GRAYSON PRESCOTT RD (0901-19-221)
Items: 39
County: GRAYSON
Length: 1.6200 MILES
Highway: PRESCOTT RD
District: PARIS
Control Number: 0901-19-221
DBE Goal: 4.0%
Project: BR 2B24(128)
Guaranty: $54,000.00
Time: 350 WORKING DAYS
Engineer's Estimate: $2,710,839.99
Date: 07/01/2025 (11 months ago)
Contract Number: 7253017
Type: BRIDGE REPLACEMENT
Project ID: A00190867
Contract Type: Federal
Project Description: BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
AARON BLOOM
MELESE NORCHA
GRAYSON PRESCOTT RD (0901-19-221)
Project Name: N/A
Project: BR 2B24(128)
Length: 0.0710 MILES
Project Type: CONSTRUCTION
Limits From: AT DRAW
Limits To: .
Project Description: BRIDGE REPLACEMENT
FANNIN COUNTY ROAD 2410 (0901-32-111)
Project Name: BRIDGE REPLACEMENT TANYARD CREEK
Project: BR 2023(480)
Length: 0.6640 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: AT TANYARD CREEK
Limits To: FANNIN CR 2410
Project Description: REPLACE BRIDGE & APPROACHES
FANNIN COUNTY ROAD 3040 (0901-32-113)
Project Name: REPLACE BRIDGE AT POLECAT CREEK
Project: BR 2024(713)
Length: 0.0720 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: CR 3040
Limits To: AT POLECAT CREEK
Project Description: REPLACE BRIDGE
FANNIN CR 3805 (0901-32-118)
Project Name: CR 3805 BRIDGE REPLACEMENT
Project: BR 2B24(058)
Length: 0.6640 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: AT SPRING CREEK
Limits To: .
Project Description: BRIDGE REPLACEMENT
FANNIN COUNTY ROAD 2905 (0901-32-114)
Project Name: REPLACE BRIDGE AT SLOANS CREEK
Project: BR 2024(153)
Length: 0.0810 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: CR 2905
Limits To: AT SLOANS CREEK
Project Description: REPLACE BRIDGE
FANNIN COUNTY ROAD 2105 (0901-32-116)
Project Name: CR 2105 BRIDGE REPLACE
Project: BR 2024(822)
Length: 0.0680 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: AT ROBERT SPRINGS BRANCH TRIB
Limits To: .
Project Description: BRIDGE REPLACEMENT
Bidders (11)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,710,839.99 | |||
| $2,294,026.67 |
-15.38%
-$416,813.32
|
|||
| $2,427,097.78 |
-10.47%
-$283,742.21
|
5.8%
$133,071.11
|
||
| $2,459,769.21 |
-9.26%
-$251,070.78
|
7.22%
$165,742.54
|
-1.35%
-$32,671.43
|
|
| $2,473,129.40 |
-8.77%
-$237,710.59
|
7.81%
$179,102.73
|
-0.54%
-$13,360.19
|
|
| $2,605,424.49 |
-3.89%
-$105,415.50
|
13.57%
$311,397.82
|
-5.35%
-$132,295.09
|
|
| $2,695,837.13 |
-0.55%
-$15,002.86
|
17.52%
$401,810.46
|
-3.47%
-$90,412.64
|
|
| $2,768,435.65 |
2.12%
$57,595.66
|
20.68%
$474,408.98
|
-2.69%
-$72,598.52
|
|
| $2,968,415.70 |
9.5%
$257,575.71
|
29.4%
$674,389.03
|
-7.22%
-$199,980.05
|
|
| $3,037,219.04 |
12.04%
$326,379.05
|
32.4%
$743,192.37
|
-2.32%
-$68,803.34
|
|
| $3,400,910.00 |
25.46%
$690,070.01
|
48.25%
$1,106,883.33
|
-11.97%
-$363,690.96
|
|
| $6,945,676.88 |
156.22%
$4,234,836.89
|
202.77%
$4,651,650.21
|
-104.23%
-$3,544,766.88
|
E
Engineer's Estimate
$2,710,839.99
1
Awarded
$2,294,026.67
Over/Under Est:
-15.38%
-$416,813.32
$2,427,097.78
Over/Under Est:
-10.47%
-$283,742.21
Amt Left:
5.8%
$133,071.11
$2,459,769.21
Over/Under Est:
-9.26%
-$251,070.78
Amt Left:
7.22%
$165,742.54
Delta:
-1.35%
-$32,671.43
$2,473,129.40
Over/Under Est:
-8.77%
-$237,710.59
Amt Left:
7.81%
$179,102.73
Delta:
-0.54%
-$13,360.19
$2,605,424.49
Over/Under Est:
-3.89%
-$105,415.50
Amt Left:
13.57%
$311,397.82
Delta:
-5.35%
-$132,295.09
$2,695,837.13
Over/Under Est:
-0.55%
-$15,002.86
Amt Left:
17.52%
$401,810.46
Delta:
-3.47%
-$90,412.64
$2,768,435.65
Over/Under Est:
2.12%
$57,595.66
Amt Left:
20.68%
$474,408.98
Delta:
-2.69%
-$72,598.52
$2,968,415.70
Over/Under Est:
9.5%
$257,575.71
Amt Left:
29.4%
$674,389.03
Delta:
-7.22%
-$199,980.05
$3,037,219.04
Over/Under Est:
12.04%
$326,379.05
Amt Left:
32.4%
$743,192.37
Delta:
-2.32%
-$68,803.34
$3,400,910.00
Over/Under Est:
25.46%
$690,070.01
Amt Left:
48.25%
$1,106,883.33
Delta:
-11.97%
-$363,690.96
$6,945,676.88
Over/Under Est:
156.22%
$4,234,836.89
Amt Left:
202.77%
$4,651,650.21
Delta:
-104.23%
-$3,544,766.88
| Subcontractor | Percentage | Amount |
|---|---|---|
| HODGES AND SON CONSTRUCTION COMPANY, INC. | 11.47% | $263,124.86 |
| DUSTIN ALLEN, INC. | 5.46% | $125,253.86 |
| WITHERS CONSTRUCTION, LLC | 2.92% | $66,985.58 |
| USA SWPPP INSPECTIONS, INC.DBA USA EROSION | 1.72% | $39,457.26 |
| DIAMOND ELITE BARRICADES, LLC | 1.39% | $31,886.97 |
| TORO BRAVO CONSTRUCTION, LLC | 0.00% | $0.00 |
| Total: | 22.96% | $526,708.53 |
Bid Items & Bid Tabulations
39
Total
0 of 39
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $52,262.26 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $26,131.13 |
| Total: | $78,393.39 |