: $520,487.50
Date: 04/03/2018 (8 years ago)
Contract Number: N/A
Type: EROSION REPAIR-INSTALL SOIL NAIL RETAINING WALL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$520,487.50
$629,000.00
Over/Under Est: 20.85% $108,512.50
Over/Under Est: 32.28% $168,014.50
Amt Left: 9.46% $59,502.00
Over/Under Est: 33.14% $172,506.00
Amt Left: 10.17% $63,993.50
Delta: -0.65% -$4,491.50
Over/Under Est: 41.67% $216,887.50
Amt Left: 17.23% $108,375.00
Delta: -6.40% -$44,381.50
Over/Under Est: 74.44% $387,465.50
Amt Left: 44.35% $278,953.00
Delta: -23.13% -$170,578.00

Bid Items & Bid Tabulations

21 Total 0 of 21
GRAYSON  |  FM0084  |  PARIS  |  6318-62-001  |  04/03/2018  |  $520,487.50  |  BPM - 631862001  |  EROSION REPAIR-INSTL SOIL NAIL RETAI...  |  75 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
ED BELL CONSTRUCTION COMPANY
GHB EQUIPMENT COMPANY, L.L.C.
WEST TEXAS REBAR PLACERS INC.
FNH CONSTRUCTION, LLC
IOWA BRIDGE & CULVERT, LC
REMOVING CONC (RIPRAP)
SY 1,027.000 $25.000 $11.550 $30.000 $20.000 $20.000 $100.000
EXCAVATION (ROADWAY)
CY 1,900.000 $20.000 $21.000 $20.000 $20.000 $20.000 $50.000
BLOCK SODDING
SY 1,350.000 $5.000 $6.300 $4.000 $5.000 $5.500 $6.000
FLOWABLE BACKFILL
CY 60.000 $200.000 $420.000 $350.000 $200.000 $350.000 $280.000
SOIL NAIL ANCHORS
LF 7,936.000 $20.000 $21.000 $37.000 $41.000 $30.000 $18.000
RETAINING WALL (SOIL NAIL)(FACIA)
SF 2,965.000 $45.000 $63.000 $50.000 $52.500 $70.000 $85.000
RIPRAP (CONC)(4 IN)
CY 43.000 $550.000 $525.000 $350.000 $500.000 $550.000 $1,200.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 50.000 $100.000 $157.500 $160.000 $150.000 $185.000 $300.000
RIPRAP (MOW STRIP)(4 IN)
CY 38.200 $650.000 $525.000 $350.000 $500.000 $550.000 $500.000
MOBILIZATION
LS 1.000 $45,000.000 $51,522.220 $68,000.000 $40,000.000 $70,000.000 $90,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,000.000 $11,550.000 $2,000.000 $2,500.000 $8,500.000 $5,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 345.000 $5.000 $1.860 $7.000 $4.000 $4.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 345.000 $2.500 $0.270 $1.000 $1.000 $2.000 $2.000
MTL W-BEAM GD FEN (STEEL POST)
LF 300.000 $25.000 $23.960 $23.000 $23.000 $30.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,911.460 $2,000.000 $2,000.000 $1,850.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 400.000 $2.500 $2.660 $5.000 $2.000 $3.000 $20.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $250.000 $197.030 $500.000 $250.000 $500.000 $360.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,750.000 $2,369.630 $3,000.000 $2,800.000 $2,550.000 $2,600.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $35.000 $25.560 $30.000 $50.000 $100.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $35.000 $25.560 $35.000 $40.000 $100.000 $30.000
TMA (STATIONARY)
DAY 10.000 $300.000 $315.000 $300.000 $400.000 $550.000 $5,000.000
Totals: $520,487.500 $629,000.000 $688,502.000 $692,993.500 $737,375.000 $907,953.000