Bid Cobra

GRAYSON CALF CREEK LN (0901-19-222)

Items: 63

County: GRAYSON
Length: 0.3170 MILES
Highway: CALF CREEK LN
District: PARIS
Control Number: 0901-19-222
DBE Goal: 0.0%
Project: BR 2025(523)
Guaranty: $63,000.00
Time: 255 WORKING DAYS
Engineer's Estimate: $2,871,854.72
Date: 10/09/2025 (8 months ago)
Contract Number: 10253222
Type: BRIDGE REPLACEMENT
Project ID: A00195167
Contract Type: Federal
Project Description: BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
TOMMY HENDERSON
BRYAN ESMAILIDOKI
MELESE NORCHA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$2,871,854.72
$2,742,957.97
Over/Under Est: -4.49% -$128,896.75
Over/Under Est: -0.82% -$23,663.46
Amt Left: 3.84% $105,233.29
Over/Under Est: -0.19% -$5,497.72
Amt Left: 4.5% $123,399.03
Delta: -0.64% -$18,165.74
$2,899,946.66
Over/Under Est: 0.98% $28,091.94
Amt Left: 5.72% $156,988.69
Delta: -1.17% -$33,589.66
$2,914,794.44
Over/Under Est: 1.5% $42,939.72
Amt Left: 6.26% $171,836.47
Delta: -0.51% -$14,847.78
Over/Under Est: 10.01% $287,334.68
Amt Left: 15.17% $416,231.43
Delta: -8.38% -$244,394.96
Over/Under Est: 11.27% $323,712.23
Amt Left: 16.5% $452,608.98
Delta: -1.15% -$36,377.55
Over/Under Est: 15.59% $447,578.90
Amt Left: 21.02% $576,475.65
Delta: -3.88% -$123,866.67
Over/Under Est: 45.25% $1,299,563.04
Amt Left: 52.08% $1,428,459.79
Delta: -25.67% -$851,984.14
Over/Under Est: 65.78% $1,889,039.08
Amt Left: 73.57% $2,017,935.83
Delta: -14.13% -$589,476.04
Subcontractor Percentage Amount
PEACHTREE CONSTRUCTION, LTD. 5.90% $161,834.52
SOUTHERN CROSS CONTRACTORS, LLC 4.64% $127,273.25
DIAMOND ELITE BARRICADES, LLC 0.89% $24,412.33
STRIPING TECHNOLOGY, L.P. 0.50% $13,714.79
Total: 11.93% $327,234.89

Bid Items & Bid Tabulations

63 Total 0 of 63
GRAYSON  |  CALF CREEK LN  |  PARIS  |  0901-19-222  |  10/09/2025  |  $2,871,854.72  |  BR 2025(523)  |  BRIDGE REPL  |  255 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
TEXAS STEEL INDUSTRIAL PLACING, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
SKYLINE BRIDGE LLC
THK CONSTRUCTION LLC
INDUS ROAD & BRIDGE, INC.
EAST TEXAS BRIDGE, INC.
GREY SKY CONSTRUCTION LLC
ED BELL CONSTRUCTION COMPANY
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
PREPARING ROW
STA 17.520 $2,800.000 $2,500.000 $3,000.000 $5,800.000 $2,000.000 $1,600.000 $5,219.690 $6,500.000 $16,406.000 $7,500.000 $2,000.000
EXCAV (ROADWAY)
CY 823.000 $25.000 $30.000 $20.000 $15.000 $17.000 $18.000 $42.000 $25.000 $20.000 $50.000 $150.000
EXCAV (CHANNEL)
CY 2,129.000 $25.000 $30.000 $20.000 $15.000 $15.000 $18.000 $37.000 $25.000 $30.000 $50.000 $150.000
EMBANK (FNL)(OC)(TY B)
CY 1,305.000 $23.000 $30.000 $20.000 $20.000 $35.000 $18.000 $26.000 $32.000 $50.000 $50.000 $35.000
BROADCAST SEED (TEMP_WARM)
SY 2,346.500 $0.750 $0.250 $1.000 $0.500 $1.250 $0.280 $0.250 $0.900 $2.000 $0.270 $2.000
BROADCAST SEED (TEMP_COOL)
SY 2,346.500 $0.750 $0.240 $1.000 $0.500 $1.250 $0.260 $0.250 $0.900 $2.000 $0.260 $2.000
HYDRO MULCH SEED (PERM_URBAN_CLAY)
SY 1,872.000 $1.000 $0.480 $1.500 $2.000 $1.900 $0.520 $0.500 $1.200 $2.000 $0.550 $20.000
STRAW/HAY MLCH SEED(PERM_RURAL_CLAY)
SY 2,821.000 $0.500 $0.480 $1.500 $2.000 $1.900 $0.520 $0.500 $2.000 $2.000 $0.550 $20.000
VEGETATIVE WATERING
TGL 30.500 $40.000 $250.000 $10.000 $1.000 $1.000 $10.000 $25.000 $40.000 $50.000 $275.000 $250.000
FL BS (CMP IN PLC)(TY D GR 4) (4")
SY 1,506.000 $35.000 $18.000 $30.000 $50.000 $35.000 $28.000 $19.490 $22.000 $20.000 $18.880 $10.000
REWORK BS MTL (TY A)(10")(ORD COMP)
SY 814.000 $10.000 $9.640 $10.000 $15.000 $25.000 $20.000 $12.000 $12.000 $15.000 $12.000 $10.000
REWORK BS MTL (TY B)(6")(ORD COMP)
SY 2,134.000 $10.000 $11.000 $10.000 $10.000 $18.000 $20.000 $9.000 $12.000 $10.000 $15.000 $10.000
D-GR HMA TY-C SAC-A PG64-22(EXEMPT)
TON 590.000 $185.000 $274.000 $200.000 $275.000 $300.000 $250.000 $290.000 $290.000 $165.000 $300.000 $250.000
CEM STABIL BKFL
CY 266.000 $275.000 $350.000 $220.000 $275.000 $290.000 $300.000 $245.000 $275.000 $350.000 $400.000 $500.000
DRILL SHAFT (24 IN)
LF 813.000 $180.000 $189.000 $200.000 $140.000 $200.000 $159.060 $145.000 $165.000 $225.000 $180.000 $425.000
DRILL SHAFT (30 IN)
LF 240.000 $260.000 $190.000 $250.000 $200.000 $300.000 $265.830 $235.000 $265.000 $250.000 $275.000 $425.000
DRILL SHAFT (36 IN)
LF 445.000 $260.000 $190.000 $260.000 $215.000 $300.000 $274.940 $245.000 $220.000 $300.000 $295.000 $425.000
CL C CONC (ABUT)
CY 121.700 $1,200.000 $1,168.000 $1,300.000 $1,300.000 $1,200.000 $1,100.000 $1,220.000 $1,350.000 $1,500.000 $2,500.000 $850.000
CL C CONC (CAP)
CY 27.000 $1,470.000 $1,500.000 $1,850.000 $2,800.000 $1,800.000 $1,500.000 $1,620.000 $1,400.000 $1,500.000 $3,000.000 $1,200.000
CL C CONC (COLUMN)
CY 14.700 $1,300.000 $1,000.000 $1,850.000 $2,500.000 $2,000.000 $2,000.000 $2,850.000 $1,400.000 $1,500.000 $3,500.000 $850.000
CL C CONC (RAIL FOUNDATION)
CY 8.400 $760.000 $1,100.000 $1,200.000 $1,000.000 $1,900.000 $1,000.000 $650.000 $1,000.000 $1,500.000 $1,100.000 $750.000
REINF CONC SLAB
SF 8,600.000 $30.000 $23.000 $23.000 $26.000 $26.000 $32.000 $29.000 $37.000 $25.000 $40.000 $50.000
REINF CONC SLAB (BOX BEAM)
SF 1,701.000 $30.000 $35.000 $23.000 $22.000 $30.000 $25.000 $31.000 $30.000 $25.000 $35.000 $50.000
SHEAR KEY
CY 8.600 $792.320 $250.000 $600.000 $800.000 $900.000 $800.000 $850.000 $800.000 $1,500.000 $500.000 $500.000
PRESTR CONC SLAB BEAM (5SB15)
LF 984.920 $325.000 $244.000 $225.000 $310.000 $260.000 $293.890 $378.000 $300.000 $250.000 $400.000 $310.000
PRESTR CONC BOX BEAM (4B20)
LF 258.000 $345.000 $402.000 $300.000 $320.000 $400.000 $295.580 $375.000 $360.000 $250.000 $700.000 $360.000
PRESTR CONC BOX BEAM (5B20)
LF 129.000 $320.000 $402.000 $500.000 $320.000 $525.000 $253.000 $465.000 $360.000 $250.000 $660.000 $360.000
PRESTR CONC X-BEAM (5XB28)
LF 422.110 $350.000 $400.000 $500.000 $380.000 $400.000 $288.770 $400.000 $435.000 $250.000 $580.000 $660.000
RIPRAP (MOW STRIP)(4 IN)
CY 28.000 $600.000 $550.000 $700.000 $750.000 $750.000 $750.000 $500.000 $800.000 $550.000 $1,000.000 $800.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,846.000 $175.000 $180.000 $175.000 $190.000 $150.000 $170.000 $135.000 $190.000 $150.000 $250.000 $300.000
RAIL (TY T223)
LF 270.000 $210.000 $180.000 $150.000 $75.000 $180.000 $200.000 $140.000 $175.000 $150.000 $175.000 $250.000
RAIL (TY T631LS)
LF 610.000 $77.000 $64.000 $80.000 $70.000 $75.000 $60.760 $70.000 $75.000 $150.000 $75.000 $150.000
RC PIPE (CL III)(12 IN)
LF 20.000 $75.000 $50.000 $100.000 $60.000 $100.000 $80.000 $70.000 $75.000 $85.000 $100.000 $150.000
RC PIPE (CL III)(18 IN)
LF 72.000 $80.000 $60.000 $200.000 $60.000 $75.000 $80.000 $100.000 $80.000 $100.000 $115.000 $150.000
RC PIPE (CL III)(36 IN)
LF 20.000 $225.000 $188.000 $300.000 $150.000 $215.000 $150.000 $190.000 $200.000 $150.000 $180.000 $300.000
SET (TY II) (12 IN) (RCP) (6: 1) (P)
EA 2.000 $1,200.000 $685.000 $1,200.000 $800.000 $600.000 $1,000.000 $2,300.000 $850.000 $1,500.000 $600.000 $3,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 8.000 $863.000 $995.000 $1,250.000 $950.000 $1,200.000 $1,000.000 $2,500.000 $1,000.000 $1,850.000 $700.000 $3,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 2.000 $4,500.000 $5,945.000 $4,000.000 $5,000.000 $7,500.000 $5,000.000 $4,600.000 $6,500.000 $3,250.000 $8,000.000 $7,500.000
REMOV STR (PIPE)
LF 44.000 $25.000 $50.000 $30.000 $25.000 $30.000 $20.000 $33.000 $20.000 $50.000 $25.000 $10.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 4.000 $20,000.000 $20,000.000 $30,000.000 $20,000.000 $15,000.000 $63,750.000 $25,000.000 $20,000.000 $35,000.000 $25,000.000 $53,000.000
MOBILIZATION
LS 1.000 $261,059.520 $200,000.000 $284,562.760 $250,000.000 $200,000.000 $260,000.000 $310,007.070 $295,000.000 $280,000.000 $400,000.000 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $1,800.000 $2,500.000 $1,000.000 $2,000.000 $2,500.000 $1,649.200 $7,500.000 $4,000.000 $12,500.000 $2,500.000 $5,000.000
TMA (STATIONARY)
DAY 1.000 $500.000 $1,000.000 $1.000 $300.000 $1,000.000 $400.000 $400.000 $500.000 $250.000 $500.000 $300.000
TMA (MOBILE OPERATION)
HR 8.000 $125.000 $100.000 $1.000 $200.000 $50.000 $100.000 $230.000 $150.000 $55.000 $125.000 $325.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 340.000 $50.000 $52.000 $45.000 $1.000 $55.000 $56.420 $55.000 $57.000 $30.000 $86.400 $55.000
ROCK FILTER DAMS (REMOVE)
LF 340.000 $20.000 $10.000 $20.000 $1.000 $10.000 $16.280 $15.000 $22.000 $15.000 $43.200 $20.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 312.000 $30.000 $10.000 $40.000 $1.000 $10.000 $1.000 $40.000 $45.000 $50.000 $35.640 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 312.000 $10.000 $10.000 $15.000 $1.000 $1.000 $1.000 $12.000 $15.000 $20.000 $19.440 $25.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,715.000 $5.000 $3.500 $4.000 $1.000 $4.000 $3.800 $4.000 $5.500 $4.000 $3.510 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,715.000 $1.500 $1.000 $1.000 $1.000 $1.500 $1.200 $1.200 $1.100 $2.000 $1.890 $2.000
DRIVEWAYS (BASE)
SY 168.000 $40.000 $25.000 $62.000 $35.000 $80.000 $40.000 $80.000 $25.000 $30.000 $75.000 $25.000
MTL W-BEAM GD FEN (STEEL POST)
LF 350.000 $35.000 $30.000 $32.000 $28.000 $32.000 $28.210 $28.000 $30.000 $35.000 $28.070 $32.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,250.000 $2,000.000 $2,000.000 $1,600.000 $1,750.000 $1,736.000 $1,900.000 $1,685.000 $1,850.000 $3,236.970 $2,200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 16.000 $3,250.000 $2,925.000 $3,000.000 $3,000.000 $3,250.000 $17.360 $3,100.000 $3,200.000 $3,850.000 $3,214.080 $5,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 16.000 $800.000 $650.000 $650.000 $1,000.000 $750.000 $651.000 $650.000 $660.000 $1,150.000 $685.800 $1,000.000
IN SM RD SN SUP&AM (RAIL MOUNT)
EA 3.000 $1,200.000 $3,950.000 $500.000 $1,500.000 $6,800.000 $6,401.500 $4,000.000 $6,500.000 $1,500.000 $4,286.520 $7,500.000
REMOVE SM RD SN SUP&AM
EA 8.000 $100.000 $100.000 $100.000 $150.000 $200.000 $250.000 $80.000 $115.000 $500.000 $85.320 $200.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 38.000 $45.000 $45.000 $30.000 $30.000 $50.000 $33.640 $26.000 $30.000 $100.000 $27.000 $40.000
PAVEMENT SLER 6"
LF 400.000 $0.800 $2.500 $2.000 $1.000 $2.000 $2.720 $2.600 $3.000 $3.000 $2.700 $3.000
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 862.000 $1.250 $4.000 $3.000 $5.000 $6.250 $4.340 $4.200 $4.500 $3.000 $4.320 $5.000
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 2,000.000 $1.250 $4.000 $3.000 $7.000 $6.250 $4.340 $4.200 $4.500 $3.000 $4.320 $5.000
REFL PAV MRKR TY II-A-A
EA 25.000 $7.500 $10.000 $15.000 $10.000 $20.000 $10.850 $11.000 $11.000 $6.000 $10.800 $15.000
PAV SURF PREP FOR MRK (6")
LF 400.000 $1.000 $2.500 $3.000 $1.000 $1.000 $2.720 $2.600 $2.750 $3.000 $2.700 $3.000
Totals: $2,871,854.722 $2,742,957.965 $2,848,191.260 $2,866,357.000 $2,899,946.650 $2,914,794.444 $3,159,189.389 $3,195,566.950 $3,319,433.620 $4,171,417.755 $4,760,893.800
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $25,556.92
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $51,113.84
Total: $76,670.76