Show Job Controls
Bid Cobra

GRAYSON VARIOUS (0901-19-229)

Items: 68

County: GRAYSON
Length: 0.0000 MILES
Highway: VARIOUS
District: PARIS
Control Number: 0901-19-229
DBE Goal: 0.0%
Project: STP 2025(695)TAPS
Guaranty: $59,000.00
Time: 90 WORKING DAYS
Engineer's Estimate: $2,967,038.96
Date: 03/05/2026 (3 months ago)
Contract Number: 3263204
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00207303
Contract Type: Federal
Project Description: CONSTRUCT SUP ALONG ABANDONED UNION PACIFIC RAILWAY CORRIDOR TO BEGIN AT LOY LAKE RD, CONTI. S UNDER SPUR 503, TERMINATING AT E BOUND SERVICE ROAD OF SPUR 503, INCLUDES A PED BRIDGE, PEDESTRIAN SIGNALS, LIGHTING, SIGNAGE, OTHER BICYCLE&PED AMENITIES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYAN ESMAILIDOKI
MELESE NORCHA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (11)
E
Engineer's Estimate
$2,967,038.96
$2,744,601.85
Over/Under Est: -7.5% -$222,437.11
$2,763,803.70
Over/Under Est: -6.85% -$203,235.26
Amt Left: 0.7% $19,201.85
Over/Under Est: -4.72% -$140,028.16
Amt Left: 3% $82,408.95
Delta: -2.29% -$63,207.10
Over/Under Est: -3.01% -$89,366.86
Amt Left: 4.85% $133,070.25
Delta: -1.79% -$50,661.30
$2,896,711.82
Over/Under Est: -2.37% -$70,327.14
Amt Left: 5.54% $152,109.97
Delta: -0.66% -$19,039.72
Over/Under Est: -0.05% -$1,457.76
Amt Left: 8.05% $220,979.35
Delta: -2.38% -$68,869.38
Over/Under Est: 3.94% $116,987.47
Amt Left: 12.37% $339,424.58
Delta: -3.99% -$118,445.23
$3,159,689.90
Over/Under Est: 6.49% $192,650.94
Amt Left: 15.12% $415,088.05
Delta: -2.45% -$75,663.47
Over/Under Est: 7.87% $233,515.80
Amt Left: 16.61% $455,952.91
Delta: -1.29% -$40,864.86
Over/Under Est: 44.4% $1,317,496.64
Amt Left: 56.11% $1,539,933.75
Delta: -33.87% -$1,083,980.84
Over/Under Est: 85.33% $2,531,688.50
Amt Left: 100.35% $2,754,125.61
Delta: -28.34% -$1,214,191.86

Bid Items & Bid Tabulations

68 Total 0 of 68
GRAYSON  |  VARIOUS  |  PARIS  |  0901-19-229  |  03/05/2026  |  $2,967,038.96  |  STP 2025(695)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCOUT 5 CONSTRUCTION LLC
STX CIVIL
TEXAS STEEL INDUSTRIAL PLACING, LLC
GARRET SHIELDS INFRASTRUCTURE
SKYLINE BRIDGE LLC
HIGHWAY 19 CONSTRUCTION LLC
PACE CONSTRUCTION SERVICES LLC
TALBERT COMPANIES LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
ED BELL CONSTRUCTION COMPANY
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
PREPARING ROW
STA 67.200 $1,000.000 $5,000.000 $350.000 $1,000.000 $600.000 $500.000 $2,500.000 $1,000.000 $2,501.550 $3,500.000 $4,800.000 $1,200.000
REMOV CONC (PAV)
SY 105.000 $40.000 $50.000 $10.000 $40.000 $40.000 $75.000 $35.000 $140.000 $27.250 $25.000 $42.000 $20.000
EXCAV (ROADWAY)
CY 2,870.000 $18.600 $33.000 $20.000 $21.000 $25.000 $18.000 $10.000 $20.000 $26.618 $20.000 $48.000 $25.000
EMBANK (FNL)(OC)(TY A)
CY 2,890.000 $20.000 $33.000 $40.000 $30.000 $35.000 $32.000 $15.000 $18.000 $40.330 $25.000 $30.000 $40.000
BLOCK SODDING
SY 14,467.000 $5.070 $6.000 $4.750 $4.000 $7.000 $6.310 $4.000 $4.650 $5.069 $4.500 $5.760 $6.500
FERTILIZER
AC 3.000 $565.130 $313.000 $500.000 $800.000 $400.000 $275.000 $850.000 $800.000 $245.250 $1,000.000 $759.360 $1,000.000
VEGETATIVE WATERING
TGL 505.000 $22.380 $11.500 $50.000 $25.000 $20.000 $1.000 $30.000 $20.000 $63.220 $1.000 $10.500 $250.000
RDSIDE AMENITY (TRASH/RECYCLE BIN)
EA 3.000 $750.000 $1,000.000 $900.000 $769.000 $1,000.000 $985.000 $1,500.000 $3,000.000 $817.500 $1,000.000 $807.450 $3,000.000
RDSIDE AMENITY (BENCH)
EA 1.000 $2,000.000 $2,500.000 $2,200.000 $1,955.000 $1,000.000 $2,350.000 $2,500.000 $3,000.000 $2,398.000 $3,000.000 $2,052.750 $5,000.000
LIME (COM OR QK)(SLURRY)
TON 132.000 $300.000 $401.000 $500.000 $320.000 $350.000 $375.000 $350.000 $400.000 $383.320 $350.000 $300.000 $450.000
LIME TRT (EXIST MATL & NEW BASE)(6")
SY 10,562.000 $10.000 $3.250 $8.000 $10.000 $8.000 $7.750 $7.000 $5.000 $5.668 $8.500 $1.500 $30.000
STRUCT EXCAV (PIPE)
CY 337.000 $4.520 $2.000 $20.000 $20.000 $20.000 $30.000 $30.000 $57.000 $16.350 $18.000 $14.020 $15.000
CEM STABIL BKFL
CY 36.000 $222.900 $200.000 $250.000 $250.000 $200.000 $300.000 $250.000 $485.000 $272.500 $250.000 $541.330 $750.000
DRILL SHAFT (36 IN)
LF 236.000 $296.600 $400.000 $380.000 $385.460 $350.000 $282.920 $350.000 $400.000 $335.720 $280.000 $375.000 $600.000
CL C CONC (ABUT)
CY 36.400 $1,145.600 $465.000 $1,300.000 $1,400.000 $1,000.000 $1,002.900 $1,600.000 $485.000 $1,090.000 $2,500.000 $2,500.000 $600.000
REINF CONC SLAB
SF 2,002.000 $30.000 $26.000 $26.000 $40.000 $30.000 $242.160 $33.000 $55.000 $29.070 $30.000 $40.000 $130.000
APPROACH SLAB
CY 8.400 $922.000 $454.000 $900.000 $750.000 $1,200.000 $1,315.030 $1,000.000 $1,300.000 $872.000 $1,800.000 $2,500.000 $550.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 18.000 $243.060 $160.000 $180.000 $200.000 $200.000 $150.000 $180.000 $450.000 $168.950 $250.000 $263.700 $250.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 126.000 $188.710 $160.000 $200.000 $200.000 $200.000 $125.000 $180.000 $150.000 $245.250 $250.000 $273.330 $250.000
ELASTOMERIC BEARING (LAMINATED)
EA 4.000 $1,690.240 $4,650.000 $4,500.000 $6,400.000 $4,000.000 $1,500.000 $5,000.000 $5,000.000 $8,835.714 $16,000.000 $7,500.000 $5,000.000
STR STEEL (MISCELLANEOUS BRIDGE)
LB 402.000 $15.900 $18.500 $16.000 $14.150 $16.000 $12.000 $35.000 $60.000 $16.350 $20.000 $24.240 $150.000
CLEAN & PAINT EXIST STR (SYSTEM II)
LS 1.000 $215,400.000 $352,000.000 $280,000.000 $247,350.000 $275,000.000 $278,268.750 $250,000.000 $330,000.000 $269,611.500 $270,000.000 $275,000.000 $350,000.000
RAIL (TY PR11)
LF 240.000 $119.400 $115.000 $155.000 $144.240 $150.000 $172.650 $180.000 $180.000 $147.150 $150.000 $151.450 $275.000
RAIL (HANDRAIL)(TY F)
LF 1,926.000 $170.000 $135.000 $155.000 $144.240 $120.000 $167.840 $180.000 $150.000 $147.150 $210.000 $151.450 $275.000
RC PIPE (CL III)(12 IN)
LF 198.000 $55.100 $37.000 $80.000 $75.000 $80.000 $47.500 $44.000 $88.000 $59.950 $60.000 $95.650 $125.000
RC PIPE (CL III)(18 IN)
LF 190.000 $57.610 $39.000 $90.000 $80.000 $80.000 $54.500 $55.000 $100.000 $67.580 $80.000 $102.360 $135.000
RC PIPE (CL III)(24 IN)
LF 34.000 $92.600 $46.000 $110.000 $100.000 $150.000 $77.500 $73.000 $350.000 $152.600 $120.000 $149.120 $150.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 6.000 $7,250.000 $3,042.000 $6,000.000 $6,000.000 $6,000.000 $5,500.000 $6,500.000 $10,000.000 $5,450.000 $7,000.000 $11,224.600 $7,000.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 1.000 $10,075.250 $4,374.500 $7,500.000 $7,000.000 $8,000.000 $6,800.000 $7,500.000 $13,000.000 $7,085.000 $8,500.000 $12,639.570 $8,000.000
SET (TY II) (12 IN) (RCP) (3: 1) (C)
EA 3.000 $1,880.300 $546.000 $800.000 $1,000.000 $1,000.000 $675.000 $585.000 $1,500.000 $872.000 $1,200.000 $610.310 $2,000.000
SET (TY II) (12 IN) (RCP) (6: 1) (C)
EA 2.000 $1,880.300 $546.000 $1,000.000 $1,200.000 $1,000.000 $675.000 $585.000 $1,800.000 $926.500 $2,000.000 $610.320 $2,000.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 3.000 $800.000 $547.000 $1,000.000 $1,000.000 $1,000.000 $675.000 $585.000 $1,800.000 $981.000 $1,500.000 $610.310 $2,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 2.000 $800.000 $850.000 $1,200.000 $1,500.000 $1,500.000 $775.000 $795.000 $2,000.000 $1,035.500 $2,200.000 $762.900 $2,100.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 1.000 $1,500.000 $720.000 $1,300.000 $1,500.000 $1,500.000 $1,105.000 $905.000 $3,000.000 $2,180.000 $2,500.000 $915.480 $2,300.000
TREAT TIMBER
MBF 10.000 $4,095.000 $3,500.000 $500.000 $5,000.000 $3,500.000 $3,650.540 $10,000.000 $1,000.000 $1,090.000 $10,000.000 $18,375.000 $15,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $12,000.000 $15,000.000 $30,000.000 $90,000.000 $25,000.000 $50,000.000 $100,000.000 $21,800.000 $50,000.000 $25,099.000 $35,000.000
MOBILIZATION
LS 1.000 $257,003.990 $300,000.000 $216,000.000 $277,857.620 $200,000.000 $225,000.000 $290,000.000 $250,000.000 $317,510.460 $270,000.000 $400,000.000 $550,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $2,000.000 $1,200.000 $1,800.000 $2,775.000 $4,000.000 $2,400.000 $2,000.000 $2,000.000 $5,450.000 $5,500.000 $7,350.000 $4,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 13,270.000 $4.690 $7.000 $4.000 $3.700 $4.000 $3.700 $4.000 $4.500 $3.815 $4.000 $2.890 $6.000
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 70.000 $1.870 $7.000 $4.000 $6.000 $5.000 $10.000 $10.000 $8.000 $8.720 $10.000 $13.390 $15.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 13,270.000 $1.440 $4.000 $0.100 $1.000 $1.000 $1.000 $1.000 $1.000 $1.090 $1.000 $2.100 $2.000
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 175.000 $2.130 $2.500 $5.000 $4.000 $5.000 $8.000 $5.000 $8.000 $5.178 $5.000 $18.900 $15.000
CONC SIDEWALKS (6")
SY 8,977.000 $108.000 $44.000 $90.000 $75.000 $80.000 $54.410 $87.000 $75.000 $106.820 $80.000 $118.950 $135.000
CURB RAMPS (TY 1)
EA 6.000 $2,386.010 $752.500 $1,200.000 $2,500.000 $2,500.000 $2,000.000 $1,500.000 $3,500.000 $2,725.000 $3,000.000 $2,590.240 $5,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $1,089.590 $483.500 $800.000 $650.000 $800.000 $725.000 $750.000 $1,200.000 $898.160 $850.000 $729.750 $900.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $951.450 $320.500 $450.000 $500.000 $500.000 $600.000 $600.000 $1,200.000 $1,073.650 $1,000.000 $666.750 $900.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 242.000 $17.220 $8.500 $9.000 $7.050 $8.000 $9.000 $8.000 $7.000 $8.720 $8.000 $8.400 $10.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 16.000 $375.000 $194.000 $225.000 $200.000 $230.000 $260.000 $220.000 $200.000 $239.800 $200.000 $231.000 $275.000
REFL PAV MRK TY I(W)(BIKE SYML)(100MIL)
EA 6.000 $390.480 $325.000 $260.000 $252.000 $300.000 $300.000 $250.000 $252.000 $272.500 $300.000 $262.500 $325.000
REFL PAV MRK TY I (Y)4"(DOT)(090MIL)
LF 6,185.000 $1.200 $1.250 $1.250 $1.550 $1.800 $1.450 $1.200 $1.550 $1.308 $1.750 $1.260 $1.500
RE PROFILE PM TY I(W)4"(SLD)(090MIL)
LF 12,956.000 $1.470 $1.250 $1.100 $1.250 $1.500 $1.190 $1.000 $1.250 $1.090 $1.250 $1.050 $1.200
RE PROFILE PM TY I(Y)4"(SLD)(090MIL)
LF 387.000 $1.640 $1.500 $1.000 $1.250 $1.500 $1.190 $1.000 $1.250 $1.090 $1.250 $1.050 $1.200
PAVEMENT SLER 4"
LF 19,528.000 $0.860 $1.500 $0.250 $0.140 $0.200 $0.270 $0.200 $0.140 $0.218 $0.150 $0.210 $0.250
PAVEMENT SLER 24"
LF 242.000 $3.960 $1.500 $3.100 $1.450 $1.700 $5.000 $1.000 $1.450 $3.270 $1.500 $3.150 $3.750
PAVEMENT SLER (WORD)
EA 16.000 $115.280 $32.500 $126.000 $34.000 $40.000 $150.000 $1.000 $34.000 $136.250 $35.000 $131.250 $150.000
PAVEMENT SLER (BIKE SYMBOL)
EA 6.000 $113.190 $26.000 $110.000 $28.000 $32.000 $120.000 $1.000 $28.000 $109.000 $30.000 $105.000 $125.000
PAV SURF PREP FOR MRK (6")
LF 19,528.000 $0.810 $1.500 $0.150 $0.020 $0.050 $0.170 $0.200 $0.020 $0.109 $0.020 $0.110 $0.120
PAV SURF PREP FOR MRK (24")
LF 242.000 $11.660 $1.500 $2.100 $0.500 $0.600 $2.500 $2.000 $0.500 $2.180 $0.500 $2.100 $2.500
PAV SURF PREP FOR MRK (WORD)
EA 16.000 $60.440 $19.000 $110.000 $14.250 $16.000 $121.000 $100.000 $14.250 $109.000 $15.000 $105.000 $125.000
PAV SURF PREP FOR MRK (BIKE SYMBOL)
EA 6.000 $71.070 $16.000 $60.000 $12.250 $15.000 $64.000 $50.000 $12.500 $54.500 $13.000 $52.500 $65.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 6.000 $7,498.400 $616.250 $9,500.000 $8,500.000 $14,000.000 $10,240.000 $9,000.000 $14,000.000 $11,970.380 $12,000.000 $9,417.450 $13,500.000
POST AND CABLE FENCE (NEW CONC ANCHOR)
EA 18.000 $156.710 $162.500 $200.000 $200.000 $200.000 $500.000 $180.000 $1,100.000 $218.000 $500.000 $1,312.500 $1,500.000
REP STL BRIDGE MEMBER (TRUSS VERTICAL)
EA 1.000 $500.000 $1,560.000 $6,000.000 $600.000 $1,000.000 $900.000 $2,000.000 $1,600.000 $654.000 $800.000 $6,300.000 $55,000.000
REP STL BRIDGE MEMBER (BATTEN PLATE)
EA 2.000 $4,562.500 $2,080.000 $1,200.000 $1,000.000 $1,000.000 $1,400.000 $1,500.000 $2,000.000 $1,090.000 $1,500.000 $8,400.000 $6,500.000
REP STL BRIDGE MEMBER (FLOORBEAM)
EA 1.000 $500.000 $2,080.000 $1,200.000 $1,000.000 $1,000.000 $1,400.000 $3,500.000 $2,000.000 $1,090.000 $1,500.000 $6,300.000 $40,000.000
REP STL BRIDGE MEMBER(REPL RIVET/BOLT)
EA 121.000 $143.380 $266.500 $220.000 $200.000 $100.000 $241.000 $5.000 $225.000 $218.000 $225.000 $205.000 $400.000
RELOCATE EXISTING TRUSS BRIDGE
LS 1.000 $60,000.000 $25,000.000 $50,000.000 $150,000.000 $160,000.000 $70,000.000 $40,000.000 $150,000.000 $21,800.000 $10,000.000 $417,246.740 $450,000.000
SHADE STRUCTURE
EA 1.000 $30,000.000 $50,000.000 $30,000.000 $30,000.000 $60,000.000 $25,000.000 $50,000.000 $75,000.000 $27,250.000 $30,000.000 $60,000.000 $85,000.000
Totals: $2,967,038.960 $2,744,601.850 $2,763,803.700 $2,827,010.800 $2,877,672.100 $2,896,711.822 $2,965,581.200 $3,084,026.430 $3,159,689.901 $3,200,554.760 $4,284,535.600 $5,498,727.460
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $29,549.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $59,098.00
Total: $88,647.00